WI 7 Spec.pdf
PDF 245 KB Posted
- Attached to
- USCGC William Hart Dockside Sewage Flush
- Solicitation number
- 70Z03426QHONO1006
About this file
This is a Performance Work Statement for Work Item 7 (Sewage and Grey Water System, Clean and Inspect) under the USCGC William Hart (WPC-1134) and USCGC Joseph Gerczak (WPC-154) Dockside Availability FY2026 contract. The Contractor is required to clean and inspect the complete sewage and grey water systems, including tanks, piping, pumps, valves, vent lines, and related components. The scope involves removing all obstructions, clogs, uric scale, and waste build-up from interior surfaces to ensure unobstructed flow of waste solids and fluids. The Contractor must submit a detailed cleaning plan within 7 days of the arrival conference containing qualified personnel lists, Safety Data Sheets for all proposed chemicals, step-by-step cleaning procedures, and locations of minimum 3 separate sewage system and 3 separate grey water system clean-out points for verification inspections. Chemical cleaning using biodegradable sewage/grey-water system descaler is recommended for piping, while mechanical cleaning methods (pressure washing, flexible auger cleaning) are suggested for grey water system piping. Government-furnished property includes Sewage Tank Zinc Anodes (NIIN: 014474686, Quantity: 2, Estimated Cost: $142.19/unit).
The Contractor must perform operational pre-testing to establish baseline conditions, open and inspect the grey water tank coating system pre-cleaning, and clean interior tank surfaces (Grey Water Tank 3-17-0-W, Sewage Holding Tank 2-4-0-W, and vacuum accumulation tank) until free of all foreign materials and sludge. Post-cleaning inspections require borescope verification of piping interiors in the presence of the Contracting Officer Representative (COR), with all solid deposits removed to the naked eye. All disturbed soft components must be renewed, and zinc anodes with more than 50% material loss must be replaced using Government-furnished property. Leak testing post-repairs includes 5-minute water runs through grey water piping, 20-minute vacuum hold tests with specified pressure ranges (-0.40 to -0.55 bar), smoke leak testing on vacuum portions where mechanical joints were disturbed, and tank pressurization testing. The Contractor must provide temporary sanitary facilities if service is disrupted, temporary HVAC if the cleaning plan degrades climate control, and may utilize Coast Guard pier facility tanks for sewage disposal per Table 1 designation, or provide contractor-furnished disposal facilities. All sewage system contents and cleaning materials must be disposed of in accordance with Federal, state, and local regulations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SFLC-ESD-25_Tank_and_Void_Assessment_Form.pdf | ||
| SFLC-Std-Spec-6310-(2022).pdf | ||
| SFLC-Std-Spec-0000-(2022).pdf | ||
| dockside SOW.docx | DOCX document | |
| Fixed_Price_Service_FAR_HSAR_Clauses.docx | DOCX document | |
| drawings.zip | ZIP file | |
| SF1449.pdf | ||
| Wage Determination Honolulu.txt | TXT text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC WILLIAM HART (WPC-1134) DOCKSIDE AVAILABILITY FY2026
59301_JLW_0523_154WPC
WORK ITEM 7: Sewage and Grey Water System, Clean and Inspect
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean the sewage and grey water system (e.g. tanks, piping, etc.).
TABLE 1
USE OF COAST GUARD SEWAGE AND GREY WATER DISPOSAL FACILITIES
(PARA 3.3.5.2)
NO
1.2 Government-furnished property.
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
N **Sewage Tank Zinc Anode NIIN: 014474686 2 142.19
*Government-loaned property, which must be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT Service Center.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 154 WPC 127-302, Rev C, Potable Water & Sewage Tank Fabrication Details
Coast Guard Drawing 154 WPC 506-201, Rev A, Fills Vents, Sounds, and Overflows
Coast Guard Drawing 154B WPC 506-201, Rev A, Fills Vents, Sounds, and Overflows
Coast Guard Drawing 154 WPC 506-301, Rev -, Fills, Vents, Sounds, Overflows Diagram
Coast Guard Drawing 154 WPC 528-301, Rev B, Grey Water System Diagram
Coast Guard Drawing 154 WPC 593-201, Rev F, Sewage System Arrangement
Coast Guard Drawing 154 WPC 593-301, Rev C, Sewage System Diagram
Coast Guard Drawing 154B WPC 593-201, Rev A, Sewage System Arrangement
Coast Guard Drawing 154B WPC 593-301, Rev -, Sewage System Diagram
Coast Guard Drawing 154 WPC 593-303, Rev A, Sewage Control System
Coast Guard Drawing 154 WPC 601-302, Rev D, General Arrangement
Coast Guard Drawing 154B WPC 601-302, Rev -, General Arrangement
Coast Guard Drawing 154 WPC 633-301, Rev C, Cathodic Protection System
USCGC JOSEPH GERCZAK (WPC-154) DOCKSIDE AVAILABILITY FY2026
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
OTHER REFERENCES
ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):
3.2.1 Inspection of Grey Water Tank.
3.1.2 Tech Rep.
None.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).
3.1.5 Temporary Sanitary and Sewage Facilities. Whenever sewage or grey water collection service is disrupted due to Contractor repairs, the Contractor must provide temporary facilities in accordance with SFLC Standard Spec 0000 par 3.2.11.
3.1.6 Temporary HVAC. If the C cleaning plan will degrade continuous operation of must provide temporary ventilation to all impacted areas equivalent to the normal zonal ventilation rating for those spaces (i.e. maintain existing climate control) for the duration of work as described in SFLC Std Spec 0000.
3.1.7 Refer to all references beneath section 2 above, as applicable.
NOTE
Be aware that the grey water system has few isolation valves and many openings that must be plugged or blanked to contain cleaning media.
Be aware that AC condensate drains into the Grey Water Tank at 8 separate locations. Any temporary disruption or degradation of climate control must be fully addressed by the cleaning plan.
For these reasons, based on lessons learned, it is suggested that chemical cleaning be used on sewage piping and grey water system piping be cleaned mechanically (e.g. waterjetting, etc.)
3.1.8 Cleaning Plan. No later than 7 days after the arrival conference, and prior to the start of cleaning work, the Contractor must submit a cleaning plan CFR that contains the following:
A list of qualified personnel who will disassemble machinery or handle chemicals.
An SDS for every chemical proposed for use.
A step by step description of the procedures and methods that will be used to clean the systems
A list of locations in the sewage and grey water piping system where piping lines will be opened and components will be removed. At a minimum the piping must be opened at 3 separate sewage system clean-out locations and 3 separate grey water system clean-out to verify cleaning was adequately performed. These locations must be pre-approved by the COR and included in the cleaning plan CFR.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.2 Operational test and inspection - initial. Prior to commencement of cleaning work, the Contractor must witness Coast Guard personnel perform an operational pre-test of all items and shipboard devices to be disturbed, used, repaired, or altered, (e.g. TLIs, pumps, etc.) to demonstrate existing operational condition and to determine a more precise scope of cleaning required. Submit a CFR detailing any required growth work or repairs identified during the operational test based on the observed condition of the systems. Use the most economical methods for accomplishing the work.
3.2.1 Inspection of Grey Water Tank. Open and inspect the grey water tank to determine the condition of the grey water tank coating system to the greatest extent practicable, pre-cleaning. Submit a CIR detailing the condition of the grey water tank coating system and any noted discrepancies, include an estimated square footage of failed coating in the CIR.
3.3 Cleaning and Inspection Requirements. he Contractor
must below. Clean, in their entirety, all sewage and grey water system interior surfaces (e.g. sewage and grey water ppg interiors, pump interiors, valve interiors, all sewage and grey water tank vent lines interiors, sewage vacuum switch manifold interiors, fire main sprinkler pipe interiors and spray hole interiors in main sewage tank used to flush sewage tank, overboard/to shore connection discharge pump and all related valve and pipe interiors, etc.) that may come in contact with sewage or grey-water, by removing all obstructions, clogs, uric scale, and waste build-up on piping and component interiors, ensuring subsequent free unobstructed flow of waste solids and fluids.
NOTE
Depending on the condition of the system at the contract start date, chemical cleaning may not adequately remove all obstructions, scale, and build-up present. More intrusive cleaning methods, such as pressure washing, flexible auger cleaning, or other mechanical means of cleaning, may be required to remove all obstructions, scale, etc. These more intrusive methods are in scope of this work item and the Contractor may be required to use one or more them, in the appropriate quantities, to achieve minimum cleaning requirements.
NOTE
Before filling a system with descaler ensure all openings below the fill point are blanked off or plugged.
3.3.1 Chemical Cleaning of Piping. When chemically cleaning piping and component interiors use a commercially available biodegradable sewage/grey-water system descaler (e.g. SEW CLEAN, etc.) safe for use on stainless steel. Fill the systems with descaler and hold for a long enough period to clean the systems as described above. After cleaning is complete drain and dispose of all sewage and grey water system contents.
3.3.2 Tank Cleaning. Interior surfaces of the Grey Water Tank 3-17-0-W, Sewage Holding Tank 2-4-0- W, and sewage vacuum accumulation tank must be cleaned until free of all foreign materials, sediment, and sludge. Remove all persistent residues, residual wash media, and moisture with clean lint-free cloths.
Remove, clean, and re-install all tank interior components (e.g. TLIs, limit switches, eductors, etc.).
Renew all sewage tank and grey water tank zinc anodes that have lost more than 50% of their material using Government-furnished property, otherwise reuse the existing zinc anodes. Remove and dispose of all sewage system contents and collect, contain, and dispose of all wash media and cleaning materials in accordance with all applicable Federal, state, and local regulations. Remove all unused chemicals from USCG property immediately upon completion of work item.
3.3.3 Inspections. After cleaning, inspect the piping interior using a borescope in the presence of the COR, verify that all solid deposits, visible to the unmagnified eye, have been removed. Visually inspect all system components (e.g. TLIs, limit switches, pressure switches, tank interior surfaces, fasteners, gasket seating surfaces, manhole cover surfaces, etc.)
for excessive wear, damage, and all other notable discrepancies. Open and vacuum-clean the control panel assembly and inspect for any indications of overheating or loose wiring or connections. Submit a
CFR.
3.3.4 Miscellaneous. Do not drain any fluids (e.g. sewage, grey water, fresh water, etc.) into any space, bilge, or exterior location. Take all precautions required to prevent contamination of personnel and spaces in accordance with all applicable Federal, state, and local regulations. Renew all disturbed soft components (e.g. seals, gaskets, o-rings, etc.). Do not use the sewage pump installed in the system to offload sewage system contents.
3.3.4.1 Plug log. Plug all unattended openings in the system. Plugs must be fitted with a lanyard, ring or other device to prevent loss of the plug inside the system. Create and maintain a written log of each plug that specifies the location of each. Remove and dispose of all plugs upon completion of work. Furnish the plug log to the Coast Guard Inspector during the performance of close-out inspections.
3.3.4.2 Use of Coast Guard Sewage and Grey Water Disposal Facilities denoted in Table 1 (Use of Coast Guard Sewage and Grey Water Disposal Facilities), beneath paragraph 1.1 (Intent), the Contractor may offload and dispose sewage and grey water system contents into the Coast Guard pier facility tanks in lieu of a Contractor furnished tank truck, otherwise the Contractor must dispose of all waste using the C
3.4 Closing tanks. The Contractor must notify the COR at least 24 hours prior to closing the tank. After completion of all authorized repairs and after the COR inspects all work performed, close the tanks.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.5 Operational test post repairs. After completion of work, the Contractor must thoroughly test all disturbed components and systems and accomplish the following tasks in conjunction with each other as appropriate, in the presence of the Coast Guard Inspector, and submit a CFR:
3.5.1 Adjust the set point on each of the vacuum pressure switches (as applicable) to the set points noted previously.
3.5.2 Verify operation of the low and high level switches/alarms and that the pumps cycle from lead to lag status during operation. Demonstrate proper operation of tank TLIs to prove satisfactory operating condition.
3.5.3 Leak test. After all system components are reinstalled, the Contractor must test all disturbed piping for leaks, as follows:
Run water down all disturbed grey water system piping runs for 5 minutes.
Ensure the system holds vacuum without cycling for at least 20 mins.
Place both vacuumarator selection switches in the "RUN" position. Allow vacuumarator pump to run until system operating pressure of -0.40 to -0.55 bar is reached. Observe vacuum tank pressure gauge. Place both vacuumarator selection switches in the "OFF" position. (NOTE: A vacuum loss of more than 0.14 bar indicates an air leak exists in the system.) Verify vacuum system pressure remains between -0.40 to -0.55 bar for 20 minutes.
Record pressure value and include in the CFR.
Perform smoke leak test on vacuum portions of the sewage system where the Contractor has disturbed a mechanical joint.
Closely monitor the systems for leaks. Repair all leaks detected. Repeat test and inspection tasks until no leaks are detected.
3.5.4 Upon completion of testing and, in the presence of the Coast Guard Inspector, pump tanks to the
4. NOTES
This section is not applicable to this work item.
File details come from the government source that posted it. Updated .