This is a bid invitation package from West Ottawa Public Schools and Fritz Wahlfield Construction for improvements to Lakeshore Elementary School located at 3765 N 168th Ave, Holland, MI 49424. The project includes various improvements across 14 bid categories including sitework, concrete, masonry, metals, general trades, roofing systems, glazing, LPDA, flooring, painting, fire protection, mechanical and electrical work. Bids are due February 20, 2025 at 10:00 AM at the West Ottawa Public Schools Administration Office, with a pre-bid walk-through scheduled for February 13, 2025 at 4:00 PM. Construction is scheduled to begin June 6, 2025 with substantial completion required by August 6, 2025.

The project includes two alternates: one for electric water coolers and related services, and another for Pine Creek Elementary improvements. A 5% bid bond is required with all bids, along with sworn familial disclosure and Iran disclosure documentation. The successful bidder will be required to provide performance, labor and material bonds. Pre-purchased equipment by the owner will be included in some bid categories for contractor installation. This is not a prevailing wage project. The bid package includes detailed scopes of work for each trade category, insurance requirements, and a comprehensive project schedule outlined in Gantt chart format.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID INVITE

INVITE DETAILS

PROJECT: Lakeshore Elementary Improvements

OWNER: West Ottawa Public Schools

A&E FIRM: GMB

BIDS DUE: February 20, 2025 @ 10:00 A.M.

PRE-BID WALK THRU: February 13, 2025 @ 4:00 P.M.

CONTACT: Fritz Wahlfield III, Ph: (616) 784.5833, Email: f3@wahlfieldconstruction.com

PROJECT DETAILS

PROJECT LOCATION: 3765 N 168th Ave, Holland, MI 49424

PROJECT DESCRIPTION: Improvements to existing Elementary School. Includes 2 Alternates

BID TRADES: Sitework, Concrete, Masonry, Metals, General Trades, Metal Roofing/Metal Panel Systems, Membrane Roofing, Aluminum Storefronts/Glazing, LPDA, Flooring, Painting, Fire Protection, Mechanical, Electrical

PROJECT SCHEDULE: Summer 2025 (See Attached Schedule)

INVITE RESPONSE

(PLEASE FILL OUT INVITE AND RETURN TO: amanda@wahlfieldconstruction.com)

Company

Contact Name Phone

Email

Please check one: ( ) We will be submitting a budget for this project.

( ) We will NOT be submitting a budget for this project mailto:f2@wahlfieldconstruction.com mailto:amanda@wahlfieldconstruction.com

00 11 13 ADVERTISEMENT FOR BIDS

BID PROPOSAL

Sealed bids, in triplicate, for West Ottawa Public Schools, Lakeshore Elementary Improvements, will be received at

West Ottawa Public Schools Administration Office, 1138 136 th Ave., Holland, MI 49424 on February 20, 2025 at

10:00 AM. Any bids received after this date and time will not be accepted or considered. All bids will be opened and read publicly. FAXED OR EMAILED BIDS WILL NOT BE ACCEPTED.

This project is not a prevailing wage project.

All bids must be accompanied by the following;

1. 5% Bid Bond/ Security

2. Sworn and Notarized Familial Disclosure

3. Iran Disclosure Act

SITE INSPECTION

A Pre-bid meeting will be Wednesday, February 13, 2025 @ 4:00 P.M. This meeting will take place at Lakeshore

Elementary School located at 3765 N 168th Ave., Holland, MI 49424. This pre-bid walk thru is highly recommended.

There will be no other time available to view the site.

BID DOCUMENTS

Bidding documents may be viewed and/or requested via the following:

GMB Architecture + Engineering 85 East Eighth St., Suite 200 Holland, MI 49423 Ph: (616) 796-0200

West Michigan Builders Exchange

678 Front St. NW, Grand Rapids, MI 49504

(616) 949-8650

Please note that vendors are responsible to review information on all drawings and specifications.

BIDDER QUALIFICATIONS

Bidders submitting a proposal for this project shall have the following qualifications:

1. At least (10) years’ experience under the current company’s name.

2. Licensed and insured to perform work in the State of Michigan.

3. Shall have financial resources to complete work under this scope

BID SECURITY

All bids are required to have a bid security or bid bond in the amount of 5% of the bid being submitted. This shall secure the Owner from loss or damage by reason in the occurrence a bid is withdrawn or failure of the successful bidder not entering into Contract with the Owner if the Bid is accepted by the Owner.

The Successful bidder will be asked to secure a Performance, Labor, and Material bond for all work under contract.

Please keep this cost separate on the bid form provided. All bonds shall be from a surety company with an ‘A’ rating.

00 41 00 BID FORM

SUBMIT IN TRIPLICATE

BID TO: West Ottawa Public Schools 1138 136 th Ave.

Holland, MI 49424

ATTENTION: Mr. Chris LaHaie, Assistant Superintendent of Business Services

BID FROM: _______________________________________________________

PROJECT: Lakeshore Elementary Improvements

The undersigned has familiarized themselves with the local conditions with the cost of the work by having examined the site conditions, and Bidding Documents prepared by GMB Architecture & Engineering (85 East Eighth St. (Suite

200), Holland, MI 49423), and hereby proposes to furnish all labor, materials, taxes, equipment, and services needed for the completion of the work category submitted. All Addendums that have been issued for this project have been recognized and included. The cost for performing work is:

Bid Category Number: _________________

Bid Category Description: ____________________________________________________________

Base Bid Amount: ____________________________________________________________ Dollars

ALLOWANCES: Base Bid includes all allowance cost(s) set forth in Section 01.2100 of the General Requirements and identified in the Instruction to Bidders.

TAXES: Base Bid includes all applicable taxes, including Michigan Sales Tax.

COST OF BONDS: Bond Cost for Performance, Labor, and Material Bond Cost. This cost must be included in the

Base Bid. Please list the cost of the bond below.

Lakeshore Elementary Improvements:

PLM Bond Amount ____________________________________________________________ Dollars

ACKNOWLEDGEMENT OF ADDENDA

The following addenda have been received and acknowledged with their execution is included in the base bid cost:

Addendum No. _____ Dated __________ Addendum No. _____ Dated __________

Addendum No. _____ Dated __________ Addendum No. _____ Dated __________

ALTERNATES (MANDATORY TO PROVIDE PRICING AS NEEDED WITH BASE BID)

The following alternates are an add to the Base Bid Cost.

Alternate No. P-1: Provide all costs associated with the provision and installation of electric water coolers including all related services.

Cost: Add/ Delete $___________________________________

Alternate No. Pine Creek Elementary: Provide all costs associated with the Pine Creek Elementary drawings attached to this Bid Package.

VOLUNTARY ALTERNATES

The following is a list of Voluntary Alternates. The owner reserves the right to accept or reject and voluntary alternates.

1. ______________________________________________________________________________

2. ______________________________________________________________________________

UNIT PRICE

1. Unit Price No. 1: NA

BID BOND

Accompanying this bid as required by the instructions to Bidders, is a bid security if the form of (Certified Check, Cashier’s Check, or Bid Bond) in the amount of:

Bid Bond Amount ____________________________________________________________ Dollars

CONSTRUCTION SCHEDULE

The undersigned acknowledges the construction schedule set in the bid documents and that they must be met.

ADDITIONAL WORK

1. There will be a fee of 10% applied to the total cost of materials purchased and work completed by a contractor's own forces. This includes both overhead and profit.

2. There will be a fee of 5% applied to the total cost of work completed by a subcontractor. This includes both overhead and profit.

CREDIT FOR WORK DELETED FROM CONTRACT

All work deleted from this contract by the Owner should be credited 100% back to the Owner.

AGREEMENT

In submitting this bid, it is understood that the Owner reserves the right to accept or reject any/all bids for any reason.

This bid is valid 60 days from the date of the opening.

Firm: _______________________________________________________________

Date: __________________

By: _____________________________________________________

Signature: ________________________________________________________

Title: ______________________________

Phone: (_______) _____________________

Email: ______________________________________________________

CONTACT INFORMATION

Please list contact information for the person(s) that should receive communication regarding THIS submitted bid, including Post-Bid Invites. (If Additional contacts should also receive communication, please attach a separate sheet listing a Name, Title, Email and Phone Number for each contact)

Name: ___________________________________________________

Title: ____________________________________________________

Email: ___________________________________________________

Phone: (________) ____________________________

FAMILIAL DISCLOSURE STATEMENT

In accordance with Section 1267 of the Revised School Code this bid must be accompanied by a sworn and notarized statement disclosing the familial relationship between the Owner or any employee of the Bidder and any member of West Ottawa Public Schools Board of Education or Superintendent of West Ottawa Public Schools.

(_____) No, there is no relationship between the Owner or any employee of the Bidder and any member of West Ottawa Public Schools Board of Education or Superintendent of West Ottawa Public Schools.

(_____) Yes, there is a relationship between the Owner or any employee of the Bidder and any member of West Ottawa Public Schools Board of Education or Superintendent of West Ottawa Public Schools. Please list the relationship below.

BIDDER BOARD OF EDUCATION MEMBER OR SUPERINTENDENT

Subscribed and sworn this _______________________ day of ___________________________________, 2025.

In the County of ______________________________ In the State of ___________________________________.

By ___________________________________________________________________________

Notary Public Signature

My Commission Expires on: ________________________________ Seal or Stamp:

AFFIDAVIT OF COMPLIANCE IRAN ECONOMICS SANCTIONS ACT

Michigan Public Act No. 517 of 2012

The undersigned, the owner, or authorized officer of the below-named company (the “Contractor”), pursuant to the compliance certification requirement provided in West Ottawa Public Schools Request for Proposal (the “RFP”), hereby certifies, represents, and warrants that the Contractor (which includes its officers, directors and employees) is not an “Iran Linked Business” within the meaning of the Iran Economic Sanctions Act, Michigan Public Act No. 517 of

2012 (the “Act”), and that in the event the Contractor is awarded a contract by the West Ottawa Public Schools as a result of the aforementioned RFP, the Contractor is not and will not become an “Iran Linked Business” at any time during the course of performing any services under the Contract.

The Contractor further acknowledges that any person who is found to have submitted a false certification is responsible for a civil penalty of not more than $250,000.00 or two (2) times the amount of the contract or proposed contract for which the false certification was made, whichever is greater, the cost of the School Districts investigation, and reasonable attorney fees, in addition to the fine. Moreover, any person who submitted a false certification shall be ineligible to bid on a request for proposal for three (3) years from the date that it is determined that the person has submitted the false certification.

Contractor: _____________________________________________________

By: _______________________________________________ Title: ____________________________________

Date: __________________________________________________________

This instrument was acknowledged before me on the __________________ day of _____________________, 2025

In the County of ______________________________ In the State of ___________________________________.

By ___________________________________________________________________________

Notary Public Signature

My Commission Expires on: ________________________________ Seal or Stamp:

REQUEST FOR INFORMATION (RFI) DURING BIDDING PHASE

Requests For Information (RFI’s) will ONLY be accepted through a completed RFI form provided on page 9 in the front ends of this project.

Pre-Bid RFI’s deadline: FEBRUARY 14, 2025 by 12:00 P.M.

Please email the completed RFI form to both:

amanda@wahlfieldconstruction.com f3@wahlfieldconstruction.com

The CM will review the RFI before submitting to the AE firm.

Any questions not submitted following this process prior to the deadline will not be answered.

REQUEST FOR INFORMATION (RFI) FORM

Project: Lakeshore Elementary Improvements Date: ________________

Deadline: FEBRUARY 14, 2025 by 12:00 P.M. Action Requested:

______ Clarification

Attn: Fritz Wahlfield III, Fritz Wahlfield Construction (CM) ______ Direction

______ Approval

Company: __________________________________________________ ______ Alternate

Contact: ___________________________________________________ ______ Other

Email: _____________________________________________________

Phone No:__________________________________________________

Reference Drawing No: __________________________ Detail No: ___________ Spec. Section: ___________

Request Information:

RFI #: _________

CM Recommendation:

By: _______________________________ Date: ________________

AE Recommendation:

By: _______________________________ Date: ________________

BID CATEGORIES INDEX

1. Sitework

2. Concrete

3. Masonry

4. Metals

5. General Trades

6. Metal Roofing/Metal Panel Systems

7. Membrane Roofing

8. Aluminum Storefronts/Glazing

9. LPDA

10. Flooring

11. Painting

12. Fire Protection

13. Mechanical

14. Electrical

BID CATEGORY NO. 01 - SITEWORK

INCLUDE:

1. Complete Sitework and related work as shown on the drawings and as specified in the following sections:

SPECIFICATION MANUAL AND FRONT ENDS

00.0110 TABLE OF CONTENTS

00.0115 LIST OF DRAWING SHEETS

00.4323 ALTERNATES FORM

00.1113 ADVERTISEMENT FOR BIDS

00.4100 BID FORM

00.4323 ALTERNATES FORM

01.0000 GENERAL REQUIREMENTS

01.0001 ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT

01.1000.0 SUMMARY

01.1000.1 ABBREVIATIONS

01.1010.1 WORK COVERED BY CONTRACT DOCUMENTS

01.1010.2 SCHEDULING

01.1010.3 CONTRACTOR USE OF PREMISES

01.1010.4 SUBSTANTIAL COMPLETION

01.2200 UNIT PRICES

01.2300 ALTERNATES

01.3000 ADMINISTRATIVE REQUIREMENTS

01.3000.1 SUBMITTALS

01.3113 INSURANCE REQUIREMENTS

01.4000 QUALITY REQUIREMENTS

01.4533 CODE REQUIRED SPECIAL INSPECTIONS

01.4100 REGULATORY REQUIREMENTS

01.4533 CODE-REQUIRED SPECIAL INSPECTIONS

01.5000 TEMPORARY FACILITIES AND CONTROLS

01.5100 TEMPORARY UTILITIES

01.5713 TEMPORARY EROSION AND SEDIMENT CONTROL

01.7329 CUTTING AND PATCHING

01.7700 CLOSE OUT PROCEDURES

01.9113 GENERAL COMMISSIONING REQUIREMENTS

01.9114 COMMISSIONING AUTHORITY RESPONSIBLITIES

02.4119 DEMOLITION

2. CONSTRUCTION DRAWINGS: CONTRACTOR IS RESPONSIBLE FOR REVIEWING ALL

CONSTRUCTION DRAWING PAGES AND BECOMING FAMILIAR WITH THE COMPLETE SET TO

SATISFY THE SCOPE OF WORK RELATED TO THE BID CATEGORY.

a. DRAWING INDEX CAN BE FOUND ON TITLE PAGE.

3. All Excavating as shown on pages C1.01, C2.02, C4.01, C4.02, C4.03, C4.04.

4. Compacting any imported soils as required to meet compaction requirements of soils for future footings, foundations, slab on grade, and/or backfill material.

5. Responsibility of the contractor to contact Miss Dig at least 36 hours prior to start of work.

6. The CM will provide a one time staking of grades, building footprint, and misc. locations.

a. Additional staking will be at the cost of the contractor.

7. Furnish and Install as shown:

a. Site demolition and site clearing as shown on C1.01

b. Standard Duty Pavement as shown on C2.01

c. Lift Pump Station Work as shown

8. Concrete or asphalt cutting to complete work in this scope.

9. Any dewatering necessary to complete this scope of work.

10. Dust control measures for all work in this Bid Category.

11. Daily clean-up at work areas.

12. Contractor to meet Project Schedule, this includes weekend work or daily overtime.

a. Project Manager/Project Foreman required to attend the following meetings:

i. Pre-Construction Kick Off

ii. Bi-Weekly Progress Meeting

iii. Any meetings required by the Local Ordinance, Architect, and/ or Civil Engineer

13. All work must be done in accordance with MIOSHA Regulations.

14. Warranties as specified.

15. Submit shop drawings to scale so they can be accurately commented on/coordinated with other trades.

16. When shop drawings are returned from the Architect to Contractor marked “Rejected” or “Revise and

Resubmit”, contractor shall reissue the second time with the revisions clouded.

BID CATEGORY NO. 02 - CONCRETE

1. Complete Concrete and related work as shown on the drawings and as specified in the following sections:

SPECIFICATION MANUAL AND FRONT ENDS

00.0110 TABLE OF CONTENTS

00.0115 LIST OF DRAWING SHEETS

00.4323 ALTERNATES FORM

00.1113 ADVERTISEMENT FOR BIDS

00.4100 BID FORM

00.4323 ALTERNATES FORM

01.0000 GENERAL REQUIREMENTS

01.0001 ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT

01.1000.0 SUMMARY

01.1000.1 ABBREVIATIONS

01.1010.1 WORK COVERED BY CONTRACT DOCUMENTS

01.1010.2 SCHEDULING

01.1010.3 CONTRACTOR USE OF PREMISES

01.1010.4 SUBSTANTIAL COMPLETION

01.2200 UNIT PRICES

01.2300 ALTERNATES

01.3000 ADMINISTRATIVE REQUIREMENTS

01.3000.1 SUBMITTALS

01.3113 INSURANCE REQUIREMENTS

01.4000 QUALITY REQUIREMENTS

01.4533 CODE REQUIRED SPECIAL INSPECTIONS

01.4100 REGULATORY REQUIREMENTS

01.4533 CODE-REQUIRED SPECIAL INSPECTIONS

01.5000 TEMPORARY FACILITIES AND CONTROLS

01.5100 TEMPORARY UTILITIES

01.5713 TEMPORARY EROSION AND SEDIMENT CONTROL

01.7329 CUTTING AND PATCHING

01.7700 CLOSE OUT PROCEDURES

01.9113 GENERAL COMMISSIONING REQUIREMENTS

01.9114 COMMISSIONING AUTHORITY RESPONSIBLITIES

02.4119 DEMOLITION

03.3000 CAST-IN-PLACE CONCRETE

07.2100 THERMAL INSULATION

07.9200 JOINT SEALANTS

SATISFY THE SCOPE OF WORK RELATED TO THE BID CATEGORY.

a. DRAWING INDEX CAN BE FOUND ON TITLE PAGE.

3. Furnish and Install all reinforcement as shown.

4. Provide Sealer and Vapor Barrier as specified.

5. Furnish and install all interior & exterior concrete MEP pads as shown.

6. Furnish and install joint sealants at all new exterior concrete paving as shown and specified.

7. Dust control measures for all work in this Bid Category.

8. Daily clean-up at work areas.

9. Contractor to meet Project Schedule, this includes weekend work or daily overtime.

a. Project Manager/Project Foreman required to attend the following meetings:

i. Pre-Construction Kick Off

ii. Bi-Weekly Progress Meeting

iii. Any meetings required by the Local Ordinance, Architect, and/ or Civil Engineer

10. All work must be done in accordance with MIOSHA Regulations.

11. Warranties as specified.

12. Submit shop drawings to scale so they can be accurately commented on/coordinated with other trades.

13. When shop drawings are returned from the Architect to Contractor marked “Rejected” or “Revise and

Resubmit”, contractor shall reissue the second time with the revisions clouded.

14. Alternate No. Pine Creek Elementary: Provide all costs associated with the Pine Creek Elementary drawings attached to this Bid Package.

BID CATEGORY NO. 03 - MASONRY

1. Complete Masonry and related work as shown on the drawings and as specified in the following sections:

SPECIFICATION MANUAL AND FRONT ENDS

00.0110 TABLE OF CONTENTS

00.0115 LIST OF DRAWING SHEETS

00.4323 ALTERNATES FORM

00.1113 ADVERTISEMENT FOR BIDS

00.4100 BID FORM

00.4323 ALTERNATES FORM

01.0000 GENERAL REQUIREMENTS

01.0001 ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT

01.1000.0 SUMMARY

01.1000.1 ABBREVIATIONS

01.1010.1 WORK COVERED BY CONTRACT DOCUMENTS

01.1010.2 SCHEDULING

01.1010.3 CONTRACTOR USE OF PREMISES

01.1010.4 SUBSTANTIAL COMPLETION

01.2200 UNIT PRICES

01.2300 ALTERNATES

01.3000 ADMINISTRATIVE REQUIREMENTS

01.3000.1 SUBMITTALS

01.3113 INSURANCE REQUIREMENTS

01.4000 QUALITY REQUIREMENTS

01.4533 CODE REQUIRED SPECIAL INSPECTIONS

01.4100 REGULATORY REQUIREMENTS

01.4533 CODE-REQUIRED SPECIAL INSPECTIONS

01.5000 TEMPORARY FACILITIES AND CONTROLS

01.5100 TEMPORARY UTILITIES

01.5713 TEMPORARY EROSION AND SEDIMENT CONTROL

01.7329 CUTTING AND PATCHING

01.7700 CLOSE OUT PROCEDURES

01.9113 GENERAL COMMISSIONING REQUIREMENTS

01.9114 COMMISSIONING AUTHORITY RESPONSIBLITIES

02.4119 DEMOLITION

04.0511 MASONTRY MORTARING AND GROUTING

04.2000 UNIT MASONRY

07.2100 THERMAL INSULATION

SATISFY THE SCOPE OF WORK RELATED TO THE BID CATEGORY.

a. DRAWING INDEX CAN BE FOUND ON TITLE PAGE.

3. All masonry reinforcement, grout fill, loose fill or cavity wall insulation, etc., as shown and/or specified.

4. Grouting solid of new hollow metal frames in masonry.

5. Clean all new masonry.

6. Furnish and Install complete Masonry as shown and specified.

7. Furnish and Install all reinforcement as shown.

8. Demo masonry openings at new louvers as called out in note 21 on pages A1.1A, A1.1B, & A1.1C.

9. All new masonry units need to be rubbed of debris and/or mortar and ready for paint.

10. Furnish and Install all necessary flashing as shown.

a. Masonry membrane flashing as shown.

11. Flashing and weep holes concealed in masonry work. Includes pre-finished flashings.

12. Cavity wall insulation, this includes all spray insulation at all new exterior walls.

13. Joint Sealants at all CMU wall CJs.

14. Fire safe-ing, fire resistant caulking, sound attenuation blankets and acoustical sealants being an integral part of the all system, where shown. Include fire safe-ing at existing masonry walls where shown. See code compliance plans for locations.

15. Install lintels as provided for new openings.

16. Provided rebar caps for all exposed rebar ends installed by this contractor.

17. This contractor is responsible for the disposal of excess masonry and masonry related items. I.e., rubble, cut blocks, mortar, etc., into concrete dumpster. Coordinate this with Construction Manager. It is the responsibility of this contractor to provide its own dumpsters as necessary.

18. All work must be done in accordance to the new Silica Regulations.

19. Furnish and install masonry toothing as required for all new openings as shown. Openings may include, but not limited to: doors, windows, louvers, chases and masonry openings for new MEP work.

20. Installation of anchor bolts at top of wall for wood blocking.

21. Dust control measures for all work in this Bid Category.

22. Daily clean-up at work areas.

23. Contractor to meet Project Schedule, this includes weekend work or daily overtime.

a. Project Manager/Project Foreman required to attend the following meetings:

i. Pre-Construction Kick Off

ii. Bi-Weekly Progress Meeting

iii. Any meetings required by the Local Ordinance, Architect, and/ or Civil Engineer

24. All work must be done in accordance with MIOSHA Regulations.

25. Warranties as specified.

26. Submit shop drawings to scale so they can be accurately commented on/coordinated with other trades.

27. When shop drawings are returned from the Architect to Contractor marked “Rejected” or “Revise and

Resubmit”, contractor shall reissue the second time with the revisions clouded.

28. Alternate No. P-1: Provide all costs associated with the provision and installation of electric water coolers including all related services.

29. Alternate No. Pine Creek Elementary: Provide all costs associated with the Pine Creek Elementary

BID CATEGORY NO. 04 - METALS

1. Complete Metals and related work as shown on the drawings and as specified in the following sections:

SPECIFICATION MANUAL AND FRONT ENDS

00.0110 TABLE OF CONTENTS

00.0115 LIST OF DRAWING SHEETS

00.4323 ALTERNATES FORM

00.1113 ADVERTISEMENT FOR BIDS

00.4100 BID FORM

00.4323 ALTERNATES FORM

01.0000 GENERAL REQUIREMENTS

01.0001 ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT

01.1000.0 SUMMARY

01.1000.1 ABBREVIATIONS

01.1010.1 WORK COVERED BY CONTRACT DOCUMENTS

01.1010.2 SCHEDULING

01.1010.3 CONTRACTOR USE OF PREMISES

01.1010.4 SUBSTANTIAL COMPLETION

01.2200 UNIT PRICES

01.2300 ALTERNATES

01.3000 ADMINISTRATIVE REQUIREMENTS

01.3000.1 SUBMITTALS

01.3113 INSURANCE REQUIREMENTS

01.4000 QUALITY REQUIREMENTS

01.4533 CODE REQUIRED SPECIAL INSPECTIONS

01.4100 REGULATORY REQUIREMENTS

01.4533 CODE-REQUIRED SPECIAL INSPECTIONS

01.5000 TEMPORARY FACILITIES AND CONTROLS

01.5100 TEMPORARY UTILITIES

01.5713 TEMPORARY EROSION AND SEDIMENT CONTROL

01.7329 CUTTING AND PATCHING

01.7700 CLOSE OUT PROCEDURES

01.9113 GENERAL COMMISSIONING REQUIREMENTS

01.9114 COMMISSIONING AUTHORITY RESPONSIBLITIES

02.4119 DEMOLITION

05.1200 STRUCTURAL STEEL FRAMING

05.3100 STEEL DECKING

SATISFY THE SCOPE OF WORK RELATED TO THE BID CATEGORY.

3. Furnish all steel lintels as shown.

4. Demolition of Existing Deck and Joist as shown for new mechanical equipment.

5. Furnish and Install Structural Steel Framing and reinforcement as shown.

6. Furnish and Install Steel Joist Framing as shown.

7. Furnish and Install Steel Decking as shown.

8. All onsite welding must be done by certified welders.

9. Provide Fire Watch for work completed above.

10. Dust control measures for all work in this Bid Category.

11. Daily clean-up at work areas.

12. Contractor to meet Project Schedule, this includes weekend work or daily overtime.

a. Project Manager/Project Foreman required to attend the following meetings:

i. Pre-Construction Kick Off

ii. Bi-Weekly Progress Meeting

iii. Any meetings required by the Local Ordinance, Architect, and/ or Civil Engineer

13. All work must be done in accordance with MIOSHA Regulations.

a. Provide lifting plan for any crane work.

14. Warranties as specified.

15. Submit shop drawings to scale so they can be accurately commented on/coordinated with other trades.

16. When shop drawings are returned from the Architect to Contractor marked “Rejected” or “Revise and

BID CATEGORY NO. 05 - GENERAL TRADES

1. Complete General Trades work as shown on the drawings and as specified in the following sections:

SPECIFICATION MANUAL AND FRONT ENDS

00.0110 TABLE OF CONTENTS

00.0115 LIST OF DRAWING SHEETS

00.4323 ALTERNATES FORM

00.1113 ADVERTISEMENT FOR BIDS

00.4100 BID FORM

00.4323 ALTERNATES FORM

01.0000 GENERAL REQUIREMENTS

01.0001 ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT

01.1000.0 SUMMARY

01.1000.1 ABBREVIATIONS

01.1010.1 WORK COVERED BY CONTRACT DOCUMENTS

01.1010.2 SCHEDULING

01.1010.3 CONTRACTOR USE OF PREMISES

01.1010.4 SUBSTANTIAL COMPLETION

01.2200 UNIT PRICES

01.2300 ALTERNATES

01.3000 ADMINISTRATIVE REQUIREMENTS

01.3000.1 SUBMITTALS

01.3113 INSURANCE REQUIREMENTS

01.4000 QUALITY REQUIREMENTS

01.4533 CODE REQUIRED SPECIAL INSPECTIONS

01.4100 REGULATORY REQUIREMENTS

01.4533 CODE-REQUIRED SPECIAL INSPECTIONS

01.5000 TEMPORARY FACILITIES AND CONTROLS

01.5100 TEMPORARY UTILITIES

01.5713 TEMPORARY EROSION AND SEDIMENT CONTROL

01.7329 CUTTING AND PATCHING

01.7700 CLOSE OUT PROCEDURES

01.9113 GENERAL COMMISSIONING REQUIREMENTS

01.9114 COMMISSIONING AUTHORITY RESPONSIBLITIES

02.4119 DEMOLITION

06.1000 ROUGH CARPENTRY

07.9200 JOINT SEALANTS

08.1113 HOLLOW METAL DOORS AND FRAMES

08.1416 FLUSH WOOD DOORS

08.7100 DOOR HARDWARE (Forthcoming)

10.2800 TOILET, BATH, AND LAUNDRY ACCESSORIES

10.5113 METAL LOCKERS

12.3200 MANUFACTURED WOOD CASEWORK

SATISFY THE SCOPE OF WORK RELATED TO THE BID CATEGORY.

a. DRAWING INDEX CAN BE FOUND ON TITLE PAGE.

3. Schedule, take delivery, inventory, and store and install all items noted as “Install Only” above. Provide a list of material received each day to the Construction Manager’s Superintendent. All items not noted are to be furnished and installed.

4. Furnish and Install Floor Protection in Areas; Corridors A101, A127, & C101. Vestibules A100, A128, C102, C109, & C112.

a. Floor protection to be One layer of Water Resistant (WR) Hardboard by Protect in area of coverage. Thickness to be 44mil.

i. This is to be installed prior to construction starting and removed at the end of the construction project as directed by the CM.

5. Furnish and Install Floor Protection in Area Gymnasium A131

a. Floor Protection to be one layer of ½” O.S.B over 6 mil clear poly plastic in area of coverage.

i. This is to be installed prior to construction starting and removed at the end of the construction project as directed by the CM.

6. Demo as shown on pages A1.1A, A1.1B, A1.1C

a. Notes 1-5, 7-9, 12 - 20, and 22.

b. Furnish and Install temporary enclosures at all new exterior openings for doors, windows, and MEP openings. Make enclosures secure from outside and shed water.

7. Furnish and erect all blocking shown on drawings or as specified in Miscellaneous Carpentry. Include all blocking not shown but incidental to your scope of work.

a. Top of wall blocking.

b. Casework and furnishings blocking as required.

c. Any doors or window bucks as needed/shown.

8. All lumber to be treated as specified.

9. Joint Sealants at all new door frames, casework, and countertops and any application where drywall meets

CMU walls.

10. Furnish and Install all Hollow Metal Door Frames and Window Frames as shown.

11. Furnish and Install all Hollow Metal and Wood Doors as shown.

12. Furnish and Install all new Door Hardware as shown.

13. Furnish and Install all new Casework and Countertops as shown.

14. Furnish and Install all new Bath Accessories as specified and shown.

15. Furnish and Install all new Toilet Partitions as specified and shown.

16. Furnish and Install new metal lockers as shown.

17. Dust control measures for all work in this Bid Category.

18. Daily clean-up at work areas.

19. Contractor to meet Project Schedule, this includes weekend work or daily overtime.

a. Project Manager/Project Foreman required to attend the following meetings:

i. Pre-Construction Kick Off

ii. Bi-Weekly Progress Meeting

iii. Any meetings required by the Local Ordinance, Architect, and/ or Civil Engineer

20. All work must be done in accordance with MIOSHA Regulations.

a. Provide lifting plan for any crane work.

21. Warranties as specified.

22. Submit shop drawings to scale so they can be accurately commented on/coordinated with other trades.

23. When shop drawings are returned from the Architect to Contractor marked “Rejected” or “Revise and

Resubmit”, contractor shall reissue the second time with the revisions clouded.

24. Alternate No. P-1: Provide all costs associated with the provision and installation of electric water coolers including all related services.

25. Alternate No. Pine Creek Elementary: Provide all costs associated with the Pine Creek Elementary

BID CATEGORY NO. 06 - METAL ROOFING/METAL PANEL SYSTEMS

1. Complete Metal Roofing/Metal Panel Systems as shown on the drawings and as specified in the following sections:

SPECIFICATION MANUAL AND FRONT ENDS

00.0110 TABLE OF CONTENTS

00.0115 LIST OF DRAWING SHEETS

00.4323 ALTERNATES FORM

00.1113 ADVERTISEMENT FOR BIDS

00.4100 BID FORM

00.4323 ALTERNATES FORM

01.0000 GENERAL REQUIREMENTS

01.0001 ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT

01.1000.0 SUMMARY

01.1000.1 ABBREVIATIONS

01.1010.1 WORK COVERED BY CONTRACT DOCUMENTS

01.1010.2 SCHEDULING

01.1010.3 CONTRACTOR USE OF PREMISES

01.1010.4 SUBSTANTIAL COMPLETION

01.2200 UNIT PRICES

01.2300 ALTERNATES

01.3000 ADMINISTRATIVE REQUIREMENTS

01.3000.1 SUBMITTALS

01.3113 INSURANCE REQUIREMENTS

01.4000 QUALITY REQUIREMENTS

01.4533 CODE REQUIRED SPECIAL INSPECTIONS

01.4100 REGULATORY REQUIREMENTS

01.4533 CODE-REQUIRED SPECIAL INSPECTIONS

01.5000 TEMPORARY FACILITIES AND CONTROLS

01.5100 TEMPORARY UTILITIES

01.5713 TEMPORARY EROSION AND SEDIMENT CONTROL

01.7329 CUTTING AND PATCHING

01.7700 CLOSE OUT PROCEDURES

01.9113 GENERAL COMMISSIONING REQUIREMENTS

01.9114 COMMISSIONING AUTHORITY RESPONSIBLITIES

02.4119 DEMOLITION

07.2500 WEATHER BARRIERS

07.4113 METAL ROOF PANELS

07.4213 METAL WALL PANELS

07.6200 SHEET METAL FLASHING AND TRIM

SATISFY THE SCOPE OF WORK RELATED TO THE BID CATEGORY.

a. DRAWING INDEX CAN BE FOUND ON TITLE PAGE.

3. Demolition of Existing Standing Seam roof as shown on pages A2.3A, A2.3B, and A2.3C.

a. Make area water sealed prior to installation of new standing seam roof system.

4. Furnish and Install all joint sealants for related work in this scope.

5. Furnish and Install complete roofing system as shown.

a. Standing Seam Metal Roofing System.

i. This includes all metal flashing and copings.

6. Furnish and Install ½” Coverboard with (2) layers of 2.6” Rigid Insulation underneath the Metal Roof System.

7. Daily clean-up at work areas.

8. Contractor to meet Project Schedule, this includes weekend work or daily overtime.

a. Project Manager/Project Foreman required to attend the following meetings:

i. Pre-Construction Kick Off

ii. Bi-Weekly Progress Meeting

iii. Any meetings required by the Local Ordinance, Architect, and/ or Civil Engineer

9. All work must be done in accordance with MIOSHA Regulations.

a. Provide lifting plan for any crane work.

10. Warranties as specified.

11. Submit shop drawings to scale so they can be accurately commented on/coordinated with other trades.

12. When shop drawings are returned from the Architect to Contractor marked “Rejected” or “Revise and

BID CATEGORY NO. 07 - MEMBRANE ROOFING

1. Complete Membrane Roofing as shown on the drawings and as specified in the following sections:

SPECIFICATION MANUAL AND FRONT ENDS

00.0110 TABLE OF CONTENTS

00.0115 LIST OF DRAWING SHEETS

00.4323 ALTERNATES FORM

00.1113 ADVERTISEMENT FOR BIDS

00.4100 BID FORM

00.4323 ALTERNATES FORM

01.0000 GENERAL REQUIREMENTS

01.0001 ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT

01.1000.0 SUMMARY

01.1000.1 ABBREVIATIONS

01.1010.1 WORK COVERED BY CONTRACT DOCUMENTS

01.1010.2 SCHEDULING

01.1010.3 CONTRACTOR USE OF PREMISES

01.1010.4 SUBSTANTIAL COMPLETION

01.2200 UNIT PRICES

01.2300 ALTERNATES

01.3000 ADMINISTRATIVE REQUIREMENTS

01.3000.1 SUBMITTALS

01.3113 INSURANCE REQUIREMENTS

01.4000 QUALITY REQUIREMENTS

01.4533 CODE REQUIRED SPECIAL INSPECTIONS

01.4100 REGULATORY REQUIREMENTS

01.4533 CODE-REQUIRED SPECIAL INSPECTIONS

01.5000 TEMPORARY FACILITIES AND CONTROLS

01.5100 TEMPORARY UTILITIES

01.5713 TEMPORARY EROSION AND SEDIMENT CONTROL

01.7329 CUTTING AND PATCHING

01.7700 CLOSE OUT PROCEDURES

01.9113 GENERAL COMMISSIONING REQUIREMENTS

01.9114 COMMISSIONING AUTHORITY RESPONSIBLITIES

02.4119 DEMOLITION

07.2100 THERMAL INSULATION

07.5300 ELASTOMERIC MEMBRANE ROOFING

SATISFY THE SCOPE OF WORK RELATED TO THE BID CATEGORY.

3. Demolition of existing Membrane roof and insulation as shown on page A2.3B.

4. Furnish and install new membrane roof system as shown on page A2.3B.

a. This includes all metal flashings and copings related to this work.

5. Furnish and Install ½” coverboard with (2) layers of 2.6” Insulation fastened to the metal deck.

a. This includes the tapered insulation as shown on the drawings.

6. Furnish and Install all joint sealants for related work in this scope.

7. Daily clean-up at work areas.

8. Contractor to Meet Project Schedule, this includes weekend work or Daily overtime.

9. Furnish and install complete roofing system as shown.

10. Tie into the existing roofing system as necessary.

11. Provide all warranties as specified.

BID CATEGORY NO. 08 - ALUMINUM STOREFRONTS & GLAZING

1. Complete Aluminum Storefronts & Glazing as shown on the drawings and as specified in the following sections:

SPECIFICATION MANUAL AND FRONT ENDS

00.0110 TABLE OF CONTENTS

00.0115 LIST OF DRAWING SHEETS

00.4323 ALTERNATES FORM

00.1113 ADVERTISEMENT FOR BIDS

00.4100 BID FORM

00.4323 ALTERNATES FORM

01.0000 GENERAL REQUIREMENTS

01.0001 ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT

01.1000.0 SUMMARY

01.1000.1 ABBREVIATIONS

01.1010.1 WORK COVERED BY CONTRACT DOCUMENTS

01.1010.2 SCHEDULING

01.1010.3 CONTRACTOR USE OF PREMISES

01.1010.4 SUBSTANTIAL COMPLETION

01.2200 UNIT PRICES

01.2300 ALTERNATES

01.3000 ADMINISTRATIVE REQUIREMENTS

01.3000.1 SUBMITTALS

01.3113 INSURANCE REQUIREMENTS

01.4000 QUALITY REQUIREMENTS

01.4533 CODE REQUIRED SPECIAL INSPECTIONS

01.4100 REGULATORY REQUIREMENTS

01.4533 CODE-REQUIRED SPECIAL INSPECTIONS

01.5000 TEMPORARY FACILITIES AND CONTROLS

01.5100 TEMPORARY UTILITIES

01.5713 TEMPORARY EROSION AND SEDIMENT CONTROL

01.7329 CUTTING AND PATCHING

01.7700 CLOSE OUT PROCEDURES

01.9113 GENERAL COMMISSIONING REQUIREMENTS

01.9114 COMMISSIONING AUTHORITY RESPONSIBLITIES

02.4119 DEMOLITION

07.9200 JOINT SEALANTS

08.1116 ALUMINUM DOORS AND FRAMES

08.7100 DOOR HARDWARE (Forthcoming)

08.8000 GLAZING

SATISFY THE SCOPE OF WORK RELATED TO THE BID CATEGORY.

a. DRAWING INDEX CAN BE FOUND ON TITLE PAGE.

3. Furnish and Install all Aluminum Frames and Doors as shown.

a. Including all Door Hardware related to this scope of work.

4. Furnish and Install all Glass and Glazing as shown.

5. Furnish and Install Mirrors as shown.

6. Furnish and Install all joint sealants for related work in this scope.

7. Glass cleaning at substantial completion of the entire project.

8. Furnish and install all storefront systems as shown and specified.

9. Contractor responsible for all field measurements for this scope of work.

10. Provide all hardware specified under this scope.

11. Furnish and install any break metal necessary to complete this scope.

12. Furnish and install egress stickers at all new egress openings.

13. Furnish and install all glazing films as shown.

14. Daily clean-up at work areas.

15. Contractor to meet Project Schedule, this includes weekend work or daily overtime.

a. Project Manager/Project Foreman required to attend the following meetings:

i. Pre-Construction Kick Off

ii. Bi-Weekly Progress Meeting

iii. Any meetings required by the Local Ordinance, Architect, and/or Civil Engineer

16. All work must be done in accordance with MIOSHA Regulations.

a. Provide lifting plan for any crane work.

17. Warranties as specified.

18. Submit shop drawings to scale so they can be accurately commented on/coordinated with other trades.

19. When shop drawings are returned from the Architect to Contractor marked “Rejected” or “Revise and

BID CATEGORY NO. 09 - LPDA

1. Complete LPDA work as shown on the drawings and as specified in the following sections:

SPECIFICATION MANUAL AND FRONT ENDS

00.0110 TABLE OF CONTENTS

00.0115 LIST OF DRAWING SHEETS

00.4323 ALTERNATES FORM

00.1113 ADVERTISEMENT FOR BIDS

00.4100 BID FORM

00.4323 ALTERNATES FORM

01.0000 GENERAL REQUIREMENTS

01.0001 ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT

01.1000.0 SUMMARY

01.1000.1 ABBREVIATIONS

01.1010.1 WORK COVERED BY CONTRACT DOCUMENTS

01.1010.2 SCHEDULING

01.1010.3 CONTRACTOR USE OF PREMISES

01.1010.4 SUBSTANTIAL COMPLETION

01.2200 UNIT PRICES

01.2300 ALTERNATES

01.3000 ADMINISTRATIVE REQUIREMENTS

01.3000.1 SUBMITTALS

01.3113 INSURANCE REQUIREMENTS

01.4000 QUALITY REQUIREMENTS

01.4533 CODE REQUIRED SPECIAL INSPECTIONS

01.4100 REGULATORY REQUIREMENTS

01.4533 CODE-REQUIRED SPECIAL INSPECTIONS

01.5000 TEMPORARY FACILITIES AND CONTROLS

01.5100 TEMPORARY UTILITIES

01.5713 TEMPORARY EROSION AND SEDIMENT CONTROL

01.7329 CUTTING AND PATCHING

01.7700 CLOSE OUT PROCEDURES

01.9113 GENERAL COMMISSIONING REQUIREMENTS

01.9114 COMMISSIONING AUTHORITY RESPONSIBLITIES

02.4119 DEMOLITION

05.4000 COLD-FORMED METAL FRAMING

07.8400 FIRESTOPPING

09.2116 GYPSUM BOARD ASSEMBLIES

09.2216 NON-STRUCTURAL METAL FRAMING

09.5100 ACOUSTICAL CEILINGS

09.8430 SOUND-ABSORBING WALL AND CEILING UNITS

SATISFY THE SCOPE OF WORK RELATED TO THE BID CATEGORY.

a. DRAWING INDEX CAN BE FOUND ON TITLE PAGE.

3. Furnish and Install all new metal studs as shown.

a. This includes cold form metal framing and non structural metal framing.

4. Engineered drawings required to be provided for cold form metal framing.

5. Furnish and Install all Gypsum boards as shown.

a. All Gypsum board must be finished as specified for painting.

6. Furnish and Install new Ceilings and Grid as shown on the drawings.

7. Furnish and Install new drywall bulkheads as shown.

8. Furnish and Install all batt insulation as shown on interior partitions as well as any exterior metal stud walls as shown.

9. Furnish and Install sound absorbing wall and ceiling units.

10. Furnish and Install firestopping at all rated assemblies as shown on the drawing.

11. Coordinate layout and elevations with the Construction Manager prior to install.

12. Dust control measures for all work in this Bid Category.

13. Daily clean-up at work areas.

14. Contractor to meet Project Schedule, this includes weekend work or daily overtime.

a. Project Manager/Project Foreman required to attend the following meetings:

i. Pre-Construction Kick Off

ii. Bi-Weekly Progress Meeting

iii. Any meetings required by the Local Ordinance, Architect, and/or Civil Engineer

15. All work must be done in accordance with MIOSHA Regulations.

16. Warranties as specified.

17. Submit shop drawings to scale so they can be accurately commented on/coordinated with other trades.

18. When shop drawings are returned from the Architect to Contractor marked “Rejected” or “Revise and

BID CATEGORY NO. 10 - FLOORING

1. Complete Flooring work as shown on the drawings and as specified in the following sections:

SPECIFICATION MANUAL AND FRONT ENDS

00.0110 TABLE OF CONTENTS

00.0115 LIST OF DRAWING SHEETS

00.4323 ALTERNATES FORM

00.1113 ADVERTISEMENT FOR BIDS

00.4100 BID FORM

00.4323 ALTERNATES FORM

01.0000 GENERAL REQUIREMENTS

01.0001 ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT

01.1000.0 SUMMARY

01.1000.1 ABBREVIATIONS

01.1010.1 WORK COVERED BY CONTRACT DOCUMENTS

01.1010.2 SCHEDULING

01.1010.3 CONTRACTOR USE OF PREMISES

01.1010.4 SUBSTANTIAL COMPLETION

01.2200 UNIT PRICES

01.2300 ALTERNATES

01.3000 ADMINISTRATIVE REQUIREMENTS

01.3000.1 SUBMITTALS

01.3113 INSURANCE REQUIREMENTS

01.4000 QUALITY REQUIREMENTS

01.4533 CODE REQUIRED SPECIAL INSPECTIONS

01.4100 REGULATORY REQUIREMENTS

01.4533 CODE-REQUIRED SPECIAL INSPECTIONS

01.5000 TEMPORARY FACILITIES AND CONTROLS

01.5100 TEMPORARY UTILITIES

01.5713 TEMPORARY EROSION AND SEDIMENT CONTROL

01.7329 CUTTING AND PATCHING

01.7700 CLOSE OUT PROCEDURES

01.9113 GENERAL COMMISSIONING REQUIREMENTS

01.9114 COMMISSIONING AUTHORITY RESPONSIBLITIES

02.4119 DEMOLITION

09.6500 RESILIENT FLOORING

09.6700 FLUID-APPLIED FLOORING

09.6813 TILE CARPETING

SATISFY THE SCOPE OF WORK RELATED TO THE BID CATEGORY.

3. Demo of Existing flooring and base as shown in note 10 on pages A1.1A, A1.1B, and A1.1C.

4. Furnish and Install new flooring as shown on the drawings.

a. This includes All Resilient Flooring (including base), Tile Carpeting, and Fluid-Applied Flooring.

5. Minor floor prep as needed.

6. Furnish and Install Entrance Floor Mats and Frames as shown.

7. Coordinate layout and elevations with the Construction Manager prior to install.

8. Dust control measures for all work in this Bid Category.

9. Daily clean-up at work areas.

10. Contractor to meet Project Schedule, this includes weekend work or daily overtime.

a. Project Manager/Project Foreman required to attend the following meetings:

i. Pre-Construction Kick Off

ii. Bi-Weekly Progress Meeting

iii. Any meetings required by the Local Ordinance, Architect, and/or Civil Engineer

11. All work must be done in accordance with MIOSHA Regulations.

12. Warranties as specified.

13. Submit shop drawings to scale so they can be accurately commented on/coordinated with other trades.

14. When shop drawings are returned from the Architect to Contractor marked “Rejected” or “Revise and

Resubmit”, contractor shall reissue the second time with the revisions clouded.

15. Alternate No. P-1: Provide all costs associated with the provision and installation of electric water coolers including all related services.

16. Alternate No. Pine Creek Elementary: Provide all costs associated with the Pine Creek Elementary

BID CATEGORY NO. 11 - PAINTING

1. Complete Painting work as shown on the drawings and as specified in the following sections:

SPECIFICATION MANUAL AND FRONT ENDS

00.0110 TABLE OF CONTENTS

00.0115 LIST OF DRAWING SHEETS

00.4323 ALTERNATES FORM

00.1113 ADVERTISEMENT FOR BIDS

00.4100 BID FORM

00.4323 ALTERNATES FORM

01.0000 GENERAL REQUIREMENTS

01.0001 ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT

01.1000.0 SUMMARY

01.1000.1 ABBREVIATIONS

01.1010.1 WORK COVERED BY CONTRACT DOCUMENTS

01.1010.2 SCHEDULING

01.1010.3 CONTRACTOR USE OF PREMISES

01.1010.4 SUBSTANTIAL COMPLETION

01.2200 UNIT PRICES

01.2300 ALTERNATES

01.3000 ADMINISTRATIVE REQUIREMENTS

01.3000.1 SUBMITTALS

01.3113 INSURANCE REQUIREMENTS

01.4000 QUALITY REQUIREMENTS

01.4533 CODE REQUIRED SPECIAL INSPECTIONS

01.4100 REGULATORY REQUIREMENTS

01.4533 CODE-REQUIRED SPECIAL INSPECTIONS

01.5000 TEMPORARY FACILITIES AND CONTROLS

01.5100 TEMPORARY UTILITIES

01.5713 TEMPORARY EROSION AND SEDIMENT CONTROL

01.7329 CUTTING AND PATCHING

01.7700 CLOSE OUT PROCEDURES

01.9113 GENERAL COMMISSIONING REQUIREMENTS

01.9114 COMMISSIONING AUTHORITY RESPONSIBLITIES

02.4119 DEMOLITION

09.9000 PAINTING AND COATING

SATISFY THE SCOPE OF WORK RELATED TO THE BID CATEGORY.

a. DRAWING INDEX CAN BE FOUND ON TITLE PAGE.

3. Furnish and Install all painting as shown and specified in the Construction Documents for this project.

4. Painting of Steel Lintels at New Louver Locations.

5. Contractor responsible for final touch-up.

6. Fire barrier signage/ stenciling on fire walls within concealed space above ceiling per Barrier Free

Dimensions.

7. Dust control measures for all work in this Bid Category.

8. Daily clean-up at work areas.

9. Contractor to meet Project Schedule, this includes weekend work or daily overtime.

a. Project Manager/Project Foreman required to attend the following meetings:

i. Pre-Construction Kick Off

ii. Bi-Weekly Progress Meeting

iii. Any meetings required by the Local Ordinance, Architect, and/or Civil Engineer

10. All work must be done in accordance with MIOSHA Regulations.

11. Warranties as specified.

12. Submit shop drawings to scale so they can be accurately commented on/coordinated with other trades.

13. When shop drawings are returned from the Architect to Contractor marked “Rejected” or “Revise and

Resubmit”, contractor shall reissue the second time with the revisions clouded.

14. Alternate No. P-1: Provide all costs associated with the provision and installation of electric water coolers including all related services.

15. Alternate No. Pine Creek Elementary: Provide all costs associated with the Pine Creek Elementary

BID CATEGORY NO. 12 - FIRE PROTECTION

1. Complete Fire Protection work as shown on the drawings and as specified in the following sections:

SPECIFICATION MANUAL AND FRONT ENDS

00.0110 TABLE OF CONTENTS

00.0115 LIST OF DRAWING SHEETS

00.4323 ALTERNATES FORM

00.1113 ADVERTISEMENT FOR BIDS

00.4100 BID FORM

00.4323 ALTERNATES FORM

01.0000 GENERAL REQUIREMENTS

01.0001 ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT

01.1000.0 SUMMARY

01.1000.1 ABBREVIATIONS

01.1010.1 WORK COVERED BY CONTRACT DOCUMENTS

01.1010.2 SCHEDULING

01.1010.3 CONTRACTOR USE OF PREMISES

01.1010.4 SUBSTANTIAL COMPLETION

01.2200 UNIT PRICES

01.2300 ALTERNATES

01.3000 ADMINISTRATIVE REQUIREMENTS

01.3000.1 SUBMITTALS

01.3113 INSURANCE REQUIREMENTS

01.4000 QUALITY REQUIREMENTS

01.4533 CODE REQUIRED SPECIAL INSPECTIONS

01.4100 REGULATORY REQUIREMENTS

01.4533 CODE-REQUIRED SPECIAL INSPECTIONS

01.5000 TEMPORARY FACILITIES AND CONTROLS

01.5100 TEMPORARY UTILITIES

01.5713 TEMPORARY EROSION AND SEDIMENT CONTROL

01.7329 CUTTING AND PATCHING

01.7700 CLOSE OUT PROCEDURES

01.9113 GENERAL COMMISSIONING REQUIREMENTS

01.9114 COMMISSIONING AUTHORITY RESPONSIBLITIES

02.4119 DEMOLITION

07.8400 FIRESTOPPING

21.0001 FIRE PROTECTION SUMMARY OF WORK

21.0500 COMMON WORK RESULTS FOR FIRE SUPPRESSION

21.1300 FIRE-SUPPRESSION SPRINKLER SYSTEMS

SATISFY THE SCOPE OF WORK RELATED TO THE BID CATEGORY.

a. DRAWING INDEX CAN BE FOUND ON TITLE PAGE.

3. Rework complete Fire Protection System as shown and specified on Page P2.00.

4. Include all sealed drawings for permitting and approvals.

5. Include all permits required for this scope of work. Provide the CM with a copy of the permit(s).

6. Include Fire Caulking/ Fire rating at all penetrations in fire rated assemblies created by this scope of work.

7. Include all tie ins and draining of the existing system as required to complete work.

8. It is the responsibility of this contractor to cut in all fire protection heads into the acoustical ceiling pads.

9. All work to be completed to meet industry standards.

10. Dust control measures for all work in this Bid Category.

11. Daily clean-up at work areas.

12. Contractor to meet Project Schedule, this includes weekend work or daily overtime.

a. Project Manager/Project Foreman required to attend the following meetings:

i. Pre-Construction Kick Off

ii. Bi-Weekly Progress Meeting

iii. Any meetings required by the Local Ordinance, Architect, and/or Civil Engineer

13. All work must be done in accordance with MIOSHA Regulations.

14. Warranties as specified.

15. Submit shop drawings to scale so they can be accurately commented on/coordinated with other trades.

16. When shop drawings are returned from the Architect to Contractor marked “Rejected” or “Revise and

BID CATEGORY NO. 13 - MECHANICAL

1. Complete Mechanical work as shown on the drawings and as specified in the following categories:

SPECIFICATION MANUAL AND FRONT ENDS

00.0110 TABLE OF CONTENTS

00.0115 LIST OF DRAWING SHEETS

00.4323 ALTERNATES FORM

00.1113 ADVERTISEMENT FOR BIDS

00.4100 BID FORM

00.4323 ALTERNATES FORM

01.0000 GENERAL REQUIREMENTS

01.0001 ELECTRONIC MODEL/DRAWING FILE EXCHANGE AGREEMENT

01.1000.0 SUMMARY

01.1000.1 ABBREVIATIONS

01.1010.1 WORK COVERED BY CONTRACT DOCUMENTS

01.1010.2 SCHEDULING

01.1010.3 CONTRACTOR USE OF PREMISES

01.1010.4 SUBSTANTIAL COMPLETION

01.2200 UNIT PRICES

01.2300 ALTERNATES

01.3000 ADMINISTRATIVE REQUIREMENTS

01.3000.1 SUBMITTALS

01.3113 INSURANCE REQUIREMENTS

01.4000 QUALITY REQUIREMENTS

01.4533 CODE REQUIRED SPECIAL INSPECTIONS

01.4100 REGULATORY REQUIREMENTS

01.4533 CODE-REQUIRED SPECIAL INSPECTIONS

01.5000 TEMPORARY FACILITIES AND CONTROLS

01.5100 TEMPORARY UTILITIES

01.5713 TEMPORARY EROSION AND SEDIMENT CONTROL

01.7329 CUTTING AND PATCHING

01.7700 CLOSE OUT PROCEDURES

01.9113 GENERAL COMMISSIONING REQUIREMENTS

01.9114 COMMISSIONING AUTHORITY RESPONSIBLITIES

02.4119 DEMOLITION

22.0517 SLEEVES AND SLEEVE SEALS FOR PLUMBING PIPING

22.0523 GENERAL DUTY VALVES FOR PLUMBING PIPING

22.0529 HANGERS AND SUPPORTS PLUMBING PIPING AND EQUIPMENT

22.0553 IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT

22.0719 PLUMBING PIPING INSULATION

22.0719.11 UNDER-LAVATORY PIPE AND SUPPLY COVERS

22.1005 PLUMBING PIPING

22.1006 PLUMBING PIPING SPECIALTIES

22.4000 PLUMBING FIXTURES

23.0500 HVAC SUMMARY OF WORK

23.0513 COMMON MOTOR REQUIREMENTS FOR HVAC PIPING

23.0517 SLEEVES AND SLEEVE SEALS FOR HVAC PIPING

23.0519 METERS AND GAGES FOR HVAC PIPING

23.0523 GENERAL-DUTY VALVES FOR HVAC PIPING

23.0529 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

23.0548 VIBRATION AND SEISMIC CONTROLS FOR HVAC

23.0553 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT

23.0593 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23.0713 DUCT INSULATION

23.0719 HVAC PIPING INSULATION

23.0800 COMMISSIONING OF HVAC

23.0913 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

23.0923 DIRECT DIGITAL CONTROL SYSTEM FOR HVAC

23.0934 VARIABLE-FREQUENCY MOTOR CONTROLLERS FOR HVAC

23.0993 SEQUENCE OF OPERATIONS FOR HVAC CONTROLS

23.1123 FACILITY NATURAL-GAS PIPING

23.2113 HYDRONIC PIPING

23.2116 HYDRONIC PIPING SPECIALTIES

23.2300 REFRIGERANT PIPING

23.2500 HVAC WATER TREATMENT

23.3100 HVAC DUCTS AND CASINGS

23.3300 AIR DUCT ACCESSORIES

23.3423 HVAC POWER VENTILATORS

23.3600 AIR TERMINAL UNITS

23.3700 AIR OUTLETS AND INLETS

23.4000 HVAC AIR CLEANING DEVICES

23.6213 PACKAGED AIR-COOLED REFRIGERANT COMPRESSOR AND

CONDENSER UNITS

23.7313 MODULAR INDOOR CENTRAL-STATION AIR-HANDLING UNITS

23.7433 DEDICATED OUTDOOR AIR UNITS

23.8126.13 SMALL-CAPACITY SPLIT-SYSTEM AIR-CONDITIONERS

23.8200 CONVECTION HEATING AND COOLING UNITS

SATISFY THE SCOPE OF WORK RELATED TO THE BID CATEGORY.

a. DRAWING INDEX CAN BE FOUND ON TITLE PAGE.

3. Plumbing and Mechanical Demo as shown on pages P2.00, M1.1A, M1.1B, M1.1C, and M1.80.

4. Furnish and Install exterior louvers as shown.

5. Furnish and Install all plumbing and HVAC as specified and shown.

a. All equipment as specified.

b.