About this file

This Statement of Need outlines a filter replacement project for a Donaldson Torit Dust Collector at McConnell Air Force Base in Kansas. The 22nd FSS/FSWT requires a comprehensive filter system replacement due to damage in the current wood shop dust collector filters. The contractor responsibilities include removing and discarding existing filters, inspecting the area, reporting any damage to the facility director, installing new filters, and providing necessary lift equipment to access the filters.

The project requires completion within 60 calendar days of order receipt and includes a minimum one-year warranty for each filter, with the contractor responsible for replacing any defective filters not caused by government damage or misuse. The scope is specific to the wood shop dust collector system, emphasizing thorough filter replacement and system functionality testing.

View the file

Other files for this federal contract opportunity

Other files attached to 22 FSS Wood Shop Filter Replacement, newest first.
File Type Posted
Wood Shop Filter QA.pdf PDF
Statement of Need - Wood Shop Dust Collector - August 8 2025.pdf PDF
Solicitation FA462125Q0064 - 22 FSS Wood Shop Filter Replacement - Signed.pdf PDF
Wood Shop Filter BNJ_Redacted.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

8 August 2025

Statement of Need

Filter Replacement of Donaldson Torit Dust Collector

McConnell AFB, Kansas

1. Overview

1.1 The 22nd FSS / FSWT requires a filter replacement for the wood shop dust collector system due to a hole in our current filters.

2. Description

2.1 The contractor shall replace all filters as well as the following:

2.1.1 Remove the existing filters and discard old filters offline.

2.1.2 Inspect and prepare the area for the new filters.

2.1.3 Report any damage or issues to the facility director.

2.1.4 Install the new filters and test run the equipment as needed.

2.1.5 Must provide lift equipment to reach filters

3. Warranty

3.1 The contractor shall provide a minimum of 1 year warranty for each filter. Any defect that is not caused by government damage or misuse shall be replaced by the contractor at no cost to the government.

4. Delivery

4.1 The contractor shall complete delivery of each line item no later than 60 calendar days after receipt of the order.