West_Cliff_Dr_Path_Realignment_Engineer's_Estimate.pdf

PDF 13 KB Posted

Attached to
West Cliff Dr Path Realignment
Solicitation number
IFB No. PW-0327
Issued by
Santa Cruz County, San Francisco City, California

About this file

This is an Engineer's Estimate document for the West Cliff Dr Path Realignment project in California. The project encompasses pedestrian access improvements and infrastructure enhancements at two sites, including demolition and repaving of existing pathways, construction of drainage improvements such as swales and storm drain connections, installation of site amenities including fencing, benches, and memorial elements, vegetation restoration, and grading work. The scope includes mobilization, stormwater pollution prevention planning, traffic control, construction surveying, decomposed granite rest area construction, and associated site preparation activities across both project locations.

The total estimated project cost is $459,800.00, broken down into eight line items: Lump Sum Items ($53,000.00), Demo and Removal ($101,000.00), Asphalt Walkway ($53,000.00), Swale and Storm Drain System ($35,000.00), Fixtures and Other Appurtenances ($18,000.00), Decomposed Granite Rest Area ($6,000.00), Planting and Restoration ($152,000.00), and a 10% Contingency allocation ($41,800.00). The estimate provides a detailed breakdown of specific work elements including asphalt paving, PCC curb and gutter, fencing installation, park bench installation, memorial relocation, trash can relocation, water spigot installation, and comprehensive vegetation restoration with ground cover installation.

View the file

Other files

File Type Posted
Planting_Totals.pdf PDF
West_Cliff_Dr_Path_Realignment_w_tcp.pdf PDF
West_Cliff_Dr_Path_Reaignment-IFB_&_Specs.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

West Cliff Dr Path Realignment Engineers Estimate

Item Price

1: Lump Sum Items $53,000.00

Mobilization

Stormwater Pollution Prevention Plan

Traffic Control and Construction Signage

Constrution Surveying

2: Demo And Removal $101,000.00

Demo and Removal & Site Prep

3: Asphalt Walkway $53,000.00

Asphalt Paving

PCC Curb and Gutter

Asphalt Conform

4: Swale and Storm Drain System $35,000.00

Grade Swale

Convert SDDI to SDAD

Construct new AD

5: Fixtures and other Appurtenances $18,000.00

Fencing

Park Bench Instalation

Relocate/Install Memorial

Relocate Trash Can

Remove Bollard Base

Install Water Spiggot

6: DG Rest Area $6,000.00

Construct DG Rest Areas Per Plan

7: Planting and Restoration $152,000.00

Grading/Soil Prep

Planting and Restoration

Install Swash Cap and other Ground Cover

8: 10% Contingency $41,800.00

9: Total Estimated Cost $459,800.00