- To design, supply and install various fall protection systems, at Watervliet Arsenal in Watervliet, NY.
- Solicitation number
- W911PT25RA002
About this file
This Statement of Work (SOW) details fall protection and ladder system requirements for Watervliet Arsenal's Building 35E and Building 135, Project #25PW045. The project involves designing, supplying, and installing comprehensive fall protection systems, including horizontal lifelines, rescue and descent systems, anchor points, and associated equipment across multiple crane access areas and ladders. Key deliverables include installing (2) 292' horizontal lifeline systems in the High Bay Crane Area, (1) 440' horizontal lifeline system in the Low Bay Crane Area, modifications to existing ladders with vertical lifeline systems, and various safety equipment such as single point anchors, rescue kits, full body harnesses, and personal fall arrest equipment.
The contractor is required to complete the entire project within 360 calendar days after receiving the notice to proceed, with work hours limited to 7:00 AM - 4:00 PM Monday through Thursday and 7:00 AM - 3:00 PM on Fridays. Additional requirements include providing a safety plan, submitting various documentation like Safety Data Sheets, obtaining necessary permits, and conducting comprehensive training sessions. The project includes two days of onsite training for Watervliet Arsenal and Arcadis personnel, with sessions covering authorized user, authorized rescuer, and competent person training. The installed systems will have a one-year warranty from the date of completion, and the contractor must provide operations and maintenance manuals.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFIs for Fall Protection.docx | DOCX document | |
| Solicitation Amendment W911PT25RA0020002 SF 30.pdf | ||
| WO25PW045_SOW_09022025.pdf | ||
| Solicitation Amendment W911PT25RA0020001 SF 30.pdf | ||
| RFIs for Fall Protection.docx | DOCX document | |
| WO25PW045_SOW_8282025.pdf | ||
| Solicitation - W911PT25RA002.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
FOR
Fall Protection and Ladder
System
AT
Watervliet Arsenal
Building 35E and Building 135
Project #: 25PW045 Installation Management, Public Works Division
Facilities Engineering (TAWV-IMP-F)
PART 1 GENERAL
1.1 SUMMARY OF WORK
1.1.1 Project Description
a. This Statement of Work (SOW) defines the effort required to provide fall protection requirements and ladder systems. This is to include, but not limited to, horizontal lifelines, rescue and decent systems, and fall protection anchor points and painting.
1.1.2 Location of Work
a. The work is in Building 35E and 135.
1.1.3 Period of Performance
a. The contractor shall be required to (i) commence work under this contract within 7 calendar days after the date the contractor receives notice to proceed, (ii) prosecute the work diligently, and (iii) complete the entire work ready for use not later than [360] calendar days after notice to proceed was given. The time stated for completion shall include final cleanup of the premises.
1.1.4 Hours of Operation
a. Normal duty hours are 7:00 AM through 4:00 PM, Monday through Thursday, and 7:00 AM through 3:00 PM on Fridays. Federal holidays are non-workdays. If a federal holiday falls on a Saturday or Sunday, the preceding Friday or following Monday is a work holiday.
1.2 SUBMITTALS
1.2.1 General Submittal Requirements
a. The contractor shall provide submittal documents via e-mail to the Contracting Officer for review and approval. Provide all physical (non-document) submittals (including but not limited to material swatches, samples, etc.) directly to the Contracting Officer for review and approval. All submittals require government approval unless otherwise explicitly stated.
b. The contractor shall reference APPENDIX A “Consolidated List of Submittals” for the complete list of required submittals.
1.2.2 Contractor Safety Plan
a. The contractor shall submit a safety plan which is specific to the work activity being performed under the scope of this project for Government review and approval.
1.2.3 Lockout / Tagout (LOTO) Acknowledgement
a. The Contractor shall sign and submit a “Lockout/Tagout (LOTO) Notification Acknowledgement Record” prior to working on or de-energizing any electrical equipment.
1.2.4 Asbestos Notification Acknowledgement Record
a. The contractor shall sign the “Asbestos Notification Acknowledgement Record” and submit this form to the Project COR prior to starting project work.
b. Asbestos containing materials may be present in the other areas of the building where work is being performed. The contractor is responsible to ensure that any asbestos containing materials are not disturbed or damaged and will be responsible for all costs associated with clean-up and the clearance of the building due to disturbance or damage to asbestos containing materials not included in the scope of work. If hazardous materials are found, the government shall be notified immediately.
c. The contractor shall always protect the existing areas around the area of work. Any damage because of the contractor activities shall be repaired at no additional cost to the owner.
d. The contractor shall exercise caution while working around the buildings fire alarm and suppression systems through the entirety of the project. The contractor shall coordinate any temporary shutdown with the fire department and COR.
1.2.5 Project Schedule
a. The contractor shall create a project schedule and submit for Government review and approval.
b. The project schedule shall detail the phases of work and the overall timeline for the execution of the work. The contractor shall include delivery dates, appropriate milestones, and shall clearly detail any requirements for work performed outside of regular hours of operation.
1.3 GENERAL REQUIREMENTS
1.3.1 Watervliet Arsenal Information for Contractors (WAIC)
a. The contractor shall perform all work in strict conformance with Watervliet Arsenal Instructions for Contractors (WAIC). The contractor shall read and understand this document prior to submitting a proposal. The WAIC is publicly available at:
<http://www.wva.army.mil/Documents/Contracting/WAIC.pdf>
1.3.2 Utility Outage Requests and Utility Connection Requests
a. Schedule work to minimize outages. For utility outages and connections required during the execution of work that affect existing systems, coordinate schedule with COR. Schedule utility outages and connections to minimize disruptions to the Government. No additional payment will be http://www.wva.army.mil/Documents/Contracting/WAIC.pdf provided for utility outages and connections required to be performed outside the regular work hours.
b. The contractor shall notify the Contracting Specialist a minimum of two (2) business days before the contractor starts work. The contractor shall notify the COR a minimum of seven (7) business days before the shut-down of a utility or building service.
c. Watervliet Arsenal Instructions For Contractors (WAIC)
d. New York State Industrial Code Rule 56 – 12 NYCRR Part 56, Asbestos (ICR56).
1.3.3 Safety Requirements
a. The contractor is required to provide the proper control of hazardous energy (lockout/tagout) per
OSHA 29 CFR 1910.147.
b. The contractor shall inspect the project work site prior to starting work and shall request a copy of the asbestos building inspection records to verify the location and description of known asbestos-containing materials.
1.4 ON-SITE PERMITS
1.4.1 Hot Work and Confined Space
a. Obtain permit for welding, burning, use of flame, or entry into confined space from WVA Fire Department by calling (518)266-5990 each day the permit is to be used.
1.5 APPLICABLE DOCUMENTS
1.5.1 Drawings
a. The following drawings accompany this Statement of Work.
i. SK1 – Schematic Plan
ii. SK2 – Partial Building Section
1.5.2 OSHA Standard – Regulation Detail
i. 1910.28(b)(9)(i)(A) - Each existing fixed ladder installed before November 19, 2018 must be equipped with a personal fall arrest system, ladder safety system, cage, or well.
ii. 1910.28(b)(9)(i)(B) - Each fixed ladder installed on and after November 19, 2018 must be equipped with a personal fall arrest system or a ladder safety system.
iii. 1910.28(b)(9)(i)(D) - On and after November 18, 2036, all fixed ladders must be equipped with a personal fall arrest system or a ladder safety system.
iv. 1910.28(b)(3)(iii) - Each employee is protected from falling into a stairway floor hole by a fixed guardrail system on all exposed sides, except at the stairway entrance.
v. 1910.28(b)(9)(i)(D) - Metal ladders should be protected against corrosion and made with corrosion-resistant materials like aluminum.
vi. 1910.23(d)(13)(i)– Ladders should be installed at least 15 inches between it and any permanent objects surrounding it, measured from the ladder’s centerline.
vii. 1910.23(d)(2) - Ladders should have a minimum perpendicular distance of 7 inches from the centerline of the rungs to the nearest permanent object in the back of the ladder.
viii. 1910.23(d)(7) - Ladders grab bars should extend 42 inches above the ladder’s surface and have the same size as the ladder rungs.
ix. 1910.27(b)(1)(i)(ii) - Ladders rungs made of metal must have a minimum diameter of three-fourths inch. and not greater than 12-inches between rungs.
x. 1910.27(b)(1)(i)(ii) - Ladders rungs must have a minimum diameter of three-fourths inch. and not greater than 12-inches between rungs
xi. 1910.27(b)(1)(v) - Ladders rungs must be so designed that the foot cannot slide off the end.
xii. 1917.118(e)(4)(i) - Be installed and maintained in accordance with the manufacturer's instructions, which shall be available for inspection.
xiii. 1910.28(b)(3)(i) - Each employee is protected from falling through any hole (including skylights) that is 4 feet (1.2 m) or more above a lower level.
xiv. 1910.28(b)(6)(ii) - Each employee 4 feet (1.2 m) or more above dangerous equipment must be protected from falling by a guardrail system or a travel restraint system.
1.5.3 References
a. The following references accompany this Statement of Work and are a part thereof.
i. Watervliet Arsenal Instructions for Contractors (WAIC).
ii. NFPA 70 – National Electric Code (NEC).
iii. OSHA Standard
1.6 CONTRACTOR EQUIPMENT
1.6.1 Equipment Identification
a. The contractor shall create and affix a label to all large equipment, dumpsters, and other mobilized property, which is weather-resistant (laminated, or within a see-thru label hanger), securely affixed to the equipment or visible through a window, and which clearly displays the General Contractor’s:
i. Company Name, POC Name (first, last), POC phone number, Project Number
(25PW045).
1.6.2 Waste Dumpster
a. The contractor shall place any waste dumpsters in a manner that does not interfere with thru-traffic.
b. Place waste dumpsters with a minimum of 33’ clearance from any building. The final location shall be coordinated with and approved by the COR before any dumpsters are mobilized.
c. Cover all waste dumpsters when not in use, and before the end of each work shift. The cover shall be weather-tight.
d. Note: The Contractor shall be required to retain and submit copies of all Bills of Lading and Weight Slips associated with the disposal of construction and demolition C&D) debris.
PART 2 PRODUCTS
2.1 GENERAL
All work shall be in strict accordance with product manufacturer’s instructions and specifications, including but not limited to manufacturer guidance for storage, staging, application, installation, and disposal of the product.
2.1.1 Hazardous Materials
a. The contractor shall submit Safety Data Sheets (SDS) for all hazardous materials to be used.
2.1.2 Asbestos, Mercury, Lead, PCB
a. Unless otherwise stated, all materials for this project shall be new. All products shall not contain any asbestos, mercury, chromium/lead paint, Class I Freon, and Polychlorinated Biphenyls (PCB), and shall state such on the manufacturer’s original packaging.
2.1.3 DoD Green Procurement Program
a. All construction materials shall meet the applicable requirements of the DoD Green Procurement Program, specifically recycled content products, environmentally preferable products and services, bio-based products, energy-and water-efficient products, alternate fuel vehicles and alternative fuels, products using renewable energy, and alternatives to hazardous or toxic chemicals as found at <http://www.acq.osd.mil/dpap/cpic/cp/docs/USA001967-08-DPAP.pdf>.
2.1.4 Contractor Deliverables:
Equipment Plans & Design:
a. Design, specifications, supply, provide installation drawings with NY Professional Engineer Seal.
System Certification at time of installation with maintenance and user demonstration on the proper use and care of the system(s) at time of installation. Operations and Maintenance Manual will be provided to the Arsenal at time of completion. These systems to include a warranty of 1 year from the date of completion of installation.
b. The contractor shall develop and submit a detailed work plan, including a project schedule, to outline the phases and duration of work activities. If project work deviates from the submitted schedule, the contractor shall revise the schedule as necessary.
c. The work plan and schedule shall be submitted to the project COR for government review and approval prior to the start of project work.
d. Contractor shall keep on the work site a copy of the drawings and specifications that are part of the deliverables and shall always give the COR access thereto. Anything mentioned in the specifications and not shown on the drawings or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both. In case of discrepancy in the figures, in the drawings or in the specifications, the matter shall be promptly submitted to the COR and a determination shall be made. Any adjustments by the Contractor without such a determination shall be at the risk and expense of the Contractor.
e. Contractor to provide all required tools, safety equipment, lifts and equipment for installation.
f. Contractor to provide personal safety equipment as specified below.
g. Contractor to provide operations and maintenance manuals.
h. Contractor to clean-up and removal of equipment and waste.
2.1.5 High Bay Crane Area:
Crane access for cab # (B100, B1010 &B244):
a. Propose to design, supply, and install (2) 292’ Horizontal Lifeline systems, on the upper (B100) and at the lower crane (B101 & B244). Each cable will be rated for three users. (2) Single Point Anchors, each rated for one user, mounted near the crane cab with a rescue descent kit. Each crane will also include one 6’ PFL, a harness, also
b. (1) 75’ Rescue Kit
c. (1) 100’ Rescue Kit
d. (2) 6’PFL
e. (3) Full Body Harness with storage bag
2.1.6 Low Bay Crane Area
Crane access for cab #(B102, B104, B106, B107, B109, B271, B330, B409 & B410, B427, B432) :
A-B Crane Access/rescue:
a. Design, supply, and install 6’x440’ grating between crane rails. This includes modifications to install the grating around existing building columns.
b. (1) New 440’ Horizontal lifeline system rated for four users, attached directly to existing building columns.
c. (4) Single Point Anchors, each rated for one user, (4) 50’ Rescue Kit mounted near the crane cab with a rescue descent (4) 6’ PFL kit. Each crane will also include one 6’ PFL, a harness, (4) Full Body Harness and a storage bag.
C-D Crane Access/rescue:
a. design, supply, and install 6’x440’ grating between crane rails. This includes modifications to install the grating around existing building columns.
b. (1) New 440’ Horizontal lifeline system rated for four users, attached directly to existing building columns.
c. (6) Single Point Anchors, each rated for one user, (4) 50’ Rescue Kit mounted near the crane cab with a rescue descent (4) 6’ PFL kit. Each crane will also include one 6’ PFL, a harness, (4) Full Body Harness and a storage bag.
2.1.7 Ladders and Access Platforms at Building 135
A-B South Ladder /platform:
a. Replace an angled ladder to first platform, approx. 21’6”, and include a new vertical lifeline fall protection system for the entire ladder, approx. 60’, complete with two ladder latch units. Remove existing 40’ ladder cage. Remove two old gates and install three new gates. Add two new gates on two upper platforms. Add four sections of approx. 12” guardrail on the sides of the platform that steps out to the crane cabs.
A-B North Ladder /platform:
a. Add six new gates and remove four old gates. Add new vertical lifeline system to lower ladder, complete with extension post, approx. 29’ long, including two ladder latch units. Remove ladder cage, approx. 16’. Provide modifications to existing ladder ensuring it is complete with metal rung grips (upper ladder to level only, approx. 13’). Add new cable vertical lifeline system to upper unit ladder with extension post and ladder latch units, system will be approx. 19’ long. Replace upper ladder to provide sufficient back N/A clearance at the top. Add midrail to railing around top of upper ladder.
C-D North Ladder /platform:
a. install six new platform gates, remove four old gates. Provide modifications to existing ladder ensuring it is complete with metal rung grips. Add new vertical lifeline system with extension post, approx. 19’ total with ladder latch units.
C-D South Ladder /platform:
a. Remove ladder cage, approx. 12’. Provide modifications to existing ladder ensuring it is complete with metal rung grips (ladder to platform level only, approx. 21’). Add new vertical lifeline system with extension post, approx. 28’ total with one ladder latch.. Provide modifications to existing ladder ensuring N/A it is complete with metal rung grips (upper ladder to platform level only, approx. 13’). - Remove two old gates, install four new gates. Add sections of approx. 12” guardrail on the sides of the platform that steps out to the crane cabs.
Roof Ladder:
a. To design, supply, and install (1) Single Point (1) 50’ SRL anchor for one user over lower section of ladder, (1) Rope tagline complete with a 50’ SRL and rope tagline and gate. To design, supply, and install (1) Top extension post for one user to the upper ladder and a gate.
b. At Building 35E add (1) 15’ Ladder complete with vertical lifeline (2) Ladder Latch unit system, attached to brick wall for access to open/close valves.
Rescue Kit:
a. (1) 75’ Rescue Kit
b. (1) 6’ PFL
c. (1) Full Body Harness
d. (1) 85’ SRL for training backup.
2.1.8 Equipment Training with POST Installation Certification:
a. Contractor to show installation maintenance and user demonstration on the proper use and care of the system(s). Contractor to provide an evacuation and rescue plan. Contractor to provide 2 days of onsite training for Watervliet Arsenal and Arcadis. Contractor to include one extra set of PPE and 1 extra set of rescue equipment to use for training. Additionally, a second rescue anchor point will be included to connect a backup SRL for training.
b. Contractor to included two one-day sessions, each consisting of 2 hours authorized user (up to 20 people per session)
c. Contractor to provide 6 hours authorized rescuer (up to 10 people per session, due to practical exercise time requirements)
d. Contractor to include is one additional 2-day session of competent person training (up to 10 people).
The competent person portion of training allows participants to train other authorized users/rescuers in the future. Competent person participants must also participate in the authorized user and authorized rescuer portion of training. 3 days of training total
e. The Competent Person for Safety at Heights course is designed for supervisors, managers, and safety professionals responsible for fall protection programs. It is specifically suited for the person who will carry OSHA’s title of “competent person” to have the responsibilities of recognition of current / predictable hazards and who have the authority to eliminate them as they relate to fall hazards.
f. The Authorized Person for Safety at Heights course is designed for employees that are regularly required to work at height who are supervised by the company’s Competent Person(s) under its fall protection program. Train-the-trainer for Authorized User and Authorized Rescuer is included in the Competent Person training.
g. System certification, at time of installation provided to the Arsenal at time of completion. These systems include a warranty of 1 year from the date of completion of installation.
PART 3 EXECUTION
3.1 ITEMS OF WORK
3.1.1 General Preparation.
a. The contractor shall document and bring to the attention of project COR, all discrepancies, and any existing damage found within the work areas.
b. The contractor shall provide all necessary dust control, floor protection in traffic areas (dirt/debris).
c. The final placement of the dumpster shall not hinder traffic. Final dumpster location shall be coordinated and approved with project COR prior to arrival.
d. The contractor shall isolate all utilities. Contractor shall not affect the utilities of neighboring areas.
If coordination with Arsenal PW maintenance staff is necessary, arrangements shall be made a minimum of 48 hours in advance.
e. The contractor shall shut off power to area when any work is being done to electrical boxes, electrical wiring, lighting fixtures, or other inherently associated tasks.
i. The contractor shall perform all electrical work in accordance with NFPA 70: National Electric Code requirements.
f. The contractor shall exercise caution while working around the buildings fire alarm and suppression systems through the entirety of the project. The contractor shall coordinate any temporary shutdowns with the project COR.
g. The Contractor agrees to do all work in accordance with the plans, specifications, and performance standards and in accordance with good building practice, all federal laws and codes pertaining thereto and to the satisfaction of the Project COR.
h. The Contractor agrees that the Government is not responsible for fire, theft, loss and/or vandalism of any of the Contractor’s tools, equipment, materials, supplies and/or work in progress.
i. It is the intent of this contract to be complete and functional in all respects meeting all applicable codes and requirements and to the final approval of the Project COR.
j. The Contractor shall supply all required expertise, labor, tools, equipment, materials, and services required to provide a complete project in accordance with the approved plans, specifications, and interior finish schedules.
3.1.2 Paint.
a. The contractor shall prepare and paint all adjacent surfaces within the work area where surfaces have been disturbed. Paint to match adjacent services or per the COR.
i. All paint work shall be performed in accordance with WVA Specification 09 90 00 -
INTERIOR PAINTS AND COATINGS.
ii. Colors and sheen are to be chosen by Contracting Officer Representative after a color wheel or samples are submitted for review and approval.
iii. At completion of painting phase, walls and ceiling shall be smooth and even coated in appearance with no bleed through. Painting of walls and ceiling shall have a professional neat appearance. Doors and windows shall operate without interference.
Any over-brushed paint shall be removed, and the underlying surface repaired.
iv. If bleeding of paint has occurred, it is the Contractors responsibility to correct the appearance and for the proper coverage, so no bleed occurs.
3.2 CLOSEOUT REQUIREMENTS
3.2.1 Construction and Demolition Debris
a. The Contractor shall submit copies of all Bills of Lading and Weight Slips associated with the disposal of construction and demolition (C&D) debris and/or recycled materials, under this scope of work. Submit documentation per Appendix A, “Consolidated List of Submittals”.
3.2.2 Cleanup of Work Site
a. The contactor shall clean all work areas and remove all tools, equipment, debris, materials, and all waste from the premises.
b. The contractor shall remove all debris from any remote holding locations, to include any excavation and concrete equipment chute cleanout debris.
c. The contractor shall remove their equipment from Watervliet Arsenal premises within five (5) working days after completion of project work.
3.2.3 Restoration of Work Site
a. The contractor shall repair any items, building surfaces, equipment or miscellaneous items which were damaged during the execution of this SOW. Items that cannot be repaired to restore original function or aesthetics shall be replaced in kind by the Contractor at no additional charge to the Government.
b. Grass, trees, and other vegetation affected by project work shall be restored to same or better condition as existed prior to the start of project work. The Contractor shall prepare the affected areas to eliminate uneven areas and low spots. Remove foreign materials, weeds, and damaged soil. The Contractor shall scratch the area to a depth of three (3) inches where topsoil is to be placed. Spread topsoil to a uniform, compacted depth of less than five (5) inches over areas to be reseeded. Rake until smooth. The Contractor shall seed, fertilize, and water the area to establish grass.
3.2.4 Warranty
a. The contractor shall provide a [1] year warranty on workmanship and construction.
PART 4 APPENDICES
a. Consolidated List of Submittals
b. Quality Assurance Surveillance Plan (QASP)
APPENDIX A: Consolidated List of Submittals
Line Item Submitted Submittal Needed By Submittal Reviewed By (Office)
1 Safety Data Sheets for Hazardous Materials
(SDS)
NLT 7 Calendar Days After Award
Safety Office
2 Signed Contractor Asbestos Notification Form NLT 7 Calendar Days After Award
Environmental Office
3 Signed Lockout/Tagout (LOTO) Notification Acknowledgement Record
NLT 7 Calendar Days After Award
Safety Office
4 Project Schedule NLT 7 Calendar Days After Award
COR
5 Contractor Safety Plan NLT 7 Calendar Days After Award
COR
6 Bills of Lading, Dump Slips for C&D Debris and Recycled Materials
Before Closeout Environmental Office
7 Paint NLT 7 Calendar Days After Award
Environmental Office
APPENDIX B: Quality Assurance Surveillance Plan (QASP)
PURPOSE
This Quality Assurance Surveillance Plan (QASP) will be used as a guide to Government Quality Assurance Personnel (QAP). It provides a systematic method to evaluate the services the contractor is required to furnish.
SURVEILLANCE PROCEDURES
Timeliness: Progress is maintained to assure compliance with completion time.
Quality: Conformance with statement of work and industry standards.
Tasks: Performed according to statement of work requirements.
Problem Resolution: Contractor submits deliverables in accordance with the contract and resolves any deficiencies identified by the government in the final submission. Following final submission, contractor resolves any additional deficiencies identified by the government and resubmits and or corrects within one week.
Delivery: Contractor submits each deliverable in accordance with the statement of work and terms of the contract.
PERFORMANCE AREAS
Management Responsiveness: Evaluate the adequacy of the contractor’s responsiveness and their ability to keep the government informed of work progress and provides for early problem identification and effective corrective action plans.
Schedule Control: Evaluate the contractor’s adherence to completion schedule.
Performance: The contractor will be evaluated as to the workmanship and adherence to the statement of work.
EVALUATION CRITERIA
(Outstanding). Indicates performance clearly exceeds contractual requirements. The area of evaluation contains few minor problems for which corrective actions appear highly effective.
(Satisfactory). Indicates performance clearly meets contractual requirements. The area of evaluation contains some minor problems for which the corrective actions appear satisfactory.
(Unsatisfactory). Indicates the contractor failed to satisfy contractual requirements and recovery is not likely in a timely manner. The area of evaluation contains serious problems for which the corrective actions were ineffective.
DOCUMENTATION
Documentation used to perform surveillance will consist of random government inspections and inspection records, as well as the evaluation of final work product delivery by the project COR/COTR.
RATING
Contractor will be given an overall rating of Outstanding, Satisfactory, or Unsatisfactory by the Government Technical point of contact or Contracting Specialist Representative, if appointed, using the above 3 evaluation criteria.
| STATEMENT OF WORK (SOW) |
| FOR |
| Fall Protection and Ladder |
| System |
| AT Watervliet Arsenal |
| Building 35E and Building 135 |
| Project #: 25PW045 Installation Management, Public Works Division |
| Drawings.pdf |
| Building 135 Fall Protection Assesment and System Recommendations 7 28 23 |
| Site Background and Executive Summary |
| 1. Existing Conditions |
| 1.1 Existing System Summary |
| 1.1.1 Fall Protection Assessment (Low Bay) |
| 1.1.2 Fall Protection Assessment (High Bay) |
| 1.1.3 Building 35 and 135 Ladder Systems |
| 2. Fall Protection Recommendations |
| 2.1 Summary of recommendations |
| 2.2 Recommendation Details |
| 2.2.1 Recommendations for Low Bay Crane Area |
| 2.2.2 Recommendations for High Bay Crane Area |
| 2.2.3 Recommendation for Building 135 Ladders |
3. Other Considerations
| Attachments |
| Figure 1- Building 135 Low Bay Cranes |
| Figure 2- Building 135 High Bay Cranes |
| Figure 3- Building 135 Low Bay Crane Catwalk System |
| Appendix A - Photo Log of Example Areas for Improvement |
| Appendix B |
| Appendix C |
File details come from the government source that posted it. Updated .