About this file

The document is a comprehensive bid specification for the Westcott Lot Retaining Wall Replacement Project issued by the City of Oneonta, New York, with engineering services provided by Herrmann Engineering, PLLC. The project involves replacing an existing multi-wythe CMU retaining wall at the Westcott Parking Lot, including installation of new concrete stairs connecting the parking lot to Main Street, new aluminum railing along the wall top, and miscellaneous infrastructure improvements such as sidewalk, curb, and asphalt replacement. Sealed bids will be received until 2:00 p.m. on June 19, 2025, with a pre-bid meeting scheduled for June 12, 2025, at City Hall. The construction work is scheduled to begin in late June 2025 and be completed by mid-October 2025, with substantial completion targeted for October 3, 2025, and final completion by October 17, 2025.

The project has a 5% bid guarantee requirement, and bidders must comply with New York State wage rates, Labor Law 220, and OSHA 10-hour construction safety certification. The City encourages bids from Minority-owned, Women-owned, and Disadvantaged Business Enterprises. Contractors must provide workers' compensation documentation and are subject to specific insurance requirements. The contract documents are available for a $5 non-refundable fee and can be obtained from the Purchasing Department or downloaded from www.govbids.com. Liquidated damages are set at $500 per day for delays in substantial completion and final completion. The project will be funded through municipal channels, with potential oversight from state agencies, and requires compliance with various local and state regulations.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

City of Oneonta

CONTRACT #2024-G-006

WESTCOTT LOT RETAINING WALL REPLACEMENT PROJECT

MARK DRNEK

Mayor

Elayne Mosher-Campoli Len Carson 1st Ward Council Member 5th Ward Council Member

Cecilia Walsh-Russo Scott Harrington 2nd Ward Council Member 6th Ward Council Member

Shannon McHugh Michael Forster Rothbart 3rd Ward Council Member 7th Ward Council Member

Kaytee Lipari Shue Don Mathisen 4th Ward Council Member 8TH Ward Council Member

Greg Mattice, PE City Administrator

Christopher Yacobucci Public Works Director

Gino Huggins

Assistant City Engineer

David Merzig City Attorney

MAY 2025

SET # 1

THIS PAGE INTENTIONALLY LEFT BLANK

PROCUREMENT AND CONTRACTING REQUIREMENTS

GROUP

City of Oneonta 2024-G-006

Westcott Parking Lot Retaining Wall Replacement Project May 29, 2025 Herrmann Engineering, PLLC

TABLE OF CONTENTS 000110 - 1

Volume 1 of 1

Procurement and Contracting Requirements Group

Division 00 - Procurement and Contracting Requirements

Introductory Information

• Table of Contents

Procurement Requirements

• Invitation to Bidders

• Instructions to Bidders – EJCDC C200 2018

Procurement Forms and Supplements – To be submitted at Bid Submission

• Bid Form – EJCDC C410 2018

• Bid Security Form

• Certification of nonsegregated facilities

• Non-collusion affidavit of Prime Bidder

• Non-collusion bidding certification

• Certification of compliance with the Iran divestment act

• Certificate as to corporate principal

• Form of surety guaranty

• Equal Opportunity Clause

• Hold Harmless Clause

Contracting Requirements

• General Conditions – EJCDC C700 2018

• Supplementary Conditions – EJCDC C800 2018

• Performance Bond

• Payment Bond

• Notice of Award

• Notice to Proceed

• Contractual Agreement – EJCDC C520 2018

• Work Change Directive – EJCDC C940 2018

• Change Order – EJCDC 941 2018

• Field Order – EJCDC 942 2018

• Prevailing Wage Schedule

• Insurance Agreement - Contractors

City of Oneonta 2024-G-006

Westcott Parking Lot Retaining Wall Replacement Project May 29, 2025 Herrmann Engineering, PLLC

TABLE OF CONTENTS 000110 - 2

Specifications Group

Division 01 – General Requirements

011000 Summary

011200 Contract Summary – Bid Item Descriptions

012600 Contract Modification Procedures

013300 Submittal Procedures

016000 Product Requirements

017419 Construction Waste Management and Disposal

017700 Closeout Procedures

017839 Project Record Documents

Division 02 – Existing Conditions

024119 Selective Demolition

Division 03 – Concrete

032000 Concrete Reinforcement

033000 Cast-in-place Concrete

Division 05 – Metals

057300 Decorative Metal Railings

Division 31 – Earthwork

312000 Earthmoving

312100 Excavation and Trenching

Division 32 – Exterior Improvements

321216 Asphalt Paving

329219 Seeding

321723 Pavement Markings

INVITATION FOR BIDS

NOTICE IS HEREBY GIVEN, pursuant to Article 5A of the General Municipal Law of the State of New York that sealed bids are sought by

THE CITY OF ONEONTA, NEW YORK

For:

WESTCOTT LOT RETAINING WALL REPLACEMENT PROJECT

Contract #2024-G-006

Sealed bids will be received by the Purchasing Agent, John Janitz, at his office at City Hall, 258 Main Street, Oneonta, New York, until 2:00 p.m., June 19, 2025 at which time bids will be publicly opened, and read.

Contract Documents and Specifications, are on file at 258 Main Street, Oneonta, New York 13820, Office of the Purchasing Agent. Copies of the Contract Documents may be obtained from the Purchasing Department during regular office hours or will be mailed to bidders on request. A $5 non-refundable fee to be charged for mailing each set when mailing is requested. All checks, money orders, etc., shall be made payable to the City of Oneonta.

Specifications are also available on the Internet at www.govbids.com under Empire State Purchasing Group.

A pre-bid meeting will be held and will be optional. The pre-bid meeting will be held at City Hall, 258 Main Street, Oneonta, New York, at 10:00 a.m., June 12, 2025. Bidders are encouraged to attend and a site visit will follow after the meeting.

Addenda, if any, will be issued to only those persons whose name and address are on record with the Owner as having obtained the Contract Documents.

At the bid opening the Contractor must supply a BID GUARANTEE of 5 percent of the TOTAL AMOUNT of the bid submitted. See Item 6 in Instructions to Bidders.

Attention is called to the fact that not less than the minimum salaries and wages set forth in the Contract Documents (see Exhibits) must be paid on this project; that the Contractor must insure that employees and applicants for employment are not discriminated against because of their race, creed, color, religion, sex or national origin. The Contractor must also be aware that he must comply with the State wage rates under New York State Department of Labor PRC# 2025006118, as well as Labor Law 220, section 220-h, which requires that on all public work projects of at least $250,000.00, all laborers, workers and mechanics on the site be certified as having successfully completed the OSHA 10-hour construction safety and health course.

The Contractor must also be aware that in conformance with Workers’ Compensation Law §57, contractor must provide either form CE-200 (Certificate of Attestation of Exemption from NYS Workers’ Compensation and/or Disability Benefits Coverage), or form C-105.2 (Certificate of Workers’ Compensation Insurance), or form SI-12 (Certificate of Workers’ Compensation Self- Insurance) http://www.wcb.state.ny.us/content/main/Employers/IM.pdf before Notice to Proceed can be issued.

Bidders are responsible for the timely delivery of their Bid proposal to the proper department as indicated in this "Invitation to Bid".

Bid proposals received after the date and time specified in the Invitation shall be considered unresponsive and will be returned to the Bidder unopened. The City of Oneonta does not accept bids by Fax or Email.

Bidders are advised not to rely on the Postal Service or any other mail delivery service for the timely and proper delivery of their bid proposals. In the event of a tie bid, the winning bid will be determined by a coin toss, as stated in the City of Oneonta’s Purchasing Policy.

The City of Oneonta encourages the submission of bids by companies that are certified as Minority-owned, Women-owned and Disadvantaged Business Enterprises.

The Owner reserves the right to reject any and all Bids or waive any informality in the Bidding.

Bids may be held by the Owner for a period not to exceed forty-five (45) days from the date of the openings of Bids for the purpose of reviewing the Bids and investigate the qualifications of the Bidders, prior to awarding the Contract.

This Contract is subject to New York State wage rate schedules.

Date: May 27, 2025

John Janitz Purchasing Agent City of Oneonta, New York

EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

TOC Page1 of 1

INSTRUCTIONS TO BIDDERS FOR CONSTRUCTION CONTRACT

TABLE OF CONTENTS

Page

Article 1— Defined Terms

Article 2— Bidding Documents

Article 3— Qualifications of Bidders

Article 4— Pre-Bid Conference

Article 5— Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;

Other Work at the Site

Article 6— Bidder’s Representations and Certifications

Article 7— Interpretations and Addenda

Article 8— Bid Security

Article 9— Contract Times

Article 10— Substitute and “Or Equal” Items

Article 11— Subcontractors, Suppliers, and Others

Article 12— Preparation of Bid

Article 13— Basis of Bid

Article 14— Submittal of Bid

Article 15— Modification and Withdrawal of Bid

Article 16— Opening of Bids

Article 17— Bids to Remain Subject to Acceptance

Article 18— Evaluation of Bids and Award of Contract

Article 19— Bonds and Insurance

Article 20— Signing of Agreement

Article 21— Sales and Use Taxes

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ARTICLE 1—DEFINED TERMS

1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:

A. Issuing Office—The office from which the Bidding Documents are to be issued, and which registers plan holders.

ARTICLE 2—BIDDING DOCUMENTS

2.01 Bidder shall obtain a complete set of Bidding Requirements and proposed Contract Documents

(together, the Bidding Documents). See the Agreement for a list of the Contract Documents. It is

Bidder’s responsibility to determine that it is using a complete set of documents in the preparation of a Bid. Bidder assumes sole responsibility for errors or misinterpretations resulting from the use of incomplete documents, by Bidder itself or by its prospective Subcontractors and Suppliers.

2.02 Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for plan holders to print documents solely for their use, and the use of their prospective Subcontractors and Suppliers, provided the plan holder pays all costs associated with printing or reproduction. Printed documents may not be re-sold under any circumstances.

2.03 Owner has established a Bidding Documents Website as indicated in the Advertisement or invitation to bid. Owner recommends that Bidder register as a plan holder with the Issuing Office at such website, and obtain a complete set of the Bidding Documents from such website. Bidders may rely that sets of Bidding Documents obtained from the Bidding Documents Website are complete, unless an omission is blatant. Registered plan holders will receive Addenda issued by

Owner.

2.04 Electronic Documents

A. When the Bidding Requirements indicate that electronic (digital) copies of the Bidding

Documents are available, such documents will be made available to the Bidders as Electronic

Documents in the manner specified.

1. Bidding Documents will be provided in Adobe PDF (Portable Document Format) (.pdf) that is readable by Adobe Acrobat Reader. It is the intent of the Engineer and Owner that such Electronic Documents are to be exactly representative of the paper copies of the documents. However, because the Owner and Engineer cannot totally control the transmission and receipt of Electronic Documents nor the Contractor’s means of reproduction of such documents, the Owner and Engineer cannot and do not guarantee that Electronic Documents and reproductions prepared from those versions are identical in every manner to the paper copies.

B. Unless otherwise stated in the Bidding Documents, the Bidder may use and rely upon complete sets of Electronic Documents of the Bidding Documents, described in

Paragraph 2.06.A above. However, Bidder assumes all risks associated with differences arising from transmission/receipt of Electronic Documents versions of Bidding Documents

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

and reproductions prepared from those versions and, further, assumes all risks, costs, and responsibility associated with use of the Electronic Documents versions to derive information that is not explicitly contained in printed paper versions of the documents, and for Bidder’s reliance upon such derived information.

ARTICLE 3—QUALIFICATIONS OF BIDDERS

3.01 To demonstrate Bidder’s qualifications to perform the Work, after submitting its Bid and within seven days of Owner’s request, Bidder must submit the following information:

A. Written evidence establishing its qualifications such as financial data, previous experience, and present commitments.

B. A written statement that Bidder is authorized to do business in the state where the Project is located, or a written certification that Bidder will obtain such authority prior to the

Effective Date of the Contract.

C. Bidder’s state or other contractor license number, if applicable.

D. Subcontractor and Supplier qualification information.

E. Other required information regarding qualifications.

3.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.

3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.

ARTICLE 4—PRE-BID CONFERENCE

4.01 A pre-bid conference is identified on the Invitation for Bids. Attendance is not required to submit a bid, but is recommended.

ARTICLE 5—SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S

SAFETY PROGRAM; OTHER WORK AT THE SITE

5.01 Site and Other Areas

A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

5.02 Existing Site Conditions

A. Subsurface and Physical Conditions; Hazardous Environmental Conditions

1. The Supplementary Conditions identify the following regarding existing conditions at or adjacent to the Site:

a. Those reports of explorations and tests of subsurface conditions at or adjacent to the Site that contain Technical Data.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

b. Those drawings known to Owner of existing physical conditions at or adjacent to the Site, including those drawings depicting existing surface or subsurface structures at or adjacent to the Site (except Underground Facilities), that contain

Technical Data.

c. Reports and drawings known to Owner relating to Hazardous Environmental

Conditions that have been identified at or adjacent to the Site.

d. Technical Data contained in such reports and drawings.

2. Owner will make copies of reports and drawings referenced above available to any

Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the

Supplementary Conditions. Bidder is responsible for any interpretation or conclusion

Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.

3. If the Supplementary Conditions do not identify Technical Data, the default definition of

Technical Data set forth in Article 1 of the General Conditions will apply.

B. Underground Facilities: Underground Facilities are shown or indicated on the Drawings, pursuant to Paragraph 5.05 of the General Conditions, and not in the drawings referred to in

Paragraph 5.02.A of these Instructions to Bidders. Information and data regarding the presence or location of Underground Facilities are not intended to be categorized, identified, or defined as Technical Data.

5.03 Other Site-related Documents

A. No other Site-related documents are available.

5.04 Site Visit and Testing by Bidders

A. Bidders visiting the Site are required to arrange their own transportation to the Site.

B. On request, and to the extent Owner has control over the Site, and schedule permitting, the

Owner will provide Bidder general access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site. Bidder is responsible for establishing access needed to reach specific selected test sites.

C. Bidder must comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.

D. Bidder must fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

5.05 Owner’s Safety Program

A. Site visits and work at the Site may be governed by an Owner safety program. If an Owner safety program exists, it will be noted in the Supplementary Conditions.

5.06 Other Work at the Site

A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the

Site by Owner or others (such as utilities and other prime contractors) and relates to the

Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.

ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS

6.01 Express Representations and Certifications in Bid Form, Agreement

A. The Bid Form that each Bidder will submit contains express representations regarding the

Bidder’s examination of Project documentation, Site visit, and preparation of the Bid, and certifications regarding lack of collusion or fraud in connection with the Bid. Bidder should review these representations and certifications, and assure that Bidder can make the representations and certifications in good faith, before executing and submitting its Bid.

B. If Bidder is awarded the Contract, Bidder (as Contractor) will make similar express representations and certifications when it executes the Agreement.

ARTICLE 7—INTERPRETATIONS AND ADDENDA

7.01 Owner on its own initiative may issue Addenda to clarify, correct, supplement, or change the

Bidding Documents.

7.02 Bidder shall submit all questions about the meaning or intent of the Bidding Documents to

Engineer in writing. Contact information and submittal procedures for such questions are as follows:

A. Gino Huggins – Senior Civil Engineer – City of Oneonta.

1. Email: ghuggins@oneonta.ny.us

B. Alex Herrmann, PE, SE – Principal Engineer – Herrmann Engineering, PLLC

1. Email: alex@herrmannengineeringpllc.com

7.03 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all registered plan holders. Questions received less than seven days prior to the date for opening of Bids may not be answered.

7.04 Only responses set forth in an Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Responses to questions are not part of the Contract

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Documents unless set forth in an Addendum that expressly modifies or supplements the Contract

Documents.

ARTICLE 8—BID SECURITY

8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of five percent of Bidder’s maximum Bid price (determined by adding the base bid and all unit prices) and in the form of a Bid bond issued by a surety meeting the requirements of Paragraph 6.01 of the General

Conditions. Such Bid bond will be issued in the form included in the Bidding Documents. Bid security must be at least 5% of the Bidder’s maximum Bid price.

8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract, furnished the required

Contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract and furnish the required Contract security within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited, in whole in the case of a penal sum bid bond, and to the extent of Owner’s damages in the case of a damages-form bond. Such forfeiture will be Owner’s exclusive remedy if

Bidder defaults.

8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of 7 days after the Effective Date of the

Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.

8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within 7 days after the Bid opening.

ARTICLE 9—CONTRACT TIMES

9.01 The number of days within which, or the dates by which, the Work is to be (a) substantially completed and (b) ready for final payment, and (c) Milestones (if any) are to be achieved, are set forth in the Agreement. For reference, the following dates are critical:

1. Substantial Completion: October 3, 2025.

2. Final Completion: October 17, 2025.

9.02 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial

Completion, or completion of the Work in readiness for final payment, are set forth in the

Agreement.

ARTICLE 10—SUBSTITUTE AND “OR EQUAL” ITEMS

10.01 All prices that Bidder sets forth in its Bid will be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of

“or-equal” or substitution requests are made at Bidder’s sole risk.

ARTICLE 11—SUBCONTRACTORS, SUPPLIERS, AND OTHERS

11.01 If requested by Owner, such list must be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such

Subcontractor or Supplier. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor or Supplier, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, in which case apparent

Successful Bidder will submit a substitute, Bidder’s Bid price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Bids and making the Contract award.

11.02 If apparent Successful Bidder declines to make any such substitution, Owner may award the

Contract to the next lowest Bidder that proposes to use acceptable Subcontractors and Suppliers.

Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor or Supplier, so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in

Paragraph 7.07 of the General Conditions.

11.05 – The Contractor shall not award work to Subcontractor(s) in excess of the limits stated in SC

7.07A.

ARTICLE 12—PREPARATION OF BID

12.01 The Bid Form is included with the Bidding Documents.

A. All blanks on the Bid Form must be completed in ink and the Bid Form signed in ink. Erasures or alterations must be initialed in ink by the person signing the Bid Form. A Bid price must be indicated for each section, Bid item, alternate, adjustment unit price item, and unit price item listed therein.

B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words “No Bid” or “Not Applicable.”

12.02 If Bidder has obtained the Bidding Documents as Electronic Documents, then Bidder shall prepare its Bid on a paper copy of the Bid Form printed from the Electronic Documents version of the

Bidding Documents. The printed copy of the Bid Form must be clearly legible, printed on 8½ inch by 11-inch paper and as closely identical in appearance to the Electronic Document version of the

Bid Form as may be practical. The Owner reserves the right to accept Bid Forms which nominally vary in appearance from the original paper version of the Bid Form, providing that all required information and submittals are included with the Bid.

12.03 A Bid by a corporation must be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation must be shown.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

12.04 A Bid by a partnership must be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership must be shown.

12.05 A Bid by a limited liability company must be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm must be shown.

12.06 A Bid by an individual must show the Bidder’s name and official address.

12.07 A Bid by a joint venture must be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture must have been formally established prior to submittal of a Bid, and the official address of the joint venture must be shown.

12.08 All names must be printed in ink below the signatures.

12.09 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Bid Form.

12.10 Postal and e-mail addresses and telephone number for communications regarding the Bid must be shown.

12.11 The Bid must contain evidence of Bidder’s authority to do business in the state where the Project is located, or Bidder must certify in writing that it will obtain such authority within the time for acceptance of Bids and attach such certification to the Bid.

12.12 If Bidder is required to be licensed to submit a Bid or perform the Work in the state where the

Project is located, the Bid must contain evidence of Bidder’s licensure, or Bidder must certify in writing that it will obtain such licensure within the time for acceptance of Bids and attach such certification to the Bid. Bidder’s state contractor license number, if any, must also be shown on the Bid Form.

ARTICLE 13—BASIS OF BID

13.01 Base Bid with Alternates

A. Bidders must submit a Bid on a lump sum basis for the base Bid and include a separate price for each alternate described in the Bidding Documents and as provided for in the Bid Form.

The price for each alternate will be the amount added to or deleted from the base Bid if

Owner selects the alternate.

B. Unit Prices are for potential increase or decrease of scope in the project.

C. In the comparison of Bids, the City of Oneonta will determine the priority of bid alternates to be the added total base bid which will be the comparison of bids for each alternate.

13.02 Allowances

A. For cash allowances the Bid price must include such amounts as the Bidder deems proper for

Contractor's overhead, costs, profit, and other expenses on account of cash allowances, if any, named in the Contract Documents, in accordance with Paragraph 13.02.B of the General

Conditions.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ARTICLE 14—SUBMITTAL OF BID

14.01 A Bid must be received no later than the date and time prescribed and at the place indicated in the Advertisement or invitation to bid and must be enclosed in a plainly marked package with the

Project title, and, if applicable, the designated portion of the Project for which the Bid is submitted, the name and address of Bidder, and must be accompanied by the Bid security and other required documents. If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid must be enclosed in a separate package plainly marked on the outside with the notation “BID ENCLOSED.” A mailed Bid must be addressed to the location designated in the

Advertisement.

14.02 Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted and will be returned to the

Bidder unopened.

ARTICLE 15—MODIFICATION AND WITHDRAWAL OF BID

15.01 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in Paragraph 15.01 and submit a new Bid prior to the date and time for the opening of Bids.

15.02 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, the Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, the Bidder will be disqualified from further bidding on the Work.

ARTICLE 16—OPENING OF BIDS

16.01 Bids will be opened at the time and place indicated in the advertisement or invitation to bid and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.

ARTICLE 17—BIDS TO REMAIN SUBJECT TO ACCEPTANCE

17.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.

ARTICLE 18—EVALUATION OF BIDS AND AWARD OF CONTRACT

18.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner also reserves the right to waive all minor

Bid informalities not involving price, time, or changes in the Work.

18.02 Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible.

18.03 If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the

Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

the Bid, whether in the Bid itself or in a separate communication to Owner or Engineer, then

Owner will reject the Bid as nonresponsive.

18.04 If Owner awards the contract for the Work, such award will be to the responsible Bidder submitting the lowest responsive Bid.

18.05 Evaluation of Bids

A. In evaluating Bids, Owner will consider whether the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the

Bid Form or prior to the Notice of Award.

B. In the comparison of Bids, alternates will be applied in the same order of priority as listed in the Bid Form. For comparison purposes alternates will be accepted, following the order of priority established in the Bid Form, until doing so would cause the budget to be exceeded.

After determination of the Successful Bidder based on this comparative process and on the responsiveness, responsibility, and other factors set forth in these Instructions, the award may be made to said Successful Bidder on its base Bid and any combination of its additive alternate Bids for which Owner determines funds will be available at the time of award.

18.06 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.

18.07 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.

ARTICLE 19—BONDS AND INSURANCE

19.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds, other required bonds (if any), and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it must be accompanied by required bonds and insurance documentation.

19.02 Article 8, Bid Security, of these Instructions, addresses any requirements for providing bid bonds as part of the bidding process.

ARTICLE 20—SIGNING OF AGREEMENT

20.01 When Owner issues a Notice of Award to the Successful Bidder, it will be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 15 days thereafter, Successful Bidder must execute and deliver the required number of counterparts of the Agreement and any bonds and insurance documentation required to be delivered by the Contract Documents to Owner. Within 10 days thereafter, Owner will deliver one fully executed counterpart of the Agreement to Successful

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Bidder, together with printed and electronic copies of the Contract Documents as stated in

Paragraph 2.02 of the General Conditions.

ARTICLE 21—SALES AND USE TAXES

21.01 Owner is exempt from New York state sales and use taxes on materials and equipment to be incorporated in the Work. Said taxes must not be included in the Bid. Refer to Paragraph SC-7.10 of the Supplementary Conditions for additional information.

ARTICLE 23 – FEDERAL REQUIREMENTS

23.01 If the contract price is in excess of $100,000, provisions of the Contract Work Hours and Safety

Standards Act at 29 CFR 5.5(b) apply.

23.02 Federal requirements at Article 19 of the Supplementary Conditions apply to this Contract.

PROCUREMENT FORMS AND SUPPLEMENTS

EJCDC® C-410, Bid Form for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

BID FORM FOR CONSTRUCTION CONTRACT

The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to

Bidders, the General Conditions, and the Supplementary Conditions.

ARTICLE 1—OWNER AND BIDDER

1.01 This Bid is submitted to: City of Oneonta, City Hall, 258 Main Street, Oneonta, NY 13820

1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.

ARTICLE 2—ATTACHMENTS TO THIS BID

2.01 The following documents are submitted with and made a condition of this Bid:

A. Required Bid security;

B. Certification of nonsegregated facilities;

C. Non-collusion affidavit of Prime Bidder;

D. Certification of compliance with the Iran Divestment Act;

E. Certificate as to corporate principal;

F. Form of surety guaranty;

G. Equal opportunity clause;

H. Hold Harmless clause.

ARTICLE 3—BASIS OF BID—LUMP SUM BID AND UNIT PRICES

3.01 Lump Sum Bids

A. Bidder will complete the Work in accordance with the Contract Documents for the following lump sum (stipulated) price(s):

1. Lump Sum Prices (Base Bid and Alternates, Per Bid Item Descriptions)

Work Item #1 – Mobilization and Miscellaneous $

Work Item #2 – Maintenance and Protection of Traffic $

Work Item #3 – Select Demolition and Disposal $

Work Item #3 – New Concrete Wall and Stair $

Work Item #4 – New Aluminum Railing $

Work Item #5 – New Concrete Sidewalk $

Work Item #6 – New Concrete Curb $

Work Item #7 – New Paving & Markings $

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Work Item #8 – Sitework & Restoration $

Work Item #9 – Erosion and Sediment Control $

Bid Alternate #1 – BA#1 – New Stamped Concrete $

Bid Alternate #2 – BA#2 – New Granite Curb $

Bid Alternate #3 – BA#3 – Grout Existing CMU Block Wall $

B. The Bidder shall be responsible for determining from the Contract Documents the affects of each alternate on the Contract Time and the Contract Sum. Owner reserves the right to accept or reject any alternate, in any order, and to award or amend the Contract accordingly within [60] days of the Notice of Award unless otherwise indicated in the Contract

Documents.

C. All specified contingency allowances are included in the price(s) set forth below, and have been computed in accordance with Paragraph 13.02 of the General Conditions.

Owner designated contingency $50,000.00

Testing and Inspection $10,000.00

3.02 Total Bid Price (Lump Sum and Allowances)

Total Bid Price (Total of all Lump Sum Work Items and Allowances)

EXCLUDING ALL BID ALTERNATES

3.03 Unit Prices

A. The undersigned Bidder proposes the amounts below may be added to or deducted from the

Contract Sum on performance and measurement of the individual items of Work. These values may be utilized for additional work or deduction of work.

B. If the unit price does not affect the Work of this Contract, the Bidder shall indicate "NOT

APPLICABLE."

a. Unit-Price No. 1: Aluminum Railing as defined on the contract drawings.

1) ____________________________ Dollars ($_____________) per linear foot.

b. Unit-Price No. 2: Concrete sidewalk as defined on the contract drawings.

1) ____________________________ Dollars ($_____________) per square foot.

c. Unit-Price No. 3: New Pavement as defined on the contract drawings.

1) ____________________________ Dollars ($_____________) per square foot.

3.04

ARTICLE 4—TIME OF COMPLETION

4.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

4.02 Bidder accepts the provisions of the Agreement as to liquidated damages.

ARTICLE 5—BIDDER’S ACKNOWLEDGEMENTS: ACCEPTANCE PERIOD, INSTRUCTIONS, AND RECEIPT OF

ADDENDA

5.01 Bid Acceptance Period

A. This Bid will remain subject to acceptance for 60 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.

5.02 Instructions to Bidders

A. Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security.

5.03 Receipt of Addenda

A. Bidder hereby acknowledges receipt of the following Addenda:

Addendum Number Addendum Date

ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS

6.01 Bidder’s Representations

A. In submitting this Bid, Bidder represents the following:

1. Bidder has examined and carefully studied the Bidding Documents, including Addenda.

2. Bidder has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

3. Bidder is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work.

4. Bidder has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the

Supplementary Conditions, with respect to the Technical Data in such reports and drawings.

5. Bidder has carefully studied the reports and drawings relating to Hazardous

Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, with respect to Technical Data in such reports and drawings.

6. Bidder has considered the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Technical

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Data identified in the Supplementary Conditions or by definition, with respect to the effect of such information, observations, and Technical Data on (a) the cost, progress, and performance of the Work; (b) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, if selected as Contractor; and

(c) Bidder’s (Contractor’s) safety precautions and programs.

7. Based on the information and observations referred to in the preceding paragraph, Bidder agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract

Times, and in accordance with the other terms and conditions of the Contract.

8. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.

9. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and of discrepancies between Site conditions and the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.

10. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.

11. The submission of this Bid constitutes an incontrovertible representation by Bidder that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.

6.02 Bidder’s Certifications

A. The Bidder certifies the following:

1. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation.

2. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid.

3. Bidder has not solicited or induced any individual or entity to refrain from bidding.

4. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 8.02.A:

a. Corrupt practice means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process.

b. Fraudulent practice means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition.

c. Collusive practice means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

d. Coercive practice means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

BIDDER hereby submits this Bid as set forth above:

Bidder:

(typed or printed name of organization)

By:

(individual’s signature)

Name:

(typed or printed)

Title:

(typed or printed)

Date:

(typed or printed)

If Bidder is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.

Attest:

(individual’s signature)

Name:

(typed or printed)

Title:

(typed or printed)

Date:

(typed or printed)

Address for giving notices:

Bidder’s Contact:

Name:

(typed or printed)

Title:

(typed or printed)

Phone:

Email:

Address:

Bidder’s Contractor License No.: (if applicable)

BID BOND

KNOW ALL MEN BY THESE PRESENTS, that we the undersigned as Principal, and _______________________________________________ as Surety are held and firmly bound unto ________________________

_________________________________hereinafter called the

"Owner", in the penal sum of _____________________________________

_______________________________________Dollars, ($________________) lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors, and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH, that whereas the Principal has submitted the Accompanying Bid, dated

_________________, 20____, for _______________________________

NOW THEREFORE, if the Principal shall not withdraw said Bid within the period specified therein after the opening of the same, or within any extended time period agreed to by the Principal, Surety and Owner, or if no period be specified, within thirty (30) days after the said opening, and shall within the period specified therefor, or if no period be specified, within ten

(10) days after the prescribed forms are presented to him for signature, enter into a written Contract with the Owner in accordance with the Bid as accepted and give bond with good and sufficient surety or sureties, as may be required, for the faithful performance and proper fulfillment of such Contract; then the above obligation shall be null and void and of no effect, otherwise to remain in full force or virtue.

Failure to comply with the aforementioned condition shall result in the forfeiture of this Bid Bond as liquidated damages.

IN WITNESS WHEREOF, the above-bounded parties have executed this instrument under their several seals this _____________day of______________, 20____, the name and corporate seal of each corporate party being hereto affixed and these presents signed by its undersigned representative, pursuant to authority of its governing body.

No extension of time or other modification of this Bid Bond shall be valid unless agreed to in writing by the parties to this Bond.

In presence of:

___________________________________________ (SEAL)

(Individual Principal)

(Business Address)

__________________________________________ (SEAL)

(Business Address)

Attest: By:_______________________________

(Corporate Principal)

By: _____________________________ Affix Corporate Seal

Attest:

(Corporate Surety)

(Business Address)

By: _______________________________ Affix Corporate Seal

Countersigned by: ____________________

*Attorney-in-Fact, State of______________________________________

*Power-of-Attorney for person signing for Surety Company must be attached to Bond.

CERTIFICATION OF NONSEGREGATED FACILITIES

This Bidder certifies that he does not maintain or provide for his employees any segregated facilities at any of his establishments, and that he does not permit his employees to perform their services at any location, under his control, where segregated facilities are maintained. The Bidder certifies further that he will not maintain or provide for his employees any segregated facilities at any of his establishments, and that he will not permit his employees to perform their services at any location under his control where segregated facilities are maintained. The Bidder agrees that a breach of his certification will be a violation of the Equal Opportunity clause in any Contract resulting from acceptance of this Bid. As used in this certification, the term "segregated facilities": means any waiting rooms, work areas, restrooms and washrooms, restaurants and other eating areas, time clock, locker rooms and other storage or dressing areas, parking lots, drinking fountains, recreation or entertainment areas, transportation, and housing facilities provided for employees which are segregated by explicit directive or are, in fact, segregated on the basis of race, color, religion, or national origin, because of habit, local custom or otherwise.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .