WLS Butler Co Type II.xlsx

XLSX spreadsheet 17 KB Posted

Attached to
RoW Mow and Trim Butler Co
Solicitation number
RFB 605 2400000410 2
Issued by
Breckinridge County, Kentucky

About this file

This is a road maintenance project specification document for Butler County, Kentucky, detailing Type II mowing services across state routes within the county. The project encompasses a comprehensive network of major and secondary roads totaling 229.509 miles requiring mowing maintenance. The service includes two main route categories: five major state routes (US 231 and KY 70, 79, 106, 185) comprising 90.209 miles with 266 mowing acres, and nineteen secondary state routes (KY 269, 340, 369, 403, 411, 626, 949, 1038, 1083, 1117, 1118, 1153, 1187, 1328, 1435, 1468, 2266, 2267, 2269, 2713, and 3182) comprising 139.300 miles with 342 mowing acres. The total project scope requires 608 mowing acres across all routes, with each route requiring three complete mowing cycles. The maximum time allowed to complete a single mowing cycle is 12 working days.

The specification establishes a fixed project scope with defined mileage and acreage requirements for bidding and contract performance purposes. Routes are identified by route number, system classification, project number designation, specific geographic endpoints, and precise length measurements in miles. All routes maintain consistent cycle requirements of three annual mowing cycles to be completed within the specified timeframes. No pricing information, funding sources, contract term, set-asides, or incumbent contractor details are provided in this specification document, as it serves primarily as a technical scope of work defining the physical parameters and work requirements for the mowing maintenance contract.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table 1

Route
NumberSystemCountyProject
NumberFROMTOLength
(Miles)Mowing
Acresof
CyclesType II

Mowing Acres

US 231MPButlerFE01 016 0231
000-019Warren County Line (MP 0.000)Ohio County Line (MP 18.846)18.84661345
KY 70MPButlerFE01 016 0070
000-030Muhlenburg County Line (MP 0.000)Edmonson County Line
(MP 29.977)29.97784372.7
KY 79MPButlerFE01 016 0079
000-025Logan County Line (MP 0.000)Grayson County Line (MP 24.901)24.90170360
KY 106MPButlerFE01 016 0106
000-011Logan County Line (MP 0.000)KY 70 near Rochester (MP 9.875)9.875293
KY 185MPButlerFE01 016 0185
000-007Warren County Line (MP 0.000)Edmonson County Line (MP 6.610)6.610223
Subtotal MP90.209266
KY 269RSButlerFE01 016 0269
000-007KY 403
(MP 0.000)Ohio County Line (MP 6.043)6.04383
KY 340RSButlerFE01 016 0340
000-013KY 70
(MP 0.000)Grayson County Line (MP 12.761)12.761233
KY 369RSButlerFE01 016 0369
000-001KY 70
(MP 0.000)Approach to the Ferry (MP 0.626)0.62613
KY 403RSButlerFE01 016 0403
000-016US 231
(MP 0.000)End of State Maintenance (MP 16.031)16.03142338
KY 411RSButlerFE01 016 0411
000-009KY 70
(MP 0.000)Grayson County Line (MP 8.822)8.822223
KY 626RSButlerFE01 016 0626
000-009KY 1153
(MP 0.000)Warren County Line (MP 8.583)8.583253
KY 949RSButlerFE01 016 0949
000-003Muhlenburg County Line (MP 0.000)KY 106
(MP 2.894)2.89463
KY 1038RSButlerFE01 016 1038
000-002Warren County Line (MP 0.000)KY 1083
(MP 1.703)1.70323
Route
NumberSystemCountyProject
NumberFROMTOLength
(Miles)Mowing
Acresof

Cycles

KY 1083RSButlerFE01 016 1083
000-007Warren County Line (MP 0.000)US 231
(MP 6.927)6.927233
KY 1117RSButlerFE01 016 1117
000-011KY 369
(MP 0.000)KY 70
(MP 10.516)10.516223
KY 1118RSButlerFE01 016 1118
000-004US 231
(MP 0.000)Ohio County Line (MP 3.825)3.825103
KY 1153RSButlerFE01 016 1153
000-016Logan County Line (MP 0.000)KY 79
(MP 15.166)15.16647336
KY 1187RSButlerFE01 016 1187
000-007KY 106
(MP 0.000)KY 1153
(MP 6.289)6.28983
KY 1328RSButlerFE01 016 1328
000-012US 231
(MP 0.000)KY 70
(MP 11.689)11.68949328
KY 1435RSButlerFE01 016 1435
000-002Warren County Line (MP 0.000)US 231
(MP 1.850)1.85033
KY 1468RSButlerFE01 016 1468
000-002KY 70
(MP 0.000)US 231
(MP 1.101)1.10133
KY 2266RSButlerFE01 016 2266
000-005Beginning of State Maintenance (MP 0.000)KY 1328
(MP 4.134)4.13463
KY 2267RSButlerFE01 016 2267
000-005KY 1153
(MP 0.000)KY 70
(MP 4.426)4.426103
KY 2269RSButlerFE01 016 2269
000-004KY 1118
(MP 0.000)KY 2713
(MP 3.365)3.36553
KY 2713RSButlerFE01 016 2713
000-007KY 79
(MP 0.000)Ohio County Line (MP 6.054)6.054143
KY 3182RSButlerFE01 016 3182KY 79KY 10833.78773
000-004(MP 0.000)(MP 3.787)
Route
NumberSystemCountyProject
NumberFROMTOLength
(Miles)Mowing
Acresof

Cycles

KY 3205RSButlerFE01 016 3205
000-003KY 1187
(MP 0.000)KY 70
(MP 2.708)2.70863
Subtotal RS139.300342
GRAND TOTAL229.509608528
Maximum time to complete a cycle: 12 working days.