This Justification and Approval (J&A) document supports a sole-source contract for Xytech software maintenance and support for the Library of Congress's National Library Service for the Blind and Print Disabled (NLS). The Library seeks to continue maintenance and support for its existing Xytech Mediapulse software, which is currently used in its Production Information Control System 2 (PICS2). Fabric Data (Xytech Systems LLC) is the sole owner of the Xytech source code and trademark, making them the only vendor capable of providing ongoing maintenance, updates, and support for the software licenses owned by the Library.

The contract is for a three-year period from January 31, 2026, to January 30, 2029, with Fabric Data as the exclusive contractor. The Library justifies the sole-source procurement by emphasizing that Xytech is an essential component of their technical architecture, and no alternative sources exist for maintaining the software. The total contract value is over $250,000, and the Library will publish an advance notice on SAM.gov for 15 days before award. The contracting officer has determined the pricing to be fair and reasonable based on historical government prices and an independent government estimate, and considers this action to represent the best value given Xytech's unique position as the sole software provider.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Justification and Approval For Other than Full and Open Competition

Plan ID Number: 2026-CIO-0164

Form Updated 4/14/2023

Justification & Approval For Other than Full and Open Competition

As a legislative branch agency, the Library is subject to the competition and advertising requirements of 41 U.S.C. § 6101. Like the Competition in Contracting Act and the FAR, 41 U.S.C. § 6101 does not require competition when a contracting officer certifies that only one source or brand-name item is available, when dictated by public exigency, or when otherwise authorized by law.

This document sets forth the justification and approval for award of a contract or order by means providing for other than full and open competition per 41 U.S.C. § 6101, LCR 7-210, and, as applicable, FAR 6.302, FAR 13.106-1, FAR 8.405, and FAR 16.505. Contracting without competition shall not be justified on the basis of a lack of advance planning or concerns related to availability of funds.

This form shall be used to support instances where competition will be limited to a single source, a limited number of sources, including where a brand name product is required.

Part 1 – Identification

1. Contracting Agency and Activity: Library of Congress, Library Collections and Services Group (LCSG), National Library Service for the Blind and Prints Disabled (NLS)

2. Nature of Action Being Approved

Contract (or modification) LoC or Leg Branch Order (or modification) GSA Schedule or GWAC:

Other:

Plan ID Number: 2026-CIO-0164 Contractor (or Brand Name): Fabric Data (Xytech Systems LLC)

Period of Performance: 01/31/2026 – 01/30/2029

3. Description of Supplies or Services Required to Meet Library Needs

The Library requires the following supplies or services:

The Library of Congress (The Library) National Library Service for the Blind and Print Disabled (NLS) currently uses commercial configurable and scalable IT application software that manages the production and quality assurance of multimedia digital materials.

NLS book production systems are used by Library staff and certain authorized 3rd party producers within the United States of America.

The contractor shall provide The Library with maintenance and support to operate its perpetual Xytech software, access to Xytech's Support help desk, and access to all standard updates for the Xytech software licenses currently owned by NLS. Xytech software is owned by The Library in perpetuity.

Plan ID Number: 2026-CIO-0164

Form Updated 4/14/2023

Part 2 – Program Office Justification & Approval

4. Authority for Contracting Without Competition Over $250,000 For this requirement over $250,000, under FAR part 6, the basis for contracting without providing for full and open competition is:

There is only one responsible source and no other supplies or services will satisfy Library requirements.

41 U.S.C. § 6101(b)(2)(C); FAR 6.302-1.

Library’s minimum needs can only be satisfied by contractor’s unique capabilities or products. FAR 6.302-1(b)(1).

Source controls copyrights, patents, raw materials, or secret processes cannot be acquired otherwise, or similar circumstances. FAR 6.302- 1(b)(2).

Other exception identified in FAR 6.302-1:

There is such unusual & compelling urgency that the Government would be seriously injured if competition is not limited.

41 U.S.C. § 6101(b)(2)(B); FAR 6.302-2. Option years are not permitted.

Source is expressly authorized or required by statute (e.g., AbilityOne, UNICOR, GPO, GSA Public Buildings Service, Appropriations Act, etc.) per 41 U.S.C. § 6101(b)(1) and FAR 6.302-5:

Other basis authorized in 41 U.S.C. § 6101(b) or FAR part 6.302:

Library’s needs can only be satisfied by a brand-name product or item which is essential to the Government’s requirement. FAR 6.302-1(c).

The Product is listed on the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable IT Standard Data Sheet)

Up to and including $250,000 For this requirement up to $250,000, using simplified acquisition procedures under FAR part 13, the basis for contracting without providing for full and open competition is:

Only one responsible source is reasonably available to meet Library requirements. 41 U.S.C. § 6101(b); FAR 13.106-1.

Product or service is reasonably available from only one source.

Source controls copyrights, patents or other exclusive licensing arrangements.

Urgent circumstances; only one source can reasonably deliver by required date. Option years are not permitted.

Source is expressly authorized or required by statute:

Library’s needs can only be satisfied by a brand-name product The Product is listed the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable IT Standard Data Sheet)

GSA Schedule Order For this GSA schedule order under FAR part 8, the basis for not competing among GSA schedule-holders and/or specifying a brand name product or item is:

An urgent and compelling need exists, and following GSA procedures would result in unacceptable delays.

FAR 8.405-6(a)(1)(i)(A).

Only one GSA source is capable of fulfilling the requirement at the level of quality required because the supplies or services are unique or highly specialized. FAR 8.405-6(a)(1)(i)(B).

In the interest of economy and efficiency, the new work is a logical follow-on to an original order that was placed competitively among GSA schedule-holders (i.e., the original order was not sole-source or limited-source.) FAR 8.405-6(a)(1)(i)(C).

Library’s needs can only be satisfied by a brand-name product The Product is listed on the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable IT Standard Data Sheet)

Order Under Multiple Award Indefinite-Delivery Contract or GWAC For this order under FAR subpart 16.5, the basis for contracting without providing for full and open competition is:

The need is so urgent fair opportunity would result in unacceptable delays. 41 U.S.C. § 6101(b)(2)(C) and FAR 16.505(b)(2)(i)(A).

The Library’s minimum needs can only be satisfied by contractor’s unique capabilities or products. 41 U.S.C. § 6101(b)(1) and FAR

16.505(b)(2)(i)(B).

A logical follow-on order in the interest of economy and efficiency. 41 U.S.C. § 6101(b)(1) and FAR 16.505(b)(i)(2)(C).

To satisfy a minimum guarantee. 41 U.S.C. § 6101(b)(1) and FAR 16.505(b)(2)(D).

Authorized or required by statute. 41 U.S.C. § 6101(b)(1) and FAR 16.505(b)(2)(E).

The Library’s minimum needs can only be satisfied by a brand-name product or item which is essential to the Government’s requirement. 41 U.S.C. § 6101(b)(2)(B) and FAR 16.505(a)(4)(i).

The Product is listed on the Library of Congress Enterprise Architecture Repository (LCEAR) database (Attach applicable IT Standard Data Sheet)

Plan ID Number: 2026-CIO-0164

Form Updated 4/14/2023

5. Rationale for Contracting Without Competition

We are authorized to limit competition on the basis of the citation in section 4 because:

The Library currently uses self-managed Xytech software as an essential component of The Library’s established technical architecture and Production Information Control System 2 (PICS2). Xytech licenses are owned by The Library in perpetuity. The Library is not seeking a new solution but to maintain the solution currently in place.

Fabric Data (Xytech) is the sole owner of the Xytech source code and trademark. As sole owner of the source code, Fabric Data is the only vendor able to support the needs of The Library for ongoing maintenance and support of its Xytech licenses. Due to the proprietary nature of the Xytech software, only the contractor with access to and ownership of the source code is able to perform the maintenance and updates that are indicated in this requirement. Xytech software does not have any other producers or distributors, so there are no possibilities of obtaining upgrades and maintenance on the product from any other sources.

6. Actions to Overcome Barriers to Competition Before Subsequent Contract Is Required

To increase competition, we will: Continue to evaluate the IT Architecture to determine essential levels of support and software functionality. The Library will review organizations that provide similar services on an ongoing basis and if/when appropriate, The Library will compete for this service.

7. Program Office Certification

I certify that the description of the Government’s minimum needs, schedule requirements, and technical information that provide the basis for this justification are accurate and complete.

Plan ID Number: 2026-CIO-0164

Form Updated 4/14/2023

0BPART 3 – CONTRACTING OFFICER DETERMINATIONS & CERTIFICATION

8. Efforts to Solicit from As Many Potential Sources As Practicable Unless a justification is based on FAR 6.302-2, Unusual and compelling urgency, contracting officers shall post justifications for other than full and open competition, including brand name justifications, to the Contract Opportunities website on sam.gov (or eBuy for Brand Name Justifications under FAR Part 8) prior to requesting a proposal or otherwise entering into negotiations.

Advance notice will be published in sam.gov for 15 days before a contract is awarded. FAR 5.203(a).

Advance or concurrent notice will be published in sam.gov for a reasonable time for commercial items FAR 5.203(a) and 12.204(b).

Advance notice will not be published because the action meets the following FAR exception:

Notice would compromise national security. FAR 5.202(a)(1).

Unusual and compelling urgency; notice period would seriously injure Government. FAR 5.202(a)(2).

Expressly authorized or required to be made through another Government agency. FAR 5.202(a)(4).

Order will be placed against an IDIQ contract awarded under FAR 16.5. FAR 5.202(a)(6).

Order will be placed against GSA schedule or other competitively-awarded contract. FAR 5.202(a)(11).

Other:

Advance notice will not be published per 41 U.S.C. § 6101; see attached deviation from the FAR per LCR 7-210 § 3.A.

We made the following efforts to interest potential sources in this award: None

9. Listing of Sources That Expressed Interest in Writing

The following sources expressed interest in this award: None

10. Additional Information

The following additional information is relevant to this justification and approval: This J&A will be posted on SAM.gov for review.

11. Contracting Officer Determination that Price Is Fair and Reasonable As explained in detail below, I have determined that the prices for this contracting action are fair and reasonable based on comparison of the prices to the following (see FAR 15.404-1(b)(2)):

Historical prices paid by the Government Published competitive price lists Library’s Independent Government Estimate Prices obtained through market research Other: Prices obtained through competitive proposals

The following analysis (based on attached pricing information) supports my determination: Fair and reasonable pricing shall be determined by price analysis performed by the Contracting Officer before an award is made.

12. Contracting Officer Determination of Responsibility Checked System for Award Management (or will check in the case of competitive proposals for a brand name product)

13. Contracting Officer Determination of Best Value I have determined that this action represents the best value to the Government because: Xytech is the only source for Xytech Mediapulse software and software maintenance. Pricing will be determined fair and reasonable using one or more of the methods provided above.

Therefore, the action will represent best value to the Government.

14. Contracting Officer Certification I certify that, to the best of my knowledge and belief, this justification is accurate and complete. For those actions up to $750,000, I approve contracting without competition for this requirement.