Questions and Answers

1. What is the name of the current contractor?

Answer: There isn’t one at the moment.

2. What is your anticipated award date for this contract?

Answer: The same day it closes or the following day. The start date is one October.

3. What would be the anticipated start date?

Answer: The start date would be 1 October but if some sort of transition is needed it would be fine just need to start setting up by 1 October.

4. Have funds been appropriated for this opportunity?

Answer: This is a Subject to Availability of Funds (SAF). Which means the new fiscal year starts on 1 October so as soon as the Presidential / DoD budget is signed funding will be added to the contract. This is common throughout the Federal Government this time of year.

5. What is the current total annual contract price for this contract?

Answer: Don’t know as we don’t have a contract in place at the moment. Once you/vendors submit proposals we’ll have an idea or a range of what vendors in the industry will charge for this service. From there we’ll assess whether or not the price is realistic and or fair and reasonable. We’ll be looking for technically capable or acceptable proposals and best price.

6. The PWS attachment 8 for a copy of the questionnaire with instructions for completion was not attached to the notice on FBO.

Answer: It’s on Pg. 37-41 of the Solicitation. Will attach it now.