SOLICITATION NO: W91ZRS-18-R-0002 (PROJECT NUMBER: CEKT139029) CONSTRUCT BASE ENTRY COMPLEX, BRADLEY AIR NATIONAL GUARD BASE, EAST GRANBY, CT
RFIS ANSWERS DATE ANSWERED
There was discussion at the pre-bid meeting regarding requirements of the General Contractor for the management and re-use of the top 9 inches of existing topsoil. The contract documents do not address this requirement. Please provide stockpile areas and management requirements.
Due to historic presence of contaminated soils on Base, no excavated soils are to be removed from Base Property (the job site area). Any excavated soils are to be stockpiled on site. Stockpiled soils, where not required to be covered with topsoil and seeded for erosion control or other "best practices" reasons, are to be left exposed (not covered) per CT DEEP recommendations. Beyond this, there are no specific contaminated soils remediation measures associated with this project. 8/8/2018
Reference Utility Company TX Pad site. Are bollards required at the TX pad location? In an on-site meeting with EVERSOURCE, the EVERSOURCE technician indicated that he would like to see three 8-inch diameter bollards (Utility Protection Bollards) provided around the transformer pad. We also recommend additional Utility Protection Bollards around the proposed lift gate operator and sensor mounting equipment. We have modified Drawing CU101 to reflect these changes.
8/8/2018
Reference "Force Protection Bollard Detail" on CD104. Please locate these bollard types. The (5) bollards identified as "K-8 Rated Force Protection" bollards on Sheet CD104 will be changed to read "Utility Protection Bollard Detail." Locations for use of these bollards are depicted on Sheet CL101.
Note: There are now (4) Types of Bollards:
(10) 6" Removable Bollards (See CD103);
(12) Security Bollards w Covers (7-11/LS504);
(5) Pipe Bollards w Covers (Details 4-6/LS504);
(3) 8" Utility Protection Bollards (See CD104);
Note: Security bollards have the same covers as the pipe bollards. Reference on the drawings for the covers for the security bollards refers to details 8 & 9 but should refer to details 4-6. We will revise Detail 9, Sheet LS504 to "Refer to Details 4-6/LS504." Detail 8, Sheet LS504 shall refer to details 9-11, not just 9 and 11.
8/8/2018
Areas of OLI # 1 and # 3 decorative concrete paving, the thickness and reinforcing of the concrete is not detailed for the vehicular concrete or the island cap concrete. Please provide details.
We have provided an additional section for the concrete in the drive lane (8-inches of Portland cement concrete over 8 inches of processed aggregate, called Concrete Pavement Section) and concrete cap in the curbed islands (5 inches of Portland cement concrete over 6 inches of processed aggregate base course called Curbed Island & Median Detail Sections). These sections have been added to the plan set via addition of Sheet CD105. The decorative concrete paving will consist of a stamped pattern color-enhanced Portland cement concrete. The specific pattern and color is stated in a specification excerpt attached to this document - namely (and among others) "Color: Basis of design is Bomacron Steadman Buff" (or approved equal) and "Imprinting Tools: Basis of design is Bomacron Herringbone Used Brick" (or approved equal). There will be the same thickness & reinforcing for both pavement types.
8/8/2018
Spec Section 321313, 1.1, E notes "Concrete paver units in vehicular areas." Please locate and provide a specification.
There are no Concrete Paver Units in this job. References will be stricken from the specifications.
8/8/2018
Spec Section 012300, OLI-#3 states to furnish and install decorative paving in lieu of broom finish. Please confirm that the base bid is concrete paving in the same areas with broom finish and provide details for tooling and/or control joints.
The base bid is broom-finish concrete in the same areas. Tooling and control joints shall be per CT DOT Form 817. In general, contraction joints shall be provided no more than 20-feet on center, with tooled joints, on average every 5 feet. Tooling and joint pattern should be proportional and laid out in an aesthetic manner. Pattern to be approved by the A/E. 8/8/2018
Are the three areas within the concrete CIP curbs and the exterior of the building concrete paving? If so, provide details, reinforcing, mix, etc.
Yes. The three areas are treated with a Portland Cement concrete finish. The section calls for a 5-inch thick concrete slab over 6 inches of compacted process aggregate base. (See Sheet CD105). We are generating new sections to depict the slab and curb. We are also adjusting the grading slightly in the area around the Gate House and adding additional spot grades for top and bottom of curb to better show the construction detail of this area, and grading transitions to provide ADA access to the building and adjacent walks. (See Sheet CG101). 8/8/2018
Where bituminous paving cuts are made for water and sewer connections and the curb cut on Rte 20, please provide the associated paving details.
All work within the state highway ROW shall be conducted following the requirements of the CT DOT.
The trench repair section for work in the DOT ROW is depicted on Sheet CD105. 8/8/2018
9 Where CIP curbing is called out on the drawings, can pre-cast curbing be substituted?
No. All Portland cement concrete curb and integral concrete curb and sidewalk shall be cast-in-place concrete. Pre-cast is not allowed. 8/8/2018
Confirm that ALL bituminous pavement in the area surrounding the Guard building is "Heavy Duty".
All pavement on the project is heavy-duty pavement, with the exception of the passenger parking areas depicted on Sheet CL101 (see shaded areas). All bituminous pavement in the area surrounding the gate house is heavy-duty bituminous pavement. 8/8/2018
11 "Pavement Section (light duty)". Please locate where this detail is used? See Sheet CL101, shaded areas.
8/8/2018
Beginning at the intersection of Thunderjet and Super Saber Roads, what pavement section is to be used? Since the existing road is being widened, provide details of demolition / milling / reuse of millings / new pavement details.
All pavement on the project is heavy-duty pavement, with the exception of the passenger parking areas depicted on Sheet CL101 (see shaded areas). Use the heavy-duty pavement section for all roadways and drives with the exception of the passenger parking areas depicted on Sheet CL101 (see shaded areas). The heavy-duty pavement section is shown on Sheet CD101. All pavement sections for the heavy-duty pavement, must conform to the section shown. Should the contractor elect to reclaim and re-use the existing subbase, base course and/or bituminous materials, that would be acceptable, and even encouraged. The re-claimed materials however will need to conform with the materials specifications noted on the detail (i.e., CT D.O.T. Form 817, Section M.05.01, and Section M.02.03).
8/8/2018 13 "Continuous spray in place insulation". Provide a thickness. 6 inches. 8/8/2018 14 Confirm that the elevated slab is 4000 psi normal weight concrete. Yes. Elevated slab is 4000 psi (at 28 days) normal weight concrete
8/8/2018
Confirm that both the wall and sofftt panels are 4 inches thick and 30 inched wide. Plans appear to indicate different widths and thicknesses.
Yes. The panels are 4 inches thick as shown, and a maximum of 30 inches wide. Some portions of the canopy and building will require less than 30 inches wide. 8/8/2018
Lift Gate Detail. Please provide a basis of design. Provide DKS DOORKING Model 1601 (Basis of Design) or approved equal. See attached product data to further clarify scope & pricing. 8/8/2018 17 ...indicates "concrete island (typical of 4)". Please provide details of concrete cap. See response to Item No. 4 above. 8/8/2018
Drawing LS401, detail 4 conflicts with 3/CL102 and adds decorative paving plus an inner curb and turf? Please provide details for 4/LS401.
Detail 4/LS401 states that the decorative concrete is an Optional Line Item. The detail lays out the shape of the paving if the option is taken. Paving sections are no different for decorative concrete than regular concrete. Refer to the civil details for paving sections. 8/8/2018
Drawing CG102, detail2, appears to be two Communication manholes within the decorative concrete paving. Please clarify the work needed to accomplish this task.
The manhole frames and covers shall be constructed to match the proposed finish grade of the decorative concrete surface. This will require matching the proposed cross-slope of the island at the proposed finish grade to provide a smooth, continuous grade across the decorative concrete.
Placement of the concrete around the manhole cover shall be done with the placement of the entire surrounding slab to form a uniform look. Separate pours around the frame (i.e., to create a concrete apron) is not allowed. 8/8/2018
Drawings CE101 through CE103, note 9 indicates "a construction sequence and phasing as outlined on these plans". Information not found on the plans. Please provide.
A general sequence of construction will be added to the plans (Sheet CE101 -CE103). Detailed construction phasing plans shall be created by the Contractor and become part of the site-specific Stormwater Pollution Prevention Plan. 8/8/2018
Drawing S-001, Soil and Foundation notes: Note 1, references a "soil study prepared by Welti Geotechnical". Please provide study.
The soils and geotechnical report was not included in the specifications as it may contain information for design which may not be applicable to these contract documents. Please see the attached file for boring location plans and logs which may be helpful. 8/8/2018
Drawing S-001, Steel Construction Notes. Please confirm that all structural steel must be fabricated and erected by an AISC certified fabricator and erector.
AISC certification is not required of the fabricator or erector for this contract. The selected fabricator and erector are required to follow the quoted AISC procedures and tolerances. 8/8/2018
Reference specification 090690, Color Schedule. Color schedule indicates masonry materials shall match the New Small Air Terminal Building. Should the Roofing, Windows, Louvers, Metal siding and Metal soffits match the same building?
Follow specification 090690, Color Schedule, for roofing, window frame, louvers, metal siding, and metal soffits. For window glazing, see Section 085653. Glazing samples will need to be submitted to verify security visibility. Color should be similar to PPG Industries Solargray, and material must be bullet resistive level V. 8/8/2018
Reference "IBC 205 Structural Tests and Inspections". Section lists all special inspections for the project but does not include testing of bituminous pavements? Please clarify.
The “IBC 2015 Structural Tests and Inspections” is a list of items for the “special inspector” to verify.
Special Inspections are typically limited to building elements and are in addition to the normally required quality control and quality assurance inspections required elsewhere in the specifications. For testing of bituminous pavements please refer to the bituminous concrete paving & curb specification (specification section 321200). 8/8/2018
On drawing AE101 “Sheet Keynotes” Item # 7. Coat Hook & Hat Rack. This item is not identified in the specs. All other items are, please advise.
Provide fixture. Basis of Design Product: Bobrick D-6827; Finish: Satin Stainless Steel; Mounting:
Concealed fasteners. 8/8/2018
Please advise who the alarm/security panel company is for this base. We are interpreting this question to refer to the (on or off base) parties that will receive fire and security alarming from said panel. Said alarming will be received by Bradley ANG Base Fire and (BDOC) Security Forces. 8/8/2018
27 Is a SWPP required by the contractor? The Base is registering for the Stormwater GP and is generating the SWPPP. 8/8/2018
Reference project specifications. There are no specifications provided for the Main Gate sign indicated on drawing LS501. Please provide.
The design of the New Base Entry Sign (outside of sign base and general format detailing shown on Sheet LS501 and as noted in Installation Sign Detail 1, Sheet LS501) is to be "by Sign Manufacturer" (Designated Design). Bidding Contractors are to consult a sign manufacturer for conceptual detailing and pricing for bids. Designs to function with base detailing shown on Sheet LS501 and are to strictly adhere to guidelines outlined in UFC 3-120-01 - DESIGN: SIGN STANDARDS, dated 1 March 2014, Changed 2, 7 October 2014, paragraphs 3-1.5, 3-2.2 and 3-2.4 (among others). Conceptual signage detailing used for bidding purposes shall be carried over by the successful bidder to a schedule of values during construction. 8/8/2018
Reference project specifications. There are no specifications provided for Division 21, Fire Protection, however the bid form contains a line item for Division 21, Fire Protection.
Division 21 specifications are not required. A sprinkler system is not required for this building. See Amendment 0001 for revised BID SCHEDULE. 8/8/2018
Reference the Bid Form. Bid form contain Division 01 through 33. Specifications contain Division 2, Site Clearing/Utility Drainage Line removal. Where should Division 2 costs be included on the bid form?
See Amendment 0001 for revised BID SCHEDULE.
8/8/2018
Reference the Bid Form. Bid form contain Division 01 through 33. Specifications contain Division 34, Crash Bollards. Where should Division 34 costs be included on the bid form?
See Amendment 0001 for revised BID SCHEDULE.
8/8/2018
Due to the geographic acreage of this project, will a Storm Water Pollution Prevention Plan be required?
If yes, will it be filed with the State of CT?
If yes, and there are fees associated with it, who is responsible for the fees?
Yes. A SWPPP will be required. The Base is registering for the Stormwater GP and is generating the
SWPPP.
8/8/2018
Has an FFA permit been filed with the CT Airport Authority for this project? Assuming you meant FAA permit then Yes. Several FAA 7460s have been submitted and approved by the FAA for this project. The most stringent (tallest items) were a part of this submittal. Several additional items are being submitted at this time to address the remainder of the site.
8/8/2018
Reference drawing CU 101. Drawing note indicates "O.F.C.I. generator (22 kva generator OLI#4)". Reference drawing ES101. Drawing note indicates "30KVA generator".
Spec section O12300-2,D1 states "new unit shall meet all requirements to support the ECF energy requirements".
Question 1, does OFCI mean Owner furnished contractor installed?
Question 2, is the generator 22 or 30 kva?
Question 3, what are the requirements of the ECF?
Question 4, what fuel type is the generator?
Question 5, if the fuel type is diesel, what is the required run time on a single tank?
Question 6, if the fuel type is gas, the plans do not show any gas service on the project?
Please provide a specification for the generator.
Please clarify the base bid versus the OLI # 4 scope of work
1. Yes. OFCI does mean Owner Furnish / Contractor Install.
2. The existing generator is a 25 kVA generator. The minimum required size generator (if OLI #4 is taken) is 30 kVA.
3. See EP701 single line diagram identifying the ECF systems to be supported on emergency power by this generator. 4. The existing generator is diesel powered.
5. 24 hours.
6. Generator is not NG powered.
7. All provisions for emergency power and generator connection shall be provided in base bid. The only item *not* in the base bid will be the generator itself. Wire, raceway, pad, etc. are all part of base bid.
8/8/2018
Reference Drawing LS40 I, There are multiple notes regarding "decorative concrete paving".
Reference Spec section 321313-2, 2.1-H, Indicates tinting of stamped concrete.
Please confirm herringbone brick pattern shown will be the stamping pattern that will be used.
Please confirm what color tinting will be used.
1. Herringbone Brick Pattern shall be the stamped pattern (OLI#3 Only). The Base Bid is Broom Finish Concrete. 2.
Color Tinting will be used (OLI #3 Only). Base Bid will have no color tinting. See attached Specification excerpt addressing the Colored & Patterned / Texture Concrete Finish.
8/8/2018
Reference specification 071326. Section indicates a 60 mil, self adhering modified bitumen sheet waterproofing.
Throughout the A drawings there are numerous notes indicating differing descriptions of the exterior wall waterproofing such as:
a. Waterproofing membrane
b. Fluid applied waterproof membrane
c. Cont air barrier Please clarify the type of waterproofing system to be used on the exterior side of the CMU back up wall.
Use specification section 072726 Fluid-Applied Membrane Air Barriers for waterproofing system to be used on the exterior side of the CMU back up wall. “Cont air barrier” is a notation for federal guidelines.
Section 071326 is not required for this project.
8/8/2018
The project specifications mention a geotechnical report by Clarence Welti Associates, Inc.
which should have that data, but I’m not sure where to find it. Would you happen to know where I could locate the geotechnical report?
The soils and geotechnical report was not included in the specifications as it may contain information for design which may not be applicable to these contract documents. Please see the attached file for boring location plans and logs which may be helpful. 8/8/2018
Reference Drawing CL10I. Entrance island containing entrance sign and flagpoles indicates the following language "Landscape Island".
Reference LS401. The same island is indicated as "Decorative Concrete paving as OLI-3.
Question #1, Is the base bid finish Landscaping or Broom finish concrete?
Question# 2, If the base bid finish is landscaping please provide a landscape plan.
1. Base Bid Finish is Broom Finish Concrete.
2. The Landscape components of this Island, (primarily on the plan-south end) which are all Base Bid Items, are shown in 1/LS101, 1/LS102, 1&2/LS401, 2/LP401 & LP501.
8/8/2018
Please clarify: Drawing ES-101 calls for a lighting control relay panel to be provided in a weather proof enclosure, This panel is not listed in the panel schedule or listed in the keynotes.
The exterior lighting circuits shall be controlled via photocell and timeclock combination. A multi-pole contactor or relay panel shall be the vehicle for circuit control. The equipment may be installed in a NEMA 3R enclosure and mounted on a unistrut frame where shown, or it may be installed within/above the guard building’s electrical room. 8/8/2018
Specification 312300, paragrapgh 1.3 references a Geotechnical Report by Dr, Clarence Welti.
The project documents did not include a geotech report.
The soils and geotechnical report was not included in the specifications as it may contain information for design which may not be applicable to these contract. See the attached file for boring location plans and logs which may be helpful. 8/8/2018
Drawing EP-701 shows us providing utility and base metering. Please describe the product requirments for this.
Please refer to attached pdf detailing EVERSOURCE Energy’s requirements.
8/8/2018
Drawings EP101 (7 - 4" Conduits) and ES-104 Key Note 4 show us providning conduits. Are the conduits empty or do they require a pull string?
The conduits will require a pull string.
8/8/2018
Drawing ES101 shows a 30KVA Generator. Specification 263600 describes the transfer switch requirements. There is no generator specification inlcuded in the documents. Is the generator part of our bid scope? Is the Generator GFCI or GFGI? Is this an existing generator?
Please see response to Item No. 34, part 7 above. A generator specification will be provided.
8/8/2018
The solicitation is requesting LEED qualifications be submitted with the proposal, however the Project specifications do not include a section on sustainable design requirements, LEED scorecard, or any other information indicating that this is a LEED project. Please clarify the LEED requirements of for this project.
See Amendment 0001 for revised Sections 00110 and 00120.
8/8/2018
Can another site visit be scheduled?
No. Only one Site Visit will be executed for this project.
8/8/2018
Considering the large amount of unanswered RFI's will the bid date be extended. Per Amendment 0001, proposal due date is now 29 August 2018 by 2 p.m.
8/20/2018
Subfactor 3 – Quality Control
2.5.2.5. Subfactor 3: Quality Control. The proposal narrative demonstrates that the quality control staff, with lines of authority, is adequate to meet the contract’s requirements. The proposed Quality Control answers should provide a detailed explanation of how quality issues are dealt with on various types of construction projects and as a minimum, meetings, inspections, submittal reviews, correction of non-compliant work and how you intend to ensure non-reoccurrence and reporting of quality problems to Government officials. (Note: A Quality Control Plan is not required with this proposal).
2.2.6. Subfactor 3 - Quality Control: The proposal narrative demonstrates that the quality control staff, with lines of authority, is acceptable to meet the contract’s requirements. Proposal demonstrates acceptable quality control processes to give the government confidence of the offeror’s ability to successfully manage the material submittal process, and ensure subcontractor compliance with contract documents. The proposed Quality Controlanswers should provide a detailed explanation of how quality issues are dealt with on various types of construction projects and as a minimum, meetings, inspections, submittal reviews, correction of non-compliant work and how you intend to ensure non-reoccurrence and reporting of quality problems to Government officials.
(Note: A Quality Control Plan is not required with this proposal).
As this is primarily a horizontal construction project and there is a specific schedule of tests to be conducted we are not sure how the described Subfactor 3 pertains to this solicitation, nor do we find any specific requirements for an On-site Quality Control Manager.
Almost all Quality Control is called out to be by independent testing companies
Submit a proposal in accordance with Sections 00110 and 00120 of the solicitation.
Subfactor 4 – LEED® (limit resumes to 2 pages each)
2.5.2.6. Subfactor 4: LEED®. Discuss company experience with building to United States Green Building Council (USGBC) LEED® standards. Indicate any previous projects that achieved USGBC LEED® certification, any level of recognition. Additionally, indicate the key construction personnel and demonstrate they have experience and required qualifications in assigned roles with building to USGBC LEED® standards. If no experience so state and indicate in detail how you plan to overcome this lack of experience. The onus is solely on the offeror to indicate in detail how the offeror plans to overcome this lack of experience. (Resumes or experience cut sheets are limited to 2 pages each and are not part of the page count.) In the event the intended person is not part of the offeror’s organization at the time the proposal is submitted then a completed Exhibit B, “Subcontractor/Team/Key Personnel Information and Consent Form” is also required or the information will not be considered. This subfactor is limited to ten (10) pages excluding the table of contents, dividers, tabs, indexes, experience cut-sheets and resumes.
2.2.7. Subfactor 4 - Experience with building to United States Green Building Council (USGBC) LEED® standards:
An acceptable proposal demonstrates experience with building to United States Green Building Council (USGBC) LEED® standards. The Government will evaluate the number and magnitude of previous projects that achieved USGBC LEED® certification, or any level of recognition. Experienced key construction personnel are identified with required qualifications in assigned roles with building to USGBC LEED® standards. If no experience is indicated, the Government will evaluate the offeror’s proposed approach for overcoming the lack of experience. For any intended personnel who are not part of the contractor’s organization at the time of proposal submission, the Government will verify submission and proper completion of Exhibit B, “Subcontractor Information and Consent Form”.
We don’t find any reference in the project specifications for LEED requirements
See Amendment 0001 for revised Sections 00110 and 00120.
8/20/2018
Under Amendment 03, CG102 was issued twice. Should one of these files have been CE102?
Please advise.
Drawing CE102-2018-08-03 now posted to solicitation package on FBO.gov.
8/20/2018
It appears there should have been a drawing CE 102-2018-08-03 in the update, but 2 copies of CG 102-2018-08-03 are listed and download the same.
Could you clarify whether or not CE 102 should have been include?
Drawing CE102-2018-08-03 now posted to solicitation package on FBO.gov.