This Price Quote Request is issued by Escambia County Marine Resources Division (MRD) in support of an application to the Florida Fish and Wildlife Conservation Commission's Derelict Vessel Removal Grant Opportunity Announcement. The document requests individual price quotes for the floating, removal, transport, and disposal of a 32-foot Islander vessel (Registration: DO591303, Color: White) located near Pensacola Pass. The vessel was broken apart during Tropical Storm Bertha and is being re-solicited due to its changed condition; contractors must account for complete removal of all vessel-related debris in their bids. Work must begin within 7 calendar days of the Notice to Proceed and be completed within 14 calendar days, with adverse weather extensions available upon written request and approval. Contractors are responsible for coordinating with the US Navy regarding permissions to work near Naval Air Station Pensacola. Responses are due by 2:00 PM on August 11, 2026, via OpenGov. The project includes comprehensive photo-documentation of all removal phases and delivery of hazardous materials (batteries, flares, propane tanks) to the landfill's Hazardous Household Waste facility.
Contractors must submit total pricing for vessel removal including all associated costs, with disposal at the Perdido Landfill as the preferred location. Escambia County will provide written authorization for vessel removal and ensure contractor insurance meets county requirements; contractors must submit an insurance letter at the time of submittal with a Certificate of Insurance required if selected. Strict Best Management Practices must be employed, including daytime operations (Monday-Friday), turbidity barriers within a 10-foot radius of the vessel, removal of all contaminants (fuels, batteries, paints, solvents, engines) by licensed operators, and avoidance of impacts to protected species and sensitive habitats. Fuel tanks larger than 20 gallons must be removed, perforated, and flattened. Contractors bear responsibility for all tipping fees at the landfill, and no salvage of vessel items is permitted. Escambia County will provide oversight and coordinate with the landfill to ensure timely disposal. Contact information is provided for derelict vessel inquiries (Robert Turpin and Matt Szatkowski) and OpenGov administrative questions (Susan Holt).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Derelict_Vessel_Removal,_Transport,_and_Disposal_-_32'_Islander_-_Re-Solicit.pdf | ||
| 20251208_Insurance_Requirements_for_Marine_activities_(1).docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Escambia County Marine Resources Division Price Quote Request: Derelict Vessel Removal, Transport and Disposal Date: 6/30/2026 Escambia County Marine Resources Division (MRD) is submitting an application to the Florida Fish and Wildlife Conservation Commission’s (FWC) Derelict Vessel Removal Grant Opportunity Announcement. As required in the application, Escambia County must provide individual price quotes for each proposed Derelict Vessel. This Price Quote seeks the total price for floating, removal, transport and tipping fees associated with the vessel’s disposal at the Perdido Landfill of the following vessel:
Vessel Name: 32’ Islander
Length:32’ *Prospective bidders should verify* :
Color: White Make: Islander Registration: DO591303 Location: Near Pensacola Pass (Approximately 30deg 20.356N, 87deg 18.902W)
FWC Case Number: FWC26ON0056048 *Vessel was broken apart due to TS Bertha. Project is being re-solicited, due to the change in condition of the vessel. Contractors should consider the cost to completely remove all vessel related debris in their bid price. Contractor should fully understand the current condition of the vessel and it’s debris before submitting a bid for complete removal. * Information provided from sources other than MRD, therefore bidders should verify actual vessel dimentions and conditions before submitting price quotes.
Due to the vessel’s proximity to naval Air Station Pensacola, contractor will be responsible for coordinating with the US Navy for any permissions that may be required to work in that area.
*Information regarding the description, location, and characteristics of the vessel represent the best available information provided to Escambia County MRD as of the date of posting*
June 11, 2026 – Before TS Bertha
No photograph available post TS Bertha.
Escambia County Responsibilities
1. Provide Contractor with written documentation of vessel and “Derelict Vessel” status and authorization for removal.
2. Ensure contractor’s insurance coverage meets Escambia County requirements. (see below)
3. Oversight of the removal project. To the extent possible, the Marine Resources Division will have someone available to be on scene during the removal operation.
4. MRD will coordinate in advance with the contractor and landfill to ensure the disposal of the vessel proceeds in a timely manner when delivered. Escambia County’s Perdido Landfill is the preferred disposal site.
Contractor Responsibilities Work to begin within 7 calendar days of the Notice to Proceed (NTP). Project expected to be completed within 14 calendar days of issuance of the NTP. Adverse weather days may allow for an extension but must be requested in writing and approved by the Marine Resource Division.
Contractor will photo-document removal process and submit photographs to MRD at completion of removal. Photos should sufficiently capture all phases of the removal, including evidence of vessel destruction.
Contractor will also deliver batteries/flairs/propane tanks found on board the vessel to Hazardous Household Waste at the landfill.
The following best management practices (BMP’s) will be employed by the marine contractor during the removal of derelict vessels. The marine contractor selected for the project will be required to show proof of their ability to meet the BMP requirements with their contingency of equipment, staff and expertise in the removal of derelict vessels.
Compliance with these BMP’s will be monitored by the County and by local Florida Fish and Wildlife Conservation Commission law enforcement officers. These BMP’s are as follows:
A. All Work Is To Meet The Following Requirements:
1. Operations are to be limited to daylight hours Monday through Friday.
2. Operations are to be staged from an upland area.
3. All work is to be performed in a manner that avoids and/or minimizes impacts to live bottom and other resource areas (e.g., seagrass beds, oyster beds, wetlands, mangroves, and other sensitive habitats) while approaching, working in, and leaving the derelict vessel site.
4. All work shall avoid impacts to manatees, sea turtles, and other species listed by the state and federal government as threatened or protected.
5. The Contractor will remove all contaminants and pollutants including fuels, batteries, paints, solvents, and engine from the derelict vessel prior to extraction. Any contaminant or pollutant found to be contained within a derelict vessel shall be removed by the Contractor, placed in an approved container, and disposed of properly. The placement of an absorbent blanket on the surface of the water around the derelict vessel within the turbidity barrier is required where free floating product (gas/oil) is observed.
6. The Contractor is to provide appropriate best management practices (BMPs) approved by the Florida Department of Environmental Protection for erosion control and turbidity protection while each derelict vessel is being removed. In areas of low to moderate currents, a Type II floating turbidity barrier will be installed within a ten (10) foot radius of the vessel being removed prior to starting any removal activities. The turbidity barrier shall be anchored to the bottom of the waterway.
7. The Contractor is to provide appropriate BMPs for erosion control and turbidity prevention around the vessels/barges being used to remove the derelict vessel and around the perimeter of any upland staging site (where necessary).
8. The Contractor is to monitor turbidity levels throughout removal work.
9. In an effort to reduce turbidity, a crane, winch and/or approved alternate method is to be used to raise the derelict vessel from the water.
10. The Contractor will assess turbidity levels and allow them to return to an acceptable level similar to pre-project condition prior to removal of turbidity measures.
11. The dragging of vessels is to be avoided both on and off-shore. All vessels/barges used in vessel removal shall continually monitor water depths to avoid running aground.
12. The Contractor will load derelict vessels onto a barge and/or flat bed truck (or similar) for proper disposal.
B. For Derelict Vessels That Are Floating or Lightly Aground:
1. The vessel is to be pumped out as needed and extracted (floated out) during high water.
2. Following extraction, the vessel is to be towed from the grounded location to a boat ramp or other removal point while avoiding and/or minimizing impacts to live bottom areas.
C. For Derelict Vessels That Are Hard Aground:
1. The vessel is to be approached using shallow draft vessels.
2. The vessel is to be extracted using a crane from a shallow draft deck barge, by hand using the best available tools, or similar approach to minimize impacts to the site and surrounding areas.
D. For Derelict Vessels Sunken in Shallow Water:
1. Install and inflate flotation bags as needed.
2. Lift the vessel with barge mounted crane or similar equipment
In addition to the above, Escambia County requires the contractor to:
1. Prior to transport to the landfill, fuel tanks must be pumped out by a licensed operator and the contents handled as contaminated. Fuel tanks less than 20 gallons may stay in the vessel. Fuel tank(s) larger than 20 gallons must be removed from the vessel. If the tanks are larger than 20 gallons, the tanks must be perforated, then flattened, and then the tanks can be placed with the vessel or vessel debris for removal to the landfill.
2. Holding tanks for sewage or grey water must be pumped out by a licensed operator.
3. The Contractor is to photo-document all removal activities with photographs taken before, during and after removal, as well as final disposal at landfill. The Contractor will provide a daily written report of all removal activities to the County with photographs.
4. Contractor will transport vessel to pre-authorized landfill; contractor will obtain pre-authorization from Escambia County Marine Resources Division regarding landfill selection and disposal. The contractor will pay the tipping fees for the vessel.
5. No items may be salvaged from the vessel during the removal/disposal process.
Insurance Requirements
See attached document: Insurance requirements for DV vessel removal-10-20-2025 Risk Mng for Escambia County Standard Insurance Requirements and Certificates.
At the time of submittal, please include a letter from your insurance company stating that your company has or can obtain the required insurance levels. A COI will later be required in order for your company to proceed if selected.
Indemnification
Contractor agrees to save harmless, indemnify, and defend County and Architect/Engineer and their, agents, officers and employees from any and all claims, losses, penalties, interest, demands, judgments, and costs of suit, including attorneys' fees and paralegals' fees, for any expense, damage or liability incurred by any of them, whether for personal injury, death, property damage, direct or consequential damages, or economic loss, including environmental impairment, arising directly or indirectly on account of or in connection with the Work done by Contractor under this Agreement or by any person, firm or corporation to whom any portion of the Work is subcontracted by Contractor or resulting from the use by Contractor, or by any one for whom Contractor is legally liable, of any materials, tools, machinery or other property of County. County and Contractor agree the first $100.00 of the Contract Amount paid by County to Contractor shall be given as separate consideration for this indemnification, and any other indemnification of County by Contractor provided for within the Contract Documents, the sufficiency of such separate consideration being acknowledged by Contractor by Contractor's acceptance and execution of the Agreement. The Contractor's obligation shall not be limited by, or in any way to, any insurance coverage or by any provision in or exclusion or omission from any policy of insurance. The Contractor agrees to pay on behalf of Escambia County, as well as provide a legal defense for the County, both of which will be done only if and when requested by the County, for all claims made. Such payment on the behalf of the County shall be in addition to any and all other legal remedies available to the County and shall not be considered to be the County's exclusive remedy.
Project expected to be completed within _14__ calendar days of issuance of Notice to Proceed.
Total Price of Vessel removal: $___________________________________________________________
Approved Disposal Location: _____________________________________________________________
Company Name: _______________________________________________________________________
Mailing Address: _______________________________________________________________________
Printed Name and Signature: _____________________________________________________________
Email________________________________________________________________________________ Contact Phone Number _________________________________________________________________ Please respond via OpenGov by 2:00 PM August 11, 2026. OpenGov questions should be directed to Susan Holt (srholt@myescambia.com; 850-595-4579). Derelict vessel questions should be directed to Robert Turpin (rkturpin@myescambia.com; Cell ph. 850-554-5869) or Matt Szatkowski mdszatkowski@myescambia.com; Cell ph. 850 426-1257) image1.png image2.jpeg