WFLHD Construction Contract Administration_2.2.2023.pdf
PDF 117 KB Posted
- Solicitation number
- 69056723R000009
About this file
This document contains data on the Federal Highway Administration's (FHWA) past performance in definitizing equitable adjustments for change orders under construction contracts. For the past three fiscal years, the majority of change order proposals were definitized within 90 days of receipt of an adequate proposal. In FY 2020, 4 proposals took over 366 days to definitize and in FY 2021, 2 proposals took over 366 days to definitize. No proposals took over 366 days to definitize in FY 2022. The related federal contract opportunity is a solicitation from the Department of Transportation Federal Highway Administration for pavement preservation work on Pinnacles in California under solicitation number 69056723R000009.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| QA_08-22-2023.pdf | ||
| QA_08-18-2023.pdf | ||
| Amendment A002.pdf | ||
| Amendment A001.pdf | ||
| PINN_C6_Final_Report.pdf | ||
| FLH Bridge oversized or overload vehicle permit request form Oct 2018.pdf | ||
| CA NP PINN PMS(1)_plans.pdf | ||
| RFP 69056723R000009.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WFLHD Construction Contract Administration
FAR 36.211 requires a description of the Federal Highway Administration’s (FHWA) procedures that apply to definitization of equitable adjustments for change orders under construction contracts. It also requires that FWHA furnish data on the agency’s past performance, for the prior 3 fiscal years, regarding the time required to definitize equitable adjustments for change orders under construction contracts.
Change orders as defined in FAR 2.101 are changes to the contract work pursuant to FAR 52.243-4, Changes.
There are no agency-specific additional policies and procedures that exist at this time.
The table below contains data regarding the definitization of equitable adjustments for change orders under construction contracts by fiscal year (FY).
Time to definitize after receipt of an adequate change order definitization proposal under construction contracts
Number of change order proposals definitized under construction contracts
FY 2020 FY 2021 FY 2022
0 to 30 days 0 1 1
31 to 60 days 3 1 0
61 to 90 days 0 0 0
91 to 180 days 0 5 1
181 to 365 days 0 0 7
366 or more days 4 2 0
After completion of contract performance via a contract modification addressing all undefinitized equitable adjustments received during contract performance
0 0 0 https://www.acquisition.gov/far/part-52#FAR_52_243_4
File details come from the government source that posted it. Updated .