Wilderness State Park National Guard Projects Horizontal Materials Bid Calculation.xlsx

XLSX spreadsheet 15 KB Posted

Attached to
Wilderness State Park Aggregate - Air National Guard Project
Solicitation number
RFQ - 751 - 240000000371
Issued by
Emmet County, Michigan

About this file

This document is an Excel spreadsheet detailing the cubic yard quantities and material types required for several horizontal construction projects at Wilderness State Park in Michigan's Emmet County. The projects include a pondside trail, dining hall, playground, loading dock, and cabins, with a total of 1,548 cubic yards of 21AA limestone, 218 cubic yards of limestone fines, 90 cubic yards of screened topsoil, 35 cubic yards of pea stone, and 10 cubic yards of sand required. Deliveries are scheduled between April 29 and May 15, with a maximum of 600 tons per delivery and 24-hour notice required due to limited storage space. The spreadsheet provides the conversion factors from cubic yards to tons and requires the bidder to enter the price per ton for each material in the corresponding line in the SIGMA VSS system, which will then calculate the total cost. The spreadsheet also includes lump sum delivery fee information, with separate delivery locations for the Big Stone Bay area, Waugoshance Point area, and the Lakeview and Lakeshore Drives parking lot within Wilderness State Park.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Aggregate

ProjectMDOT 21AA
CYDsLimestone Fines
CYDsScreened Topsoil
CYDsPea Stone
CYDsSand

CYDS

Pondside Trail38520060
Dining Hall/BH331810303510
Playground158
Loading Dock10
Big Stone Cabin300
Caps300
Waugoshance70
Sturgeon Bay Lot150230
Total Cubic Yards1548218903510
Yards to Tons Factor1.51.31.21.41.25
Estimated Tons2,350.003001505012.5
Price per Ton
Materials Cost
$ per Train
Number of trains
Delivery Fee
Total Cost$ - 0$ - 0$ - 0$ - 0$ - 0total$ - 0
3000lbs/yrd2600 lbs./yrd2400 lbs/yrd2800lbs/yrd2500 lbs/yrd
Do not make changes to the Yards to Ton converstions on this spreadsheet
Complete area of spreadsheet highlighted in yellow.
Delivery between April 29 and May 15.
Due to limited storage space, deliveries will be ON-CALL with 24-hour notice. Up to 600 tons per delivery.
Enter the PRICE PER TON in the corresponding line in SIGMA VSS. SIGMA will calculate the total. Enter the LUMP SUM total for Trucking & Delivery Fees.
Delivery for the projects highlighted in Green will be to the Big Stone Bay area of Wilderness State Park
Delivery for the projects highlighted in Red will be to the Waugoshance Point area west of Big Stone Bay of Wilderness State Park