Work List.docx

DOCX document 26 KB Posted

Attached to
Margaret Bay Restoration Road Maintenance
Solicitation number
12010920Q0059
Issued by

View the file

Other files

File Type Posted
Amendment 003.pdf PDF
Amendment 002.pdf PDF
Amendment 001.pdf PDF
Relevant Experience Evaluation Form.pdf PDF
Construction Wage Determination.pdf PDF
12010920Q0059.pdf PDF
Maps.docx DOCX document
SF24-16d Bid Bond Form.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Margaret Bay Restoration Tongass National Forest – Work List Margaret Restoration Access- Worklist

Road Number
Milepost
Description of Work

8000470

0.00
Begin reconditioning road. Place Borrow Excavation 1 ft rock cap including turnouts. Construct drivable water bar across existing ditch
0.02
Construct drivable water bar
0.14
Install log culvert
0.25
Install log culvert – with erosion control
0.32
Existing designated rock pit (left)
0.35
Construct drivable water bar
0.36
Install log culvert with erosion control
0.41
Construct drivable water bar
0.46
Install log culvert – with erosion control
0.51
Install Log Bridge 18 foot span– with erosion control
0.60
Construct drivable water bar
0.69
Construct drivable water bar
0.71
Construct drivable water bar
0.74
Construct drivable water bar
0.77
Install log culvert
0.75
Install log culvert
0.76
Construct drivable water bar
0.77
Install log culvert
0.82
Install log culvert
0.92
Construct drivable water bar
0.96
Install log culvert
0.99
Install log culvert
1.04
Construct water bar
1.09
Install log culvert
1.10
Construct drivable water bar
1.17
Install log culvert
1.23
Install log culvert
1.26
Construct drivable water bar
1.32
Install log culvert – with erosion control
1.34
Install log culvert – with erosion control
1.37
Install log culvert- with erosion control
1.39
Construct drivable water bar
1.48
Install log culvert – with erosion control
1.53
Existing intersection – place 1 ft borrow excavation as needed for turnaround
Begin Spur
0.00
Continue road reconditioning and placing 1 ft cap borrow excavation
0.10
Install log culvert – with erosion control
0.27
Construct and excavate log storage area( 100 ft. x 70 ft) Place 500 CY borrow excavation

End Road reconditioning, end borrow excavation placement