SOLICITATION NO: W91ZRS-18-R-0002 (PROJECT NUMBER: CEKT139029) CONSTRUCT BASE ENTRY COMPLEX, BRADLEY AIR NATIONAL GUARD BASE, EAST GRANBY, CT

RFIS ANSWERS DATE ANSWERED

There was discussion at the pre-bid meeting regarding requirements of the General Contractor for the management and re-use of the top 9 inches of existing topsoil. The contract documents do not address this requirement. Please provide stockpile areas and management requirements.

Due to historic presence of contaminated soils on Base, no excavated soils are to be removed from Base Property (the job site area). Any excavated soils are to be stockpiled on site. Stockpiled soils, where not required to be covered with topsoil and seeded for erosion control or other "best practices" reasons, are to be left exposed (not covered) per CT DEEP recommendations. Beyond this, there are no specific contaminated soils remediation measures associated with this project. 8/8/2018

Reference Utility Company TX Pad site. Are bollards required at the TX pad location? In an on-site meeting with EVERSOURCE, the EVERSOURCE technician indicated that he would like to see three 8-inch diameter bollards (Utility Protection Bollards) provided around the transformer pad. We also recommend additional Utility Protection Bollards around the proposed lift gate operator and sensor mounting equipment. We have modified Drawing CU101 to reflect these changes.

8/8/2018

Reference "Force Protection Bollard Detail" on CD104. Please locate these bollard types. The (5) bollards identified as "K-8 Rated Force Protection" bollards on Sheet CD104 will be changed to read "Utility Protection Bollard Detail." Locations for use of these bollards are depicted on Sheet CL101.

Note: There are now (4) Types of Bollards:

(10) 6" Removable Bollards (See CD103);

(12) Security Bollards w Covers (7-11/LS504);

(5) Pipe Bollards w Covers (Details 4-6/LS504);

(3) 8" Utility Protection Bollards (See CD104);

Note: Security bollards have the same covers as the pipe bollards. Reference on the drawings for the covers for the security bollards refers to details 8 & 9 but should refer to details 4-6. We will revise Detail 9, Sheet LS504 to "Refer to Details 4-6/LS504." Detail 8, Sheet LS504 shall refer to details 9-11, not just 9 and 11.

8/8/2018

Areas of OLI # 1 and # 3 decorative concrete paving, the thickness and reinforcing of the concrete is not detailed for the vehicular concrete or the island cap concrete. Please provide details.

We have provided an additional section for the concrete in the drive lane (8-inches of Portland cement concrete over 8 inches of processed aggregate, called Concrete Pavement Section) and concrete cap in the curbed islands (5 inches of Portland cement concrete over 6 inches of processed aggregate base course called Curbed Island & Median Detail Sections). These sections have been added to the plan set via addition of Sheet CD105. The decorative concrete paving will consist of a stamped pattern color-enhanced Portland cement concrete. The specific pattern and color is stated in a specification excerpt attached to this document - namely (and among others) "Color: Basis of design is Bomacron Steadman Buff" (or approved equal) and "Imprinting Tools: Basis of design is Bomacron Herringbone Used Brick" (or approved equal). There will be the same thickness & reinforcing for both pavement types.

8/8/2018

Spec Section 321313, 1.1, E notes "Concrete paver units in vehicular areas." Please locate and provide a specification.

There are no Concrete Paver Units in this job. References will be stricken from the specifications.

8/8/2018

Spec Section 012300, OLI-#3 states to furnish and install decorative paving in lieu of broom finish. Please confirm that the base bid is concrete paving in the same areas with broom finish and provide details for tooling and/or control joints.

The base bid is broom-finish concrete in the same areas. Tooling and control joints shall be per CT DOT Form 817. In general, contraction joints shall be provided no more than 20-feet on center, with tooled joints, on average every 5 feet. Tooling and joint pattern should be proportional and laid out in an aesthetic manner. Pattern to be approved by the A/E. 8/8/2018

Are the three areas within the concrete CIP curbs and the exterior of the building concrete paving? If so, provide details, reinforcing, mix, etc.

Yes. The three areas are treated with a Portland Cement concrete finish. The section calls for a 5-inch thick concrete slab over 6 inches of compacted process aggregate base (See Sheet CD105). We are generating new sections to depict the slab and curb. We are also adjusting the grading slightly in the area around the Gate House and adding additional spot grades for top and bottom of curb to better show the construction detail of this area, and grading transitions to provide ADA access to the building and adjacent walks (See Sheet CG101). 8/8/2018

Where bituminous paving cuts are made for water and sewer connections and the curb cut on Rte 20, please provide the associated paving details.

All work within the state highway ROW shall be conducted following the requirements of the CT DOT.

The trench repair section for work in the DOT ROW is depicted on Sheet CD105. 8/8/2018

9 Where CIP curbing is called out on the drawings, can pre-cast curbing be substituted?

No. All Portland cement concrete curb and integral concrete curb and sidewalk shall be cast-in-place concrete. Pre-cast is not allowed. 8/8/2018

Confirm that ALL bituminous pavement in the area surrounding the Guard building is "Heavy Duty".

All pavement on the project is heavy-duty pavement, with the exception of the passenger parking areas depicted on Sheet CL101 (see shaded areas). All bituminous pavement in the area surrounding the gate house is heavy-duty bituminous pavement. 8/8/2018

11 "Pavement Section (light duty)". Please locate where this detail is used? See Sheet CL101, shaded areas.

8/8/2018

Beginning at the intersection of Thunderjet and Super Saber Roads, what pavement section is to be used? Since the existing road is being widened, provide details of demolition / milling / reuse of millings / new pavement details.

All pavement on the project is heavy-duty pavement, with the exception of the passenger parking areas depicted on Sheet CL101 (see shaded areas). Use the heavy-duty pavement section for all roadways and drives with the exception of the passenger parking areas depicted on Sheet CL101 (see shaded areas). The heavy-duty pavement section is shown on Sheet CD101. All pavement sections for the heavy-duty pavement, must conform to the section shown. Should the contractor elect to reclaim and re-use the existing subbase, base course and/or bituminous materials, that would be acceptable, and even encouraged. The re-claimed materials however will need to conform with the materials specifications noted on the detail (i.e., CT D.O.T. Form 817, Section M.05.01, and Section M.02.03).

8/8/2018 13 "Continuous spray in place insulation". Provide a thickness. 6 inches. 8/8/2018 14 Confirm that the elevated slab is 4000 psi normal weight concrete. Yes. Elevated slab is 4000 psi (at 28 days) normal weight concrete.

8/8/2018

Confirm that both the wall and sofftt panels are 4 inches thick and 30 inched wide. Plans appear to indicate different widths and thicknesses.

Yes. The panels are 4 inches thick as shown, and a maximum of 30 inches wide. Some portions of the canopy and building will require less than 30 inches wide. 8/8/2018

Lift Gate Detail. Please provide a basis of design. Provide DKS DOORKING Model 1601 (Basis of Design) or approved equal. See attached product data to further clarify scope & pricing. 8/8/2018 17 ...indicates "concrete island (typical of 4)". Please provide details of concrete cap. See response to Item No. 4 above. 8/8/2018

Drawing LS401, detail 4 conflicts with 3/CL102 and adds decorative paving plus an inner curb and turf? Please provide details for 4/LS401.

Detail 4/LS401 states that the decorative concrete is an Optional Line Item. The detail lays out the shape of the paving if the option is taken. Paving sections are no different for decorative concrete than regular concrete. Refer to the civil details for paving sections. 8/8/2018

Drawing CG102, detail2, appears to be two Communication manholes within the decorative concrete paving. Please clarify the work needed to accomplish this task.

The manhole frames and covers shall be constructed to match the proposed finish grade of the decorative concrete surface. This will require matching the proposed cross-slope of the island at the proposed finish grade to provide a smooth, continuous grade across the decorative concrete.

Placement of the concrete around the manhole cover shall be done with the placement of the entire surrounding slab to form a uniform look. Separate pours around the frame (i.e., to create a concrete apron) is not allowed. 8/8/2018

Drawings CE101 through CE103, note 9 indicates "a construction sequence and phasing as outlined on these plans". Information not found on the plans. Please provide.

A general sequence of construction will be added to the plans (Sheet CE101 -CE103). Detailed construction phasing plans shall be created by the Contractor and become part of the site-specific Stormwater Pollution Prevention Plan. 8/8/2018

Drawing S-001, Soil and Foundation notes: Note 1, references a "soil study prepared by Welti Geotechnical". Please provide study.

The soils and geotechnical report was not included in the specifications as it may contain information for design which may not be applicable to these contract documents. Please see the attached file for boring location plans and logs which may be helpful. 8/8/2018

Drawing S-001, Steel Construction Notes. Please confirm that all structural steel must be fabricated and erected by an AISC certified fabricator and erector.

AISC certification is not required of the fabricator or erector for this contract. The selected fabricator and erector are required to follow the quoted AISC procedures and tolerances. 8/8/2018

Reference specification 090690, Color Schedule. Color schedule indicates masonry materials shall match the New Small Air Terminal Building. Should the Roofing, Windows, Louvers, Metal siding and Metal soffits match the same building?

Follow specification 090690, Color Schedule, for roofing, window frame, louvers, metal siding, and metal soffits. For window glazing, see Section 085653. Glazing samples will need to be submitted to verify security visibility. Color should be similar to PPG Industries Solargray, and material must be bullet resistive level V. 8/8/2018

Reference "IBC 205 Structural Tests and Inspections". Section lists all special inspections for the project but does not include testing of bituminous pavements? Please clarify.

The “IBC 2015 Structural Tests and Inspections” is a list of items for the “special inspector” to verify.

Special Inspections are typically limited to building elements and are in addition to the normally required quality control and quality assurance inspections required elsewhere in the specifications. For testing of bituminous pavements please refer to the bituminous concrete paving and curb specification (Specification section 321200). 8/8/2018

On drawing AE101 “Sheet Keynotes” Item # 7. Coat Hook & Hat Rack. This item is not identified in the specs. All other items are, please advise.

Provide fixture. Basis of Design Product: Bobrick D-6827; Finish: Satin Stainless Steel; Mounting:

Concealed fasteners. 8/8/2018

Please advise who the alarm/security panel company is for this base. We are interpreting this question to refer to the (on or off base) parties that will receive fire and security alarming from said panel. Said alarming will be received by Bradley ANG Base Fire and (BDOC) Security Forces. 8/8/2018

27 Is a SWPP required by the contractor? The Base is registering for the Stormwater GP and is generating the SWPPP. 8/8/2018

Reference project specifications. There are no specifications provided for the Main Gate sign indicated on drawing LS501. Please provide.

The design of the New Base Entry Sign (outside of sign base and general format detailing shown on Sheet LS501 and as noted in Installation Sign Detail 1, Sheet LS501) is to be "by Sign Manufacturer" (Designated Design). Bidding Contractors are to consult a sign manufacturer for conceptual detailing and pricing for bids. Designs to function with base detailing shown on Sheet LS501 and are to strictly adhere to guidelines outlined in UFC 3-120-01 - DESIGN: SIGN STANDARDS, dated 1 March 2014, Changed 2, 7 October 2014, paragraphs 3-1.5, 3-2.2 and 3-2.4 (among others). Conceptual signage detailing used for bidding purposes shall be carried over by the successful bidder to a schedule of values during construction. 8/8/2018

Reference project specifications. There are no specifications provided for Division 21, Fire Protection, however the bid form contains a line item for Division 21, Fire Protection.

Division 21 specifications are not required. A sprinkler system is not required for this building. See Amendment 0001 for revised BID SCHEDULE. 8/8/2018

Reference the Bid Form. Bid form contain Division 01 through 33. Specifications contain Division 2, Site Clearing/Utility Drainage Line removal. Where should Division 2 costs be included on the bid form?

See Amendment 0001 for revised BID SCHEDULE.

8/8/2018

Reference the Bid Form. Bid form contain Division 01 through 33. Specifications contain Division 34, Crash Bollards. Where should Division 34 costs be included on the bid form?

See Amendment 0001 for revised BID SCHEDULE.

8/8/2018

Due to the geographic acreage of this project, will a Storm Water Pollution Prevention Plan be required?

If yes, will it be filed with the State of CT?

If yes, and there are fees associated with it, who is responsible for the fees?

Yes. A SWPPP will be required. The Base is registering for the Stormwater GP and is generating the

SWPPP.

8/8/2018

Has an FFA permit been filed with the CT Airport Authority for this project? Assuming you meant FAA permit then Yes. Several FAA 7460s have been submitted and approved by the FAA for this project. The most stringent (tallest items) were a part of this submittal. Several additional items are being submitted at this time to address the remainder of the site.

8/8/2018

Reference drawing CU 101. Drawing note indicates "O.F.C.I. generator (22 kva generator OLI#4)". Reference drawing ES101. Drawing note indicates "30KVA generator".

Spec section O12300-2,D1 states "new unit shall meet all requirements to support the ECF energy requirements".

Question 1, does OFCI mean Owner furnished contractor installed?

Question 2, is the generator 22 or 30 kva?

Question 3, what are the requirements of the ECF?

Question 4, what fuel type is the generator?

Question 5, if the fuel type is diesel, what is the required run time on a single tank?

Question 6, if the fuel type is gas, the plans do not show any gas service on the project?

Please provide a specification for the generator.

Please clarify the base bid versus the OLI # 4 scope of work

1. Yes. OFCI does mean Owner Furnish / Contractor Install.

2. The existing generator is a 25 kVA generator. The minimum required size generator (if OLI #4 is taken) is 30 kVA.

3. See EP701 single line diagram identifying the ECF systems to be supported on emergency power by this generator. 4. The existing generator is diesel powered.

5. 24 hours.

6. Generator is not NG powered.

7. All provisions for emergency power and generator connection shall be provided in base bid. The only item *not* in the base bid will be the generator itself. Wire, raceway, pad, etc. are all part of base bid.

8/8/2018

Reference Drawing LS40 I, There are multiple notes regarding "decorative concrete paving".

Reference Spec section 321313-2, 2.1-H, Indicates tinting of stamped concrete.

Please confirm herringbone brick pattern shown will be the stamping pattern that will be used.

Please confirm what color tinting will be used.

1. Herringbone Brick Pattern shall be the stamped pattern (OLI#3 Only). The Base Bid is Broom Finish Concrete. 2.

Color Tinting will be used (OLI #3 Only). Base Bid will have no color tinting. See attached Specification excerpt addressing the Colored & Patterned / Texture Concrete Finish.

8/8/2018

Reference specification 071326. Section indicates a 60 mil, self adhering modified bitumen sheet waterproofing.

Throughout the A drawings there are numerous notes indicating differing descriptions of the exterior wall waterproofing such as:

a. Waterproofing membrane

b. Fluid applied waterproof membrane

c. Cont air barrier Please clarify the type of waterproofing system to be used on the exterior side of the CMU back up wall.

Use specification section 072726 Fluid-Applied Membrane Air Barriers for waterproofing system to be used on the exterior side of the CMU back up wall. “Cont air barrier” is a notation for federal guidelines.

Section 071326 is not required for this project.

8/8/2018

The project specifications mention a geotechnical report by Clarence Welti Associates, Inc.

which should have that data, but I’m not sure where to find it. Would you happen to know where I could locate the geotechnical report?

The soils and geotechnical report was not included in the specifications as it may contain information for design which may not be applicable to these contract documents. Please see the attached file for boring location plans and logs which may be helpful. 8/8/2018

Reference Drawing CL10I. Entrance island containing entrance sign and flagpoles indicates the following language "Landscape Island".

Reference LS401. The same island is indicated as "Decorative Concrete paving as OLI-3.

Question #1, Is the base bid finish Landscaping or Broom finish concrete?

Question# 2, If the base bid finish is landscaping please provide a landscape plan.

1. Base Bid Finish is Broom Finish Concrete.

2. The Landscape components of this Island, (primarily on the plan-south end) which are all Base Bid Items, are shown in 1/LS101, 1/LS102, 1&2/LS401, 2/LP401 & LP501.

8/8/2018

Please clarify: Drawing ES-101 calls for a lighting control relay panel to be provided in a weather proof enclosure, This panel is not listed in the panel schedule or listed in the keynotes.

The exterior lighting circuits shall be controlled via photocell and timeclock combination. A multi-pole contactor or relay panel shall be the vehicle for circuit control. The equipment may be installed in a NEMA 3R enclosure and mounted on a unistrut frame where shown, or it may be installed within/above the guard building’s electrical room. 8/8/2018

Specification 312300, paragrapgh 1.3 references a Geotechnical Report by Dr, Clarence Welti.

The project documents did not include a geotech report.

The soils and geotechnical report was not included in the specifications as it may contain information for design which may not be applicable to these contract. See the attached file for boring location plans and logs which may be helpful. 8/8/2018

Drawing EP-701 shows us providing utility and base metering. Please describe the product requirments for this.

Please refer to attached pdf detailing EVERSOURCE Energy’s requirements.

8/8/2018

Drawings EP101 (7 - 4" Conduits) and ES-104 Key Note 4 show us providing conduits. Are the conduits empty or do they require a pull string?

The conduits will require a pull string.

8/8/2018

Drawing ES101 shows a 30KVA Generator. Specification 263600 describes the transfer switch requirements. There is no generator specification inlcuded in the documents. Is the generator part of our bid scope? Is the Generator GFCI or GFGI? Is this an existing generator?

Please see response to Item No. 34, part 7 above. A generator specification will be provided.

8/8/2018

The solicitation is requesting LEED qualifications be submitted with the proposal, however the Project specifications do not include a section on sustainable design requirements, LEED scorecard, or any other information indicating that this is a LEED project. Please clarify the LEED requirements of for this project.

See Amendment 0001 for revised Sections 00110 and 00120.

8/8/2018

Can another site visit be scheduled?

No. Only one Site Visit will be executed for this project.

8/8/2018

Considering the large amount of unanswered RFI's will the bid date be extended. Per Amendment 0001, proposal due date is now 29 August 2018 by 2 p.m.

8/20/2018

Subfactor 3 – Quality Control

2.5.2.5. Subfactor 3: Quality Control. The proposal narrative demonstrates that the quality control staff, with lines of authority, is adequate to meet the contract’s requirements. The proposed Quality Control answers should provide a detailed explanation of how quality issues are dealt with on various types of construction projects and as a minimum, meetings, inspections, submittal reviews, correction of non-compliant work and how you intend to ensure non-reoccurrence and reporting of quality problems to Government officials. (Note: A Quality Control Plan is not required with this proposal).

2.2.6. Subfactor 3 - Quality Control: The proposal narrative demonstrates that the quality control staff, with lines of authority, is acceptable to meet the contract’s requirements. Proposal demonstrates acceptable quality control processes to give the government confidence of the offeror’s ability to successfully manage the material submittal process, and ensure subcontractor compliance with contract documents. The proposed Quality Controlanswers should provide a detailed explanation of how quality issues are dealt with on various types of construction projects and as a minimum, meetings, inspections, submittal reviews, correction of non-compliant work and how you intend to ensure non-reoccurrence and reporting of quality problems to Government officials.

(Note: A Quality Control Plan is not required with this proposal).

As this is primarily a horizontal construction project and there is a specific schedule of tests to be conducted we are not sure how the described Subfactor 3 pertains to this solicitation, nor do we find any specific requirements for an On-site Quality Control Manager.

Almost all Quality Control is called out to be by independent testing companies

Submit a proposal in accordance with Sections 00110 and 00120 of the solicitation.

Subfactor 4 – LEED® (limit resumes to 2 pages each)

2.5.2.6. Subfactor 4: LEED®. Discuss company experience with building to United States Green Building Council (USGBC) LEED® standards. Indicate any previous projects that achieved USGBC LEED® certification, any level of recognition. Additionally, indicate the key construction personnel and demonstrate they have experience and required qualifications in assigned roles with building to USGBC LEED® standards. If no experience so state and indicate in detail how you plan to overcome this lack of experience. The onus is solely on the offeror to indicate in detail how the offeror plans to overcome this lack of experience. (Resumes or experience cut sheets are limited to 2 pages each and are not part of the page count.) In the event the intended person is not part of the offeror’s organization at the time the proposal is submitted then a completed Exhibit B, “Subcontractor/Team/Key Personnel Information and Consent Form” is also required or the information will not be considered. This subfactor is limited to ten (10) pages excluding the table of contents, dividers, tabs, indexes, experience cut-sheets and resumes.

2.2.7. Subfactor 4 - Experience with building to United States Green Building Council (USGBC) LEED® standards:

An acceptable proposal demonstrates experience with building to United States Green Building Council (USGBC) LEED® standards. The Government will evaluate the number and magnitude of previous projects that achieved USGBC LEED® certification, or any level of recognition. Experienced key construction personnel are identified with required qualifications in assigned roles with building to USGBC LEED® standards. If no experience is indicated, the Government will evaluate the offeror’s proposed approach for overcoming the lack of experience. For any intended personnel who are not part of the contractor’s organization at the time of proposal submission, the Government will verify submission and proper completion of Exhibit B, “Subcontractor Information and Consent Form”.

We don’t find any reference in the project specifications for LEED requirements

See Amendment 0001 for revised Sections 00110 and 00120.

8/20/2018

Under Amendment 03, CG102 was issued twice. Should one of these files have been CE102?

Please advise.

Drawing CE102-2018-08-03 now posted to solicitation package on FBO.gov.

8/20/2018

It appears there should have been a drawing CE 102-2018-08-03 in the update, but 2 copies of CG 102-2018-08-03 are listed and download the same.

Could you clarify whether or not CE 102 should have been include?

Drawing CE102-2018-08-03 now posted to solicitation package on FBO.gov.

8/20/2018

Drawing CU-102 it requires us to provide 3 handholes but to match existing? What are the specifications for the existing handholes?

Communications Handholes are Type 1 or Type 2, as depicted on CD103, and as called out on CU102.

8/20/2018

Detail #1 on M-801 references SS-1,2,3 this unit designation is not shown on the mechanical schedule or the mechanical drawings. Are these units part of the project?

Unit designation shall be AC-01/CU-01 and AC-02/CU-02 for detail 1.

8/20/2018

Detail #3 on M-801 only references AC-01. What is the sequence for AC-02 serving the electrical room?

AC-02/CU-02 shall run off of thermostatic control.

8/20/2018

Will the (2) two infrared heaters be controlled by the EMCS? The infrared heaters shall only be monitored by the ECMS to show whether they are on or off.

8/20/2018

Note “I” on EP101 makes reference to drawing BEC01 and BEC02 neither are included in the drawing set. Can you please provide these drawings?

See attachment "Item 58 - NGBCT Base…" containing the Base Comm Map and a Copper Fiber Endpoint Map.

8/20/2018

There doesn’t appear to be a site demolition plan. There was existing paving and stone on the project site. There doesn’t appear to be any drawings calling for the removal of any of the existing materials. Please advise.

The town of East Granby will be removing the existing concrete barriers before the project breaks ground.

8/20/2018

Will contractors have full use of the project site or will access through the site need to be maintained?

Access through the site will need to be maintained/managed. The Base will provide a temporary “security” fence with gate (as identified on the attached drawing- spanning the area of the traffic circle to the airfield fence) freeing-up the project site to the south and southwest for contractor use. Site access will be established by the Contractor at the existing Rainbow Road (Route 20) gate. Contractor to manage construction traffic at this entrance in a manner meeting all safety and security requirements by the Base, the Airport, the City of East Granby, and the State of Connecticut.

Base access to facilities which are currently accessed off of the existing Super Sabre and Thunderjet Roads (i.e. the Munitions Storage area) will need to be provided by the Contractor throughout construction and upon request from the Base. Very low frequency is anticipated.

Upon completion of work south of the temporary security fence (or at a time best suited for Contractor phasing of the work), the temporary “security” fencing will be opened allowing further demolition and construction to take place on remaining road and foundation work to the north.

The Contractor shall make every effort to minimize construction traffic through the Main Base Gate.

8/20/2018

Drawing LS401 depicts what appears to be pavers or stone bordering the grass swale but not identified.

What is the material? Size? Composition of the system?

The plans call for a 2-foot wide apron made of CT DOT Special rip rap along the edge of pavement. See Roadway Section on Sheet CD102.

8/20/2018

Drawing LS101 depicts grass and sod locations. Drawing LP-501 does not mention the minimum topsoil depth required for grass, shrubs or tree's. What is the minimum topsoil required for each?

Refer to Specification Section 329113 Soil Preparation, paragraphs 3.2 through 3.4. Grass mix C does not receive topsoil.

8/20/2018

Can CADD Drawings be made available pre-bid? CADD Drawings will not be available during the pre-bid phase.

8/20/2018

As this is primarily a horizontal construction project and there is a specific schedule of tests to be conducted we are not sure how the described Subfactor 3 pertains to this solicitation, nor do we find any specific requirements for an On-site Quality Control Manager.

Almost all Quality Control is called out to be by independent testing companies.

A full-time Quality Assurance Manager is required.

Please confirm if this material will meet the warranty and the specs for the standing seam metal roofing.

a. 24 Gauge baked on finish over Galvalume ASTM A-792-83, AZ50, 50 KSI yield point, 52 KSI tensile strength 22 Gauge baked on finish over Galvalume ASTM A-792-83, AZ50, 50 KSI yield point, 52 KSI tensile strength.

Substitution Requests are typically submitted by Bidding Contractors through the Base Civil Engineer.

The information submitted for comparison is incomplete. Judging from the limited information provided, the proposed materials do not meet project specifications.

8/20/2018

Please confirm if reclaiming of the existing asphalt and re-use of that material for the new asphalt base, will be acceptable.

Reclamation/re-use the existing subbase, base course and/or bituminous materials is acceptable, and even encouraged. The re-claimed materials however will need to conform with the materials specifications noted on the details/section (i.e., CT D.O.T. Form 817, Section M.05.01, and Section M.02.03).

8/20/2018

CU-101 says that the generator is owner furnished contractor installed. It is also listed as optional line item 4. I don't see any specifications other than the following and the notes on the drawings. Spec Section 012300 D. OLI No. 4: Furnish and install an emergency generator. 1.

New unit shall meet all requirements to support the ECF emergency power needs.

a. Please confirm the requirements to support the ECF emergency power needs

All provisions for emergency power and generator connection shall be provided in base bid. The only item *not* in the base bid will be the generator itself. Wire, raceway, pad, etc. are all part of base bid. A generator specification will be provided.

8/20/2018

The sidewalk with curb details shows 6” of gravel, while the plain sidewalk detail shows 8” of gravel.

a. Please confirm this is correct, or if they should match.

All five (5) inch- thick Portland cement concrete sidewalk slabs should be constructed with a 6-inch compacted processes aggregate base course. All 8-inch Portland cement concrete slabs pavement should be constructed with an 8-inch compacted processes aggregate base course.

8/20/2018

Please clarify scope of work for the camera system and advise if they are POE or separate power.

Security Cameras are GFGI. The cameras are PoE.

8/20/2018

Drawing EP101 note I references spec section 260543 and attachments BEC-1 and BEC-2 for the point of origin of the fiber and copper. We do not find the attachments and spec section 260543 does not define the point of origin. Please advise.

See attachment "Item No. 67 - Base Entry Complex…." containing the Base Comm Map and a Copper Fiber Endpoint Map.

8/22/2018

The contract drawings reference security cameras. There are no specifications that relate to security. Are contractors responsible for supplying and installing cameras? If so please provide a specification.

Security Cameras are GFGI.

8/20/2018

There are 3 new dog house man holes shown on CU102. What if any electrical work is required in these manholes. There doesn’t appear to be any shown on the E drawings or CU drawings.

The doghouse manholes are for replacing existing handholes and risers for the Frontier communications copper service that traverses the area. The existing handholes and/or risers are currently located in landscaped areas, off of the existing paved surfaces. The new roadway will be constructed over the existing utility access handholes/risers. The new doghouse manholes will provide the necessary HS-20 load rated access for the utilities. Coordination with Frontier will be required.

8/20/2018

Clarification of general requirements for the following "key Personnel": Project Manager / Site Superintendent / Quality Control Manager / Site Safety Manager Please clarify which of the personnel listed in the solicitation are required to be on site "full time."

A Project Manager, a full-time Site Superintendent and a full-time Quality Assurance Manager are required.

8/22/2018

Please confirm that the General Contractor is responsible for engaging and paying for all independent Testing and Special Inspections in accordance with specification section 014000-5, 1.8, A., 3.

Yes, the General Contractor is responsible for this (coordination and costs).

8/22/2018

There was discussion at the pre-bid meeting regarding requirements of the General Contractor for grounds maintenance through the duration of the project. The contract documents do not address this requirement. Please provide mowing frequency, snowplowing, stockpiling, etc.

The fence needs to be clear at all times of obstructions, leafs and weeds. Mowing frequency should be at a minimum every two (2) weeks. Keep all means of egress clear of snow, snow levels at any egress will not exceed more than three (3) inches of snow at any time. Snow is not allowed to be pushed against the Bradley Air Port fence line.

8/22/2018

Drawing CU101, Drawing note "Remove utility poles CL&P 1757 and 1756 and OH wires back to CL&P 1755 (by Eversource). Please clarify who is responsible for the cost of the work.

The Contractor shall be responsible for coordinating and scheduling the work with EVERSOURCE. For purposes of this project, the total allowance for all the EVERSOURCE involved work will be $25,000 total. 8/22/2018

Drawing CU1O1, Drawing note "Extend 3 phase power overhead. Replace pole 1755 to facilitate service extension. Please clarify who is responsible for the cost of the work.

The Contractor shall be responsible for coordinating and scheduling the work with EVERSOURCE. For purposes of this project, the total allowance for all the EVERSOURCE involved work (not including the pole replacement) will be $25,000 total. 8/22/2018

Drawing CU101, Drawing note "3 phase power in conduit". Please clarify who is responsible for the cost of the work.

The Contractor shall be responsible for coordinating and scheduling the work with EVERSOURCE. The Contractor is responsible for providing, excavating for and installation of the conduit. EVERSOURCE will provide and install the electric primary cables in the conduit, between the riser and transformer pad. For purposes of this project, the total allowance for all the EVERSOURCE involved work (not including the pole replacement) will be $25,000 total. 8/22/2018

Drawing CU101, Drawing note "prop. 30 KVA transformer". Please clarify who is responsible for the cost of the transformer.

The Contractor shall be responsible for coordinating and scheduling the work with EVERSOURCE. The Contractor is responsible for providing, excavating for, and installation of the transformer pad. The transformer will be provided and installed by EVERSOURCE and will be paid for by the Contractor as a part of this project. For purposes of this project, the total allowance for all the EVERSOURCE involved work (not including the pole replacement) will be $25,000 total. 8/22/2018

Drawing EP-701 it shows we are responsible for running conduit and wire to the service transformer outside. Drawing CU101 shows power being extended overhead from the transformer to a new pole. Are we to assume Eversource is doing the pole replacement?

The Contractor shall be responsible for coordinating and scheduling the work with EVERSOURCE. For purposes of this project, the total allowance for this EVERSOURCE involved work (pole replacement only) will be $7,000 total.

8/22/2018

The site utility plans call for three phase power to be extended, poles to be removed and a new transformer to be installed. Typically, the utility companies perform this work. Utility companies typically do not provide estimates for this work prior to work starting. Are contractors responsible for paying the utility companies for this work and if so can an allowance be established to cover these costs since actual costs will not likely be provided prior to bid?

The Contractor shall be responsible for coordinating and scheduling the work with EVERSOURCE. For purposes of this project, the total allowance for this EVERSOURCE involved work (pole replacement only) will be $7,000 total.

8/22/2018

Reference 1/CL102 and Note 5/ES101 "Active Vehicle Barrier". The contract documents do not address this installation. If included in the project, please provide specifications and detail.

See attached Manufacturer's Specifications and Details for the "Delta Scientific Corporation, Model HD 300 EM, Phalanx Type Barricade System." This system is to be used as a “Basis of Design.” Submitted (considered) “equal” systems subject to Government approval. Procure and install all foundations & drainage, associated power & communications cabling & conduit and controls, for a complete, operational and maintainable system - per approved Manufacturer's recommendations.

There will be a single control button on the exterior of the Gate House (ingress lane side) near the guard door for activation of the Final Barrier Units.

8/22/2018

Will re-construction of Thunderjet and Super Saber roads have to be phased? Phasing is not required only close coordination with Base Civil Engineering.

8/22/2018

In reference to page S-001 of the drawings, a Geotechnical Report by Terraconn Consultans is referenced in note 1 under FOUNDATIONS. Can this report be made available?

See answers to RFI #21, #37 and #40 above.

8/22/2018

There doesn’t appear to be a site demolition plan. There was existing paving and stone on the project site. There doesn’t appear to be any drawings calling for the removal or reclaiming of any of the existing materials. Please provide a document showing the existing conditions that need to be removed.

All existing pavement and gravel paving shall be excavated and stockpiled on-site within the project limits. Pavement and gravel materials may be reclaimed for reuse on-site provided they conform with the material specifications noted on the details and the typical sections (i.e. CT D.O.T. Form 817, Section M.05.01, and Section M.02.03). All topsoil within the project limits shall be excavated to a depth of 9” and stockpiled separately for reuse. Surplus materials shall be stockpiled on-site in the spoils areas specified on the plans. All excavated materials shall remain on-site. Our calculations show that the stockpiled topsoil (stripped to a 9” depth) will provide sufficient topsoil required for the project when placed to a 4” depth. 8/22/2018

Please reference RFI#001 response. Please confirm contractors can assume the strip and reuse of the existing top 9” of topsoil on the project site and that no new topsoil will be required.

Excavated topsoil (9” depth) will be reused and applied at a depth of 4”. Surplus topsoil shall be place in the designated areas. There is no additional payment for additional topsoil imported from offsite.

8/22/2018

Drawing CU102 shows new drainage structures going through existing gravel paved areas. Can contractors assume that the areas of gravel drive that are being affected can be stripped and reused on site? Gravel drive detail on CD101 calls for gravel paving to be 20” thick. Please confirm that the existing gravel drive are 20” thick and that the reuse of existing materials is acceptable.

Materials excavated for trenches for the drainage structures and pipes shall be handled so that gravel pavement and subbase materials are stockpiled individually and separately from excavated subsoils to avoid intermixing. Existing gravel and subbase materials shall be reused if they can be processed to conform to the material specifications. Existing material depths are unknown. Any excess materials may be reused onsite as suitable.

8/22/2018

Drawing CD102 shows a detail for underground electric and telephone ductbank. This detail calls for electrical and phone lines to be encased in concrete where as other drawings call for these lines to be encased in sand. Do all underground conduits need to be encased in concrete per this detail?

Only conduits located under paved areas need to be concrete encased. All others shall be sand encased.

8/22/2018

The site electrical plan on ES101 doesn’t appear to coincide with the CU drawings. The E drawing shows new lighting controls extending all the way up Super Sabre rd where as the CU drawings has conduits stopping at the intersection. Please clarify.

Lighting Plan ES101 is correct. Plans CU101 to CU103 have been revised accordingly.

8/22/2018

ANSWERED