This is an Engineer's Estimate document for the West Cliff Dr Path Realignment project in California. The project encompasses pedestrian access improvements and infrastructure enhancements at two sites, including demolition and repaving of existing pathways, construction of drainage improvements such as swales and storm drain connections, installation of site amenities including fencing, benches, and memorial elements, vegetation restoration, and grading work. The scope includes mobilization, stormwater pollution prevention planning, traffic control, construction surveying, decomposed granite rest area construction, and associated site preparation activities across both project locations.
The total estimated project cost is $459,800.00, broken down into eight line items: Lump Sum Items ($53,000.00), Demo and Removal ($101,000.00), Asphalt Walkway ($53,000.00), Swale and Storm Drain System ($35,000.00), Fixtures and Other Appurtenances ($18,000.00), Decomposed Granite Rest Area ($6,000.00), Planting and Restoration ($152,000.00), and a 10% Contingency allocation ($41,800.00). The estimate provides a detailed breakdown of specific work elements including asphalt paving, PCC curb and gutter, fencing installation, park bench installation, memorial relocation, trash can relocation, water spigot installation, and comprehensive vegetation restoration with ground cover installation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Planting_Totals.pdf | ||
| West_Cliff_Dr_Path_Realignment_w_tcp.pdf | ||
| West_Cliff_Dr_Path_Reaignment-IFB_&_Specs.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
West Cliff Dr Path Realignment Engineers Estimate
Item Price
1: Lump Sum Items $53,000.00
Mobilization
Stormwater Pollution Prevention Plan
Traffic Control and Construction Signage
Constrution Surveying
2: Demo And Removal $101,000.00
Demo and Removal & Site Prep
3: Asphalt Walkway $53,000.00
Asphalt Paving
PCC Curb and Gutter
Asphalt Conform
4: Swale and Storm Drain System $35,000.00
Grade Swale
Convert SDDI to SDAD
Construct new AD
5: Fixtures and other Appurtenances $18,000.00
Fencing
Park Bench Instalation
Relocate/Install Memorial
Relocate Trash Can
Remove Bollard Base
Install Water Spiggot
6: DG Rest Area $6,000.00
Construct DG Rest Areas Per Plan
7: Planting and Restoration $152,000.00
Grading/Soil Prep
Planting and Restoration
Install Swash Cap and other Ground Cover
8: 10% Contingency $41,800.00
9: Total Estimated Cost $459,800.00