Well_Site__3_Electrical_Upgrade.pdf
PDF 549 KB Posted
- Attached to
- Well Site #3 Electrical Upgrade
- Solicitation number
- 2027-RFB-00000005
- Issued by
- Yuma County, Arizona
About this file
This is a Request for Bid (RFB) issued by the City of San Luis, Arizona for the Well Site #3 Electrical Upgrade project located at 1317 B Street in San Luis, Yuma County, Arizona. The project involves upgrading and replacing existing electrical equipment and systems to improve facility reliability and operation, including replacement of electrical service equipment, upgrades to well pump motor controls and variable frequency drives (VFDs), modifications to motor control equipment and booster pump controls, installation of new site lighting, and associated electrical equipment, conduit, conductors, grounding, controls, and connections. A non-mandatory pre-bid conference will be held on September 23, 2026 at 1:00 PM at City Hall, with virtual attendance available. Questions must be submitted through the Procurement Portal no later than 6:00 PM on September 30, 2026, with responses due by October 1, 2026. Sealed bids are due by 1:30 PM on October 6, 2026, with public opening and reading of bids immediately following at 1:00 PM on the same date. Contractor selection is anticipated for October 8, 2026, with formal contract award at the City Council meeting on October 28, 2026. The project completion date will be determined upon contract award, with the contractor required to complete all work within the specified contract time determined at award.
Bidders must submit a bid security of 10 percent of the total bid amount via certified check, cashier's check, or surety bond. The contract will be awarded to the lowest qualified responsive bidder with a valid Arizona State Classification "A" Contractor's license. The successful contractor must provide Performance and Payment Bonds each equal to 100 percent of the Contract Price and maintain comprehensive general liability insurance with minimum coverage limits including a $6,000,000 general aggregate, $6,000,000 each occurrence for bodily injury and property damage, $2,000,000 personal injury and advertising injury, and coverage for explosion, collapse, and underground hazards. Progress payments will be made at 90 percent of certified work with 10 percent retained until substantial completion, at which point retention schedules adjust. Liquidated damages apply for failure to achieve final completion within the contract time as specified in the City of San Luis Supplement to the MAG Uniform Standard Specifications. The contractor is responsible for all permits, fees, and compliance with applicable state laws, municipal ordinances, and regulations. No Davis-Bacon wage rates apply to this solicitation, which is open to general contractors and subcontractors licensed to operate in Arizona.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFB No. 2027-RFB-00000005 Well Site #3 Electrical Upgrade
CITY OF SAN LUIS
REQUEST FOR BID (RFB)
FOR
WELL SITE #3 ELECTRICAL UPGRADE
2027-RFB-00000005
SEALED REQUEST FOR BID DEADLINE
Tuesday, October 6, 2026, 1:30 pm
1090 EAST UNION STREET | P.O. BOX 7740 | SAN LUIS, AZ 85349
TABLE OF CONTENTS
undefined
1. ADVERTISEMENT FOR BIDS
2. INSTRUCTIONS TO BIDDERS
3. SCOPE OF WORK
4. PROPOSAL KIT
5. BID SCHEDULE
6. CITY INSURANCE REQUIREMENTS
7. GENERAL CONDITIONS OF THE CONTRACT
8. ATTACHMENTS
Attachments:
A - Contractor's Affidavit Regarding Settlement of Claims
B - Well Site #3 Electrical Upgrade Plans
ADVERTISEMENT FOR BIDS
NOTICE IS HEREBY GIVEN THAT sealed proposals or bids will be received through the Procurement Portal at https://procurement.opengov.com/portal/sanluisaz, until 1:30 pm (M.S.T.) on Tuesday, October 6, 2026, for furnishing all labor, materials, equipment, tools and performing all services required for the construction of the Well Site #3 Electrical Upgrade and work incidental thereto.
The Well Site #3 Electrical Upgrade project consists of upgrading and replacing existing electrical equipment and system to improve the reliability and operation of the facility. Work includes, but is not limited to, replacement of the existing electrical service equipment, upgrades to well pump motor controls and variable frequency drives (VFDs), modifications to existing motor control equipment and booster pump controls, installation of new site lighting and associated electrical equipment, conduit, conductors, grounding, controls, and connections.
The completion date of project will be determined upon award of contract.
Plans, specifications and contract documents may be obtained through the Procurement Portal at https://procurement.opengov.com/portal/sanluisaz.
A Non-Mandatory Pre-Bid Conference will be held at City of San Luis City Hall, Pedro Julian Conference Room, 1090 E Union St. San Luis, AZ 85349 on Wednesday, September 23, 2026, at 1:00 pm (M.S.T.) to discuss specifications and any questions Bidders may have. The pre-bid conference may also be attended virtually via the following link: Well Site 3 - Electrical Upgrade. Meeting ID: 252 448 077 719 312 Passcode: Kp6ri6xi
All bids must be submitted through the Procurement Portal and be accompanied by a certified or cashier's check or bid bond in the amount of ten (10%) percent of the total amount of the bid.
Bids will be publicly opened at the City of San Luis City Hall, Pedro Julian Conference Room, 1090 E. Union St.
San Luis, AZ 85349, on Tuesday, October 6, 2026, at 1:00 P.M. (M.S.T) and read aloud. Bid opening can also be viewed virtually via the following link: Bid Opening - Well Site 3 - Electrical Upgrade. Meeting ID: 233 280 908
587 378 Passcode: 9aL9ou65
The City of San Luis reserves the right to cancel this procurement, and/or to reject any or all bids, and/or to waive any informality in any bid. No bidder may withdraw their bid for a period of thirty (30) days after the date set for the bid opening thereof:
City of San Luis, Arizona
Jenny Torres, City Manager
INSTRUCTIONS TO BIDDERS
2.1. DEFINITIONS
1.1 All definitions set forth in the General Conditions are applicable to these Instructions to Bidders.
https://procurement.opengov.com/portal/sanluisaz https://procurement.opengov.com/portal/sanluisaz https://teams.microsoft.com/meet/252448077719312?p=VCuWEz8vzy5DnqP980 https://teams.microsoft.com/meet/233280908587378?p=fKtq3bjVcJutHGlW9P
1.2 Bidding Documents include the Advertisement for Bids, Instructions to Bidders, Bid Form, Bid Bond
Form, and the proposed Contract Documents, including any addenda issued prior to the receipt of bids.
1.3 Addenda are written or graphic instructions issued prior to the execution of the contract which modify or interpret the Bidding Documents, including Drawings, conditions of the Contract and
Specifications, by additions, deletions, clarifications or corrections. Addenda will become part of the
Contract Documents when the Construction Contract is executed.
1.4 The term "Owner" or "City" shall be interpreted to mean City of San Luis, Arizona.
2.2. BIDDER'S REPRESENTATION
2.1 Before submitting a bid, bidders shall carefully examine the Drawings, Bidding Requirements, Bid
Document Contract Forms, General Conditions, Supplementary General conditions, Specifications, and
Related Documents, visit the site of the work, and fully inform themselves as to all existing conditions and limitations and shall include in the bid a sum sufficient to cover the cost of all items included in the
Contract. The Bidder, if awarded the Contract, shall not be allowed any extra compensation by reason of any matter or thing concerning the Project, which said Bidder might have fully informed himself prior to the building.
2.3. BIDDING DOCUMENTS
3.1 Bidders may obtain copies of the bidding Documents through the Procurement Portal at https://procurement.opengov.com/portal/sanluisaz.
2.4. INTERPRETATION OF BIDDING DOCUMENTS
4.1 Should a Bidder find discrepancies, inconsistencies or obscurities in, or omissions from the bidding documents, or should he be in doubt as to their meaning, Bidder shall submit their questions through the Procurement Portal. A written Addendum, clarifying the intent of the documents shall be issued, if needed. Addenda may not be issued less than 48 hours before the time specified for receipt of bids.
Questions received less than four calendar days prior to the assigned bid date cannot be answered in writing. Should any discrepancies not be clarified by Addendum, the Contractor shall use the most expensive condition shown or specified in bid.
4.2 Prior to the receipt of bids, each person or firm recorded by the Office of the City Clerk as having received the bidding documents will be notified of any addendum. Addenda will also be available for
Inspection wherever the bidding documents are kept available for that purpose.
4.3 All Addenda issued by the City during the time of bidding are to be included in the bid, and shall become a part of the bidding documents (bidder’s responsibility to check for addendums). Acknowledge receipt of Addenda through the Procurement Portal.
4.4 All questions must be submitted through the Procurement Portal no later than 6:00 pm on
Wednesday, September 30, 2026.
2.5. SUBSTITUTIONS
https://procurement.opengov.com/portal/sanluisaz
5.1 When a specific manufacturer, trade name or material is specified, or indicated, it is to establish a standard of quality and shall not be construed as limiting competition. However, components of electrical systems shall be standard items and/or interchangeable with specified manufacturer to facilitate repairs and upkeep by the Owner.
5.2 It shall be the Contractor's responsibility to provide materials of equal standards to those specified.
The City shall be the sole judge as to whether or not the products meet the established standards. The
Contractor MUST request written approval of equal materials from the City prior to, or after the bid date.
2.6. BIDDING PROCEDURES
6.1 A bid is invalid if it has not been submitted through the Procurement Portal at https://procurement.opengov.com/portal/sanluisaz prior to the time and date for receipt of bids indicated in the Invitation to Submit Proposals, or prior to any extension thereof issued to the bidders.
6.2 Bid Security:
1. Each bidder is required to submit, with his bid, a certified or cashier's check upon a solvent bank, or a surety bond for ten percent (10%) of the amount of the Base Bid made payable to the Owner.
a. If more than one proposal is submitted, only one Bid Security is required for the largest base
Bid amount, however, this bond shall apply to any and/or all bids submitted.
2. The Bid Security shall be given as a guarantee that the bidder will enter into a contract to perform the work, if awarded to him, and provide a satisfactory Performance Bond and Payment Bond as required under the provisions of Title 34, Chapter 2, Article 2, Arizona Revised Statutes. Bid Security shall be declared forfeited as liquidated damages if he refuses to enter into said contract upon request to do so by the Owner.
3. Bid Security will be returned to the unsuccessful bidders, and to the successful bidder upon the execution of a satisfactory Performance Bond and Payment Bond and Construction Contract.
4. Bidders may withdraw their bid at any time prior to bid opening, but may not resubmit them. No bid may be modified or withdrawn after the bid opening for a period of 30 days except where the award of the contract has been delayed at least 31 days.
6.3 A Non-Mandatory pre-bidders conference will be held at 1:00 pm at the City of San Luis City Hall, Pedro Julian Conference Room, 1090 E Union St. San Luis, AZ 85349on Wednesday, September 23, 2026.
2.7. SUBCONTRACTOR LIST FORM
7.1 Complete the Subcontractor List Form, listing a single company, firm, or organization name only for each branch of the work. Submit through the vendor PROPOSAL KIT.
https://procurement.opengov.com/portal/sanluisaz https://procurement.opengov.com/portal/sanluisaz/projects/301820/document?section=2894383
7.2 The competency and responsibility of bidders and their proposed subcontractors will be considered in making the award.
7.4 The Contractor shall pay the cost of all permits, changes, meters, connections, fees, etc., directly to governmental agencies having jurisdiction to comply with the law of the place of the Project in order to complete the work. The bidders' attention is directed to the fact that all applicable state laws, municipal ordinances, and the rules and regulations of all authorities having jurisdiction shall apply to the
Contract.
2.8. REJECTION OF BIDS
8.1 The Bidder acknowledges the right of the Owner to reject any or all bids, to waive any informality or irregularity in any bid received, or to withhold the award for any reason he determines. In addition, the
Bidder recognizes the right of the Owner to reject a bid if the Bidder failed to furnish any required Bid
Security or to submit the data required by the Bidding Documents, or if the bid is in any way incomplete or irregular. Bidders shall understand that the Owner will not be responsible for any errors or omissions in the preparation of the bid.
2.9. AGREEMENT
9.1 The form of Agreement which the successful Bidder will be required to execute in two (2) original counterparts. Progressed payments will be made to the Contractor by the Owner in an amount equal to
90% of that due until the final payment.
2.10. WARRANTY
10.1 The Contractor certifies by submitting his bid that he has familiarized himself with all specified products, materials, and systems which are proposed for inclusion in the required work, and that said materials, products, and systems are appropriate for the use(s) intended. He additionally certifies by submitting this bid that he shall, in fact, install said materials, products, and systems in the work properly and in rigid compliance with the terms and conditions of the Contract Documents, and shall issue his written warranty applicable to the work as required by the applicable Supplementary General
Conditions. If the Bidder determines that the proposed materials, products, and/or systems are not appropriate for the use(s) intended, he shall submit his written exceptions attached to the Bid Form.
2.11. PERFORMANCE AND PAYMENT BONDS
11.1 The Contractor is hereby required to provide and pay for Performance and Payment Bonds. Bonds shall secure the faithful performance (100%) of the Contract and the payment of all obligations (100%) arising there under, in such form as the Owner may prescribe and with such sureties that he may approve. Both Bonds shall be active and held by the Owner for duration of the guaranty (warranty).
2.12. CONTRACTOR LICENSE LAW, ELIGIBILITY & PREFERENCE
12.1 The Contractor shall comply with, and require all subcontractors to comply with State of Arizona and City Contractor's License Laws. Contractor shall comply with the provisions of "an Act to Regulate the Business of Contracting", Title 32, Chapter 10, Arizona Revised Statutes with latest adopted revisions and ‘Contractor's License Laws and Regulations" dated July, 1981, published by the Arizona State
Registrar of Contractors, or the latest revision thereof adopted under the provision of AIRS title 32, chapter 10, Articles 2 and 3.
The prime Contractor shall have a State of Arizona Classification “A” Contractor’s license to perform the work. A bid submitted by any Contractor not properly licensed at the time of bid opening shall be considered non-responsive and will be rejected.
2.13. NONDISCRIMINATION
13.1 In connection with the performance of work under this Contract, the Contractor agrees (as prescribed in
A.R.S. Section 23-373) not to discriminate against any employee or applicant for employment because of race, sex, religion, color, or national origin. The aforesaid provision shall include, but not be limited to, the following: employment upgrading, demotion, or transfer, recruitment or recruitment advertising, layoff or termination, rates of pay or other forms of compensations and selection for training, including apprenticeship.
The Contractor agrees to post hereafter in conspicuous places, available for employees and applicants for employment, notices setting forth the provisions of the nondiscrimination clauses. The contractor further agrees to insert the foregoing provision in all subcontracts hereunder, except subcontracts for standard commercial supplies or raw materials.
2.14. COPIES OF DOCUMENTS FURNISHED
14.1 The Contractor shall obtain Construction Documents free of charge through the Procurement
Portal.
2.15. INSURANCE
15.1 The contractor is required to provide and pay for insurances. He shall file, with his Performance and
Payment Bonds, all required Certificates of Insurance and endorsements demonstrating that the insurance policy was amended to add City of San Luis, Arizona as an additionally insured.
15.2 The Contractor shall not commence work under this Contract until he has obtained all the insurance required under this paragraph and such insurance has been approved by the Owner, nor shall the Contractor allow any Subcontractor to commence work on his subcontract until the insurance require of the subcontractor has been so obtained and approved.
15.3 The Contractor shall procure and maintain during the life of this contract, Workmen's
Compensation Insurance as required by applicable State or Territorial Law for all of his employees to be engaged in work at the site of the project under this contract, and in any such work sublet, the
Contractor shall require the Subcontractor similarly to provide Workmen's Compensation Insurance for all of the latter's employees to be engaged in such work unless such employees are covered by the protection afforded by the Contractors Workmen's Compensation Insurance. In case any class of the employees engaged in hazardous work on the project under this contract are not protected under the
Workmen's Compensation Statute, the Contractor shall provide and shall cause each subcontractor to provide adequate employer's liability insurance for the protection of such of his employees as are not otherwise protected.
15.4 The Contractor shall provide public liability insurance and show evidence specified in the Contract
Documents in the City Insurance Requirements.
2.16. ADDITIONAL SERVICES
16.1 Contractor agrees to pay for additional testing services, additional Engineering services, and any similar related additional costs as designated in the Contract Documents.
2.17. SUMMARY OF THE WORK
17.1 Refer to the Overview, Summary and Scope of Work, and Summary of the Work, for description of the work.
2.18. SUBSTANTIAL COMPLETION
18.1 Substantial Completion TBD--The completion date of project will be determined upon award of contract.
2.19. LIQUIDATED DAMAGES
19.1 The liquidated damages for this project shall be determined by the Schedule of Liquidated
Damages in City of San Luis Supplemental to the MAG Uniform Standard Specifications.
2.20. EVALUATION AND AWARD
• Bid opening will take place on Tuesday, October 6, 2026 immediately after the close of the bidding.
• City staff will convene in the City of San Luis City Hall, Pedro Julian Conference Room, 1090 E Union St.
San Luis, AZ 85349, open the proposals virtually, and read the bids into the record.
• Award will be made to the lowest qualified responsive bidder.
• Formal award of contract will be on the next available Regular City Council meeting.
2.21. PROTESTS
All responders will receive notification via e-mail regarding their status vis-a-vis the proposed contract award.
Responders not selected have two days from e-mail sent date to initiate protest proceedings. To do this, a dissatisfied party must lodge a protest with Angelica Cifuentes, Procurement Coordinator, via receipted e-mail
(acifuentes@sanluisaz.gov) or by certified mail (Attn: Angelica Cifuentes/City of San Luis/P.O. Box 7740/San
Luis, AZ 85349). The City of San Luis will then hold a hearing within two days of the receipt of the protest and make a determination within two days of the hearing. In the absence of a successful protest, the contract will be awarded to the most responsive qualified bidder.
SCOPE OF WORK
3.1. TIMELINE
Advertisement/Release Project Date: September 13, 2026
Advertisement/Release Project Date: September 20, 2026
Pre-Bid Meeting (Non-Mandatory): September 23, 2026, 1:00pm
City of San Luis City Hall, Pedro Julian Conference Room, 1090 E Union St. San
Luis, AZ 85349
Question Submission Deadline: September 30, 2026, 6:00pm
Question Response Deadline: October 1, 2026, 6:00pm
Submission Deadline: October 6, 2026, 1:30pm
Bid Opening: October 6, 2026, 1:30pm
Contractor Selection Date: October 8, 2026
Council Meeting: October 28, 2026, 6:00pm
3.2. PROJECT NAME, LOCATION, AND OVERVIEW
PROJECT NAME:
The name of this project is Well Site #3 Electrical Upgrade. All correspondence and documents are to reference “Well Site #3 Electrical Upgrade”.
PROJECT LOCATION:
The Project is located in Yuma County, Arizona. The proposed work is located within the limits of the City of
San Luis, Arizona, on 1317 B St. San Luis, AZ 85349.
OVERVIEW:
The Well Site #3 Electrical Upgrade project is being undertaken by the City of San Luis, Arizona. This bid pertains to those activities described herein under the Scope of Work.
It is especially important that bidders are aware of the following:
A. This solicitation is open to general contractors and subcontractors licensed to operate in the State of
Arizona.
B. Davis-Bacon wage rates NO VALUE apply.
3.3. SCOPE OF WORK
Scope of Work, Well Site #3 Electrical Upgrade.
The Well Site #3 Electrical Upgrade project consists of upgrading and replacing existing electrical equipment and system to improve the reliability and operation of the facility. Work includes, but is not limited to, replacement of the existing electrical service equipment, upgrades to well pump motor controls and variable frequency drives (VFDs), modifications to existing motor control equipment and booster pump controls, installation of new site lighting and associated electrical equipment, conduit, conductors, grounding, controls, and connections. The Contractor shall provide all labor, materials, equipment, testing, startup, and incidentals necessary to provide a complete and fully operational electrical system in accordance with the project plans and specifications.
PROPOSAL KIT
1. Proposal*
Project Name: Well Site #3 Electrical Upgrade
In compliance with the Advertisement for Bids:
Having examined the contract documents, site of work, and being familiar with the conditions to be met, hereby submits the following Proposal for furnishing the material, equipment, labor and everything necessary for the completion of the work listed and agrees to execute the contract documents and furnish the required
CONTRACT AND LABOR AND MATERIAL surety bonds and certificates of insurance for the completion of said work, at the locations and for the prices set forth on the inside pages of this form;
Understands that construction of this project shall be in accordance with all applicable Maricopa Association of Governments (MAG) Uniform Standard Specifications and Details for Public Works Construction as adopted by the City of San Luis, the City of Yuma Construction Standard Detail Drawings – 2009 edition [details], the
City of San Luis Supplemental to the MAG Uniform Standard Specifications and Details for Public Works
Construction and the City of Yuma Construction Standard Detail Drawings, except as otherwise required by the
Plans and Special Provisions;
Understands that this proposal for construction of this project shall be submitted with a proposal guarantee of cash, certified check, cashier's check or bid surety bond for an amount not less than 10 percent of the amount bid;
Agrees that upon receipt of Notice of Award, from the City of San Luis, Arizona, Bidder will execute the contract documents within 10 (Ten) calendar days;
Understands that the work shall commence on day 1 of the Contract Time and be completed within TBD--The completion date of project will be determined upon award of contract. from the date of Notice to Proceed.
☐ Please confirm
*Response required
2. Bid Surety Bond*
Please download the below documents, complete, and upload.
• Bid_Surety_Bond.pdf
*Response required
3. Non-Collusion Affidavit*
Please download the below documents, complete, and upload.
• Non-Collusion_Affidavit.pdf
*Response required
4. Bidders Participation Subcontractors and Suppliers List*
Please download the below documents, complete, and upload.
• Bidders_Participation_Subco...
*Response required
5. Certificate of Insurance*
Please upload your Certificate of Insurance.
*Response required
BID SCHEDULE
Line Item Description Quantity Unit of
Measure Unit Cost Total
1 Electrical Service Equipment 1 LS
2 Well Pump Motor & VFD Upgrades 1 LS
3 Booster Pump Control 1 LS
4 Site Lighting & Electrical
Improvements
1 LS
5 Testing & Startup 1 LS
TOTAL
https://government-project.s3.us-west-2.amazonaws.com/175409/719b116e-9b87-4d4e-8d13-0456be5395ac_Bid_Surety_Bond.pdf https://government-project.s3.us-west-2.amazonaws.com/175409/25de944b-a4fc-4e72-a432-400f1a1e83c8_Non-Collusion_Affidavit.pdf https://government-project.s3.us-west-2.amazonaws.com/175409/52c3c49e-5fbf-4512-8c65-af24ecf2987c_Bidders_Participation_Subcontractors_and_Suppliers_List.pdf
CITY INSURANCE REQUIREMENTS
The following are the minimum required under the Contract. Greater amounts may be required by law or regulation. Any insurance proceeds in excess of the lmits and coverage required in this Contract and which is applicable to a given loss will be available to the City. These limits required by the Contract do not limit the
Contractor’s liability under the indemnification provisions of the Contract.
6.1. Contractor’s Obligation
The Contractor shall secure and maintain, at the Contractor’s expense, until the Final Completion of the
Project, general liability and property insurance as shall protect the Contractor and the City from claims for bodily injury, personal injury, and property damage which may arise because of the nature of the work or from operations under this Contract. The Contractor’s insurance coverage shall be primary insurance with respect to all other available sources. Any coverage maintained by the City shall not contribute to any claims arising from the Contractor’s performance of this Contract. The Contractor shall file these certificates with City of San
Luis within ten (10) days of execution of this Contract and prior to engaging in any operation or activities set forth in this AGREEMENT. The foregoing insurance policies shall provide that no cancellation, major change in coverage, or expiration by the insurance company or the insured.
6.2. General Liability Coverage
Contractor shall have general liability coverage on a per occurrence, and in comprehensive form. General liability coverage shall include Products, Completed Operations, Products Liability, Explosion, Underground and Collapse Hazard, Premises, Operations, Contractual, Independent Contractors, Broad Form Property
Damage and Personal Injury. General Liability coverage shall include and eliminate the exclusion for property under the care, custody, and control of the Contractor.
6.3. Coverage Amounts
Contractor shall provide general liability and excess general liability coverage in the following amounts, at a minimum:
Employer’s Liability
A. Each Accident $100,000
B. Disease for Each Employee $100,000
C. Disease Policy Limit $250,000
Contractors General Liability
A. General Aggregate $6,000,000
B. Products-Completed Operations Aggregate $2,000,000
C. Each Occurrence (Bodily Injury and Property Damage) $6,000,000
D. Personal Injury and Advertising Injury $2,000,000
1. Property Damage liability insurance will provide Explosion, Collapse, and Underground coverages.
Automobile Liability
A. Bodily Injury:
1. Each Person $1,000,000
2. Each Accident $1,000,000
B. Property Damage
1. Each Accident $1,000,000
C. Combined Single Limit $1,000,000
Contractual Liability
A. Bodily Injury:
1. Each Accident $2,000,000
2. Annual Aggregate $2,000,000
B. Property Damage:
1. Each Accident $2,000,000
2. Annual Aggregate $2,000,000
3. Each Accident $2,000,000
4. Annual Aggregate $2,000,000
Professional Liability Errors and Omissions $1,000,000
6.4. Additional Provisions
A. Additional Insured: Contractor shall name the City of San Luis, Arizona (an Arizona municipal corporation) and its elected officials, officers, agents, as “Additional Insureds” on all insurance policies, except Worker’s Compensation and Errors and Omissions, and this shall be reflected on the
Certificate(s) of Insurance, with corresponding endorsement relative to the additionally insured indemnification. Contractor shall name the City of San Luis as certificate holder.
B. Cancellation Notice of Material Change of Coverage: The Contractor shall keep all policies in force for the duration of the Contract and any possible extension thereof. Contractors’ required insurance shall be endorsed to provide that the policies will not be canceled, reduced, discontinued, or otherwise materially altered during the period of performance without thirty (30) days prior written notice to the
City of San Luis Public Workers Department.
C. Certificate(s) of Insurance: Certificates of Insurance shall be Project-specific. Prior to commencing work under the Contract, Certificates of Insurance shall be submitted and approved by the
City. Contractor is responsible for obtaining Certificates of Insurance, establishing that the Contractor and all subcontractors have complied with insurance requirements previously stated. Copies of
Certificates of Insurance shall be forwarded to the City Risk Manager for review and filing. Failure of the City to demand such Certificate or other evidence of full compliance with these insurance requirements or failure of the City to identify a deficiency from the evidence that is provided shall not be construed as a waiver of the Contractor’s obligation to maintain such insurance. City shall have the right, but not the obligation, to prohibit Contractor or any of its subcontractors from entering the
Project Site until such certificates or other evidence that insurance has been placed in complete compliance with these requirements is received and approved by City.
D. Rating of Insurance Companies: Any and all insurance companies supplying coverage to the Contractor shall be approved to write insurance in the State of Arizona and must possess no less than an “A” rating in accordance with the A.M. Best rating guide.
E. Deductible: Contractor shall be solely responsible to satisfy any deductible or self-insured retention with respect to any of the coverages required by the Contract Documents. Such deductibles or self-insured retention shall not be applicable with respect to the policy limits provided to the City of San
Luis. The City of San Luis, at its option, may require the Contractor to secure payment of such deductible or self-insured retention by a surety bond or irrevocable and unconditional Letter of Credit.
F. Rental Equipment: In the event that rental of equipment is undertaken to complete and/or perform the Work, the Contractor agrees that it shall be solely responsible for such rental equipment. Such responsibility shall include, but not be limited to, theft, fire, vandalism, and use by unauthorized persons.
G. Personal Property: In the event that materials or any other type of personal property are acquired for the Project or delivered to the Project site, the Contractor agrees that it shall be solely responsible for such property until it becomes a fixture on the Project, or otherwise is installed and incorporated as a final part of the Project. Such responsibility shall include, but not be limited to, theft, fire, vandalism, and use by unauthorized persons. Contractor shall maintain “all risk” insurance on a replacement cost basis, covering loss or damage to personal property (for which it has title and/or risk of loss), which is to become a final part of the Project, during any time such personal property is in transit and while stored or worked upon away from the Project site. City and its officials, officers, employees, and agents shall be named as additional insured under such insurance.
H. Waiver of Subrogation: City and Contractor waive all rights against each other and Architect/Engineer, and separate contractors for damages caused by fire or other perils covered by Builder’s Risk or any other property insurance, except such rights as they may have to the proceeds of such insurance.
I. Right to Require Higher Limits: City reserves the right, in its sole discretion, to require higher limits of liability coverage if, in the City’s opinion, operations by or on behalf of the Contractor create higher-than-normal hazards and to require the Contractor to name additional parties in interest to be
Additional Insureds.
J. Waiver of Requirements: The City Manager, in consultation with the City Risk Manager and/or City
Attorney, reserves the right to waive or reduce insurance requirements should it be in the best interest of the City.
GENERAL CONDITIONS OF THE CONTRACT
SECTION 1 - Bidders Participation Subcontractors and Suppliers List
These General Conditions encompass provisions that apply and are incorporated into all construction contracts entered into by the City of San Luis unless otherwise specifically excluded in the executed Contract.
Sections 2 through 14 of these General Conditions apply to all construction contracts, in whatever form, including without limitation, Fixed Price, Unit Price, Construction Manager at Risk (CM@Risk), Guaranteed
Maximum Price (GMP) Cost-Based, and Job Order Contracts (JOC).
SECTION 2 - GENERAL DEFINITIONS
2.1 The Definitions in the Invitation for Bid (IFB), the Request for Proposals (RFP), the Request for
Qualifications (RFQ), and/or the JOC Solicitation (JOC) giving rise to the Contract shall apply to these General
Conditions and the Contract for the Project.
2.2 Change Order – A written instrument issued after execution of the Contract Documents signed by City and Contractor, stating their agreement upon all of the following: the addition, deletion, or revision in the scope of services or deliverables; the amount of the adjustment to the Contract Price, the extent of the adjustment to the Contract Time, or modifications of other contract terms. Only a Change Order allows the
Contract Price or the Contract Time or both to be changed.
2.3 City – City of San Luis, Arizona, a municipal corporation, with whom the Contractor has entered into the
Contract and for whom the Services and/or Work are to be provided pursuant to the Contract(s).
2.4 Contract - The written agreement executed between the City and Contractor, including all of the Contract
Documents.
2.5 Contract Documents - The documents which together form the Contract between City and Contractor, as identified in Article 2 of the Contract, or are otherwise incorporated into the Contract, including the Contract, the exhibits and attachments to it, these General Conditions, any Notice to Proceed, and any Job Order (if applicable), the Plans and Specifications, Project Schedule, written and properly executed Change Orders, and any other documents so designated in the Contact.
2.6 Contract Price - The agreed-upon price to be paid to the Contractor for full, timely, and acceptable completion of the Services or Work under the terms of the Contract.
2.7 Contract Time(s) - The number of days or the dates related to the Final Completion as stated in Contract
Documents. The Contract Time is set forth in the Contract and is based upon the Project Schedule agreed to by the City in writing.
2.8 Contractor - The person or corporation with whom the City has entered into a contract for construction-related work or services related to the Project at issue. As used in these General Conditions, the term
Contractor includes CM@Risk and JOC under contract with the City to provide pre-construction and/or construction services.
2.9 Contractor Payment Request - The form that is accepted by the City and used by the Contractor in requesting progress payments or final payment and which shall include such supporting documentation as is required by the Contract Documents and/or City.
2.10 Construction Documents - The plans, specifications, and drawings prepared and issued by the Design
Professional and approved by the City for construction, meaning the documents are sealed by the Contractor
(as required), acceptable for permitting, and incorporated into the Contract by reference. All amendments and modifications to the Construction Documents must be approved in writing by the City prior to incorporation into the Contract.
2.11 Critical Path - The critical path is the sequence of Project network activities that add up to the longest overall duration. Once established in the Project Schedule, the Critical Path for the Project shall not be changed without prior written approval of the City.
2.12 Day - Calendar day(s) unless otherwise specifically stated in the Contract Documents.
2.13 Final Acceptance - The written notice from the City to the Contractor that Final Completion has occurred.
2.14 Final Completion - The point when all items of the Work, including punch list items, have been completed to the City’s satisfaction as reflected in the written Final Acceptance.
2.15 Float - The number of Days by which an activity can be delayed without lengthening the Critical Path and extending the Contract Time. Unless otherwise expressly agreed in writing, all Float belongs to City.
2.16 MAG Specifications – The latest edition adopted by the City of the Uniform Standard Specifications for
Public Works Construction published by Maricopa Association of Governments (“MAG”), or the latest revision published by MAG.
2.17 MAG Standard Details – The latest edition adopted by the City of the Uniform Standard Details for
Public Works Construction published by Maricopa Association of Governments (“MAG”), or the latest revision published by MAG.
2.18 Notice to Proceed (NTP) - A written notice given by the City to the Contractor fixing the date on which the Contractor will start to perform the Contractor’s obligations under the Contract. The Notice to Proceed shall not be issued until the Contract Price is approved and accepted by the City.
2.19 Project – The Project specified in the Contract (including the Job Order).
2.20 Project Manager - The Project Manager designated in Article 1 of the Contract, or any successor Project
Manager the City designates. The Project Manager has the authority to act on behalf of the City, as delineated and limited by the Contract Documents and applicable law. The City shall communicate with the Contractor through the Project Manager. However, the Project Manager has no authority to bind the City or City Council in contravention of any City code, State or Federal statute or regulation, or these General Conditions.
2.21 Project Schedule - The schedule for the completion of the Project agreed to and/or required by the City and incorporated into the Contract.
2.22 Project Specific Provisions - Additional conditions that apply to the specific Project and/or Scope of
Work.
2.23 Proposal A Proposal submitted to the City by a Contractor in response to an Invitation for Bid (IFB), Request for Qualifications (RFQ), a Request for Proposals (RFP), or other solicitation or request by the City.
Bids may be Fixed Price, Guaranteed Maximum Price (GMP), Unit Price, or other form as required or requested by the City in the Bid Schedule.
2.24 Requests for Information (RFIs) - Formal written request from the Contractor to the City and/or
Contractor for the Project seeking clarification or additional information needed for the Contractor to properly complete the Work and/or Services under the Contract. The City may require RFI’s to be submitted on a specific form or in a specified format.
2.25 Schedule of Values (SOV) - The specified document prepared by the Contractor and approved and accepted by the City, which divides the Contract Price into pay items, such that the sum of all pay items equals the Contract Price for the construction phase Work, or for any portion of the Work having a separate specified
Contract Price.
2.26 Scope of Work The scope of work agreed to and/or required by the City and incorporated into the
Contract as set forth in the IFB and/or an Exhibit to the Contract.
2.27 Subconsultant A person, firm, or corporation having a Contract with a Consultant/Contractor to furnish services required as its independent professional associate or consultant with respect to the Project.
2.28 Subcontractor - An individual or firm having a direct contract with the Contractor or any other individual or firm having a contract with the aforesaid contractors at any tier, who undertakes to perform a part of the pre-construction services or construction phase Work at the site for which Contractor is responsible.
Subcontractors shall be selected through the Subcontractor selection process described in the Contract
Documents, if any.
2.29 Supplier. Any person or entity providing materials or property for the Project.
2.30 Total Float. The number of Days by which the pre-construction services or construction phase Work or any part of the same may be delayed without necessarily extending a pertinent Contract Time or schedule milestone in the Project Schedule.
2.31 Work - The entire completion of construction or the various separately identifiable parts thereof, required to be furnished during the construction phase. Work includes and is the result of:
a. performing or furnishing labor;
b. furnishing and incorporating materials, resources, and equipment into the construction; and
c. performing or furnishing services and documents as required by the Contract Documents for the construction phase.
SECTION 3 - STANDARD SPECIFICATIONS AND DETAILS
3.1 The City operates under the 2016 City of San Luis Supplement to the 2015 MAG Uniform Standard
Specifications for Public Works Construction.
3.2 The City also operates under the 2009 City of Yuma Construction Standard Detail Drawings.
3.3 The City also operates under the 2006 Yuma County Public Works Standards – Volume III – Storm
Drainage Facilities.
3.4 The above standard specifications and details may be viewed and downloaded at the City of San Luis website: https//www.sanluisaz.gov/DocumentCenter/Index/268. 3.5 The City may require particular sections of the revisions of the MAG Specifications and Standard Details after the 2015 revision that the City adopted.
3.6 Current and Historical MAG Specifications and Standard Details may be viewed at the Maricopa
Association of Governments website at https://azmag.gov/Programs/Public-Works/Specifications-and-Details.
3.7 The MAG Specifications and Standard Details and the City’s amendments to them are incorporated into the Contract.
SECTION 4 - CONTRACTOR’S RESPONSIBILITIES FOR CONSTRUCTION SERVICES
4.1 General
4.1.1 The Contractor shall construct the Work in accordance with the Contract Documents and as outlined in the Contract Documents to the satisfaction of the City, exercising the degree of professional care, skill, diligence, quality, and judgment that a professional Contractor engaged, experienced, and specializing in the construction of facilities of similar scope, function, size, quality, complexity, and detail in urban areas throughout the United States comparable to the City would exercise at such time, under similar conditions. The Contractor shall, at all times, perform the Work in conformance with sound and generally accepted engineering principles and construction management and construction contracting practices.
https://azmag.gov/Programs/Public-Works/Specifications-and-Details
4.1.2 The Contractor shall comply with, and require all Subcontractors to comply with, the Arizona
Contractors’ license laws, including all requirements with respect to being duly registered and licensed.
4.1.3 Pursuant to A.R.S. § 41-4401, the Contractor warrants to the City that the Contractor and all its
Subcontractors are in compliance and will comply with all Federal Immigration laws and regulations that relate to their employees and with the E-Verify Program under A.R.S. § 23-214(A). The Contractor acknowledges that a breach of this warranty by the Contractor or any of its Subcontractors is a material breach of this Contract subject to penalties up to and including termination of the Contract or any subcontract. The City retains the legal right to inspect the papers of any employee related to this statute and of the Contractor or any Subcontractor who works on this Contract to ensure compliance with this warranty. The City may conduct random verification of the Contractor’s employment records and any of its Subcontractors’ employment records to ensure compliance with this warranty. The City will not consider the Contractor or any of its Subcontractors in material breach of the foregoing warranty if the
Contractor and its Subcontractors establish that they have complied with the employment verification provisions prescribed by 8 USCA §1324(a) and (b) of the Federal Immigration and Nationality Act and the e-verify requirements prescribed by Arizona Revised Statutes § 23-214(A). The provisions of this Section must be included in any agreement the Contractor enters into with its Subcontractors who provide services under this Contract or any subcontract. “Services” are defined as furnishing labor, time, or effort in the State of Arizona by a contractor or Subcontractor. Services include construction or maintenance of any structure, building, or transportation facility or improvement to real property.
Breach of this warranty shall constitute a material breach of the contract and shall subject the
Contractor to penalties, including termination of the Contract at the sole discretion of the City.
4.1.4 The Contractor further understands and acknowledges the applicability of the Americans with
Disabilities Act, the Immigration Reform and Control Act of 1986, and the Drug-Free Workplace Act of
1989 to the Contract. The Contractor understands and acknowledges that it must also comply with
A.R.S. § 34-301, “Employment of Aliens on Public Works Prohibited,” and A.R.S. § 34-302, as amended, “Residence Requirements for Employees,” and A.R.S. § § 12-2701 through 12-704 “Immigration and
Nationality Law Practice Act” as amended.
4.2 Contractor’s Pre-Contract and Pre-Work Deliverables
4.2.1 Before beginning any Work under the Contract, the Contractor shall execute the Contract and deliver to the City the items listed in Section 4-2.2 below within seven (7) days after the award of the
Contract, and the City must execute the Contract. Failure to do so will be a material breach of the
Contract, entitling the City to terminate the Contract for Cause.
4.2.2 When the Contractor delivers the executed Contract to the City, the Contractor shall also deliver to the City such bonds and certificates of insurance with endorsements in such amounts (and other evidence of insurance requested by the City) required under Section 11 - of these General Conditions, and as the Contract requires.
4.2.3 The Contractor shall obtain all necessary permits for the Work and pay all applicable fees unless otherwise noted on the plans and in the specifications. The Contractor is specifically notified of the need to obtain traffic control permits from the Arizona Department of Transportation (ADOT) and the necessary environmental permits or file the necessary environmental and regulatory permit notices.
Copies of all permits and the associated notices must be provided to the City prior to starting the permitted activity.
4.3 Pre-Construction Conference
4.3.1 Prior to the commencement of any Work, the City may schedule a Pre-Construction Conference.
4.3.2 Prior to the Pre-construction Conference, the Contractor shall provide the Project Manager with a
Schedule of Values reflecting the subcontracts and other categories that will be used to submit pay applications for the Work. The total amount of the Schedule of Values shall not be greater than the
Contract Price. The Schedule of Values shall be reviewed at the Pre-Construction Conference and revised in response to comments and questions from the City. Once accepted by the City in writing, the
Schedule of Values for the Project will not be changed without the City’s prior written approval.
4.4 Performance of the Work (Including Field Measurements, Subcontractors, and Suppliers)
4.4.1 Unless otherwise provided in the Contract Documents to be the responsibility of the City or a separate Contractor, the Contractor shall provide through itself or its Subcontractors the necessary supervision, labor, inspection, testing, start-up, material, equipment, machinery, temporary utilities, and other temporary facilities to permit Contractor to complete the Work consistent with the Contract
Documents.
4.4.2 The Contractor’s Superintendent shall be present at the Project site at all times that material Work under this Contract is taking place. The Contractor’s Superintendent or designee shall be present at the
Project site at all times any other Work under this Contract is taking place. All elements of the Work shall be under the direct supervision of a foreman or his designated representative on the Project site, who shall have the authority to take actions required to carry out that particular element of the Work properly.
4.4.3 Before ordering materials or doing work, the Contractor and each Subcontractor shall verify measurements at the Project site and shall be responsible for the correctness of such measurements.
No extra charge or compensation will be allowed because of differences between the actual dimensions and the dimensions indicated on the Contract Documents, including the drawings.
4.4.4 If the Contractor observes errors, discrepancies, or omissions in the Contract Documents, it shall promptly notify the Contractor and City and request clarification. The Contractor shall be liable to the
City for damages resulting from errors, inconsistencies, or omissions in the Contract Documents or for differences between field measurements or conditions in the Contract Documents. If the Contractor, with the exercise of reasonable care, should have recognized such error, inconsistency, omission, or difference and fails to report it to the City, and if the Contractor proceeds with the Work affected by such observed errors, discrepancies, or omissions, without receiving such clarifications, it does so at its own risk.
4.4.5 In all cases of interconnection of its Work with existing or other work, the Contractor shall verify at the Project site all dimensions relating to such existing or other work. Any errors due to the Contractor’s failure to so verify all such grades, elevations, locations, or dimensions shall be promptly rectified by the
Contractor without any increase in the Contract Price. Any design errors or omissions noted by the
Contractor during this review shall be reported promptly to the City.
4.4.6 The Contractor shall be responsible for the proper performance of the Work of Subcontractors and any acts and omissions in connection with such performance. Nothing in the Contract Documents is intended or deemed to create any legal or contractual relationship between the City and any
Subcontractor or Sub-Subcontractor, including but not limited to any third-party beneficiary rights.
4.4.7 The Contractor will not substitute or change any Subcontractor or Supplier without the City’s prior written approval. Any substitute or replacement Subcontractor or Supplier shall be required to meet the same qualifications and selection criteria and process as the original Subcontractor or supplier. If a
Subcontract or Supplier selection plan has been approved by the City, the Contractor will follow that plan unless otherwise approved by the City in writing.
4.4.8 The Contractor shall not change or replace the Contractor’s Project Manager or Superintendent on this Project without an explanation for the change being given to the City and receiving prior written approval of the change from the City, which approval will not be unreasonably withheld.
4.4.9 Subcontractors whose scope of work has a value greater than fifteen percent (15%) of the total
Contract Price may be required to furnish performance and payment bonds to the Contractor if directed in writing by the City.
4.5 Control of the Project Site
Throughout all phases of construction, including suspension of Work, the Contractor shall keep the Project site reasonably free from debris, trash, and construction wastes to permit the Contractor to perform its construction services efficiently, safely, and without interfering with the use of adjacent land areas.
This is the start of the file's text. The full file is on GovTribe.