This document contains technical questions and answers related to a solicitation for the lease of a mobile MRI unit by the Department of the Army Materiel Command Contracting Command Redstone Arsenal. Key details include that the solicitation seeks a mobile MRI unit in an 8.5' x 48' trailer to be located at Naval Hospital Guantanamo Bay for a minimum of one year. The document provides contact information for transportation services to deliver the unit from Jacksonville, FL to GTMO as the government will not provide transportation assets. It also answers questions regarding insurance, training needs, helium delivery, moving requirements, testing responsibilities, emergency repairs, potential second location needs, and staffing responsibilities.

View the file

Other files

File Type Posted
PWS_GTMO MRI Capital Lease_25SEP23_Final.docx DOCX document
Exhibit A_Corporate Experience Data Sheet.docx DOCX document
W91WRZ24Q0001_GTMO MRI Lease.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

QuestionTechnical Response
1Can the NAVHOSP GTMO handle a Siemens Aera MRI enclosed in a 12’X70’
transportable building on their existing concrete pad? Some Mobile MRIs are in 8.5’X48’ trailers. Since this MRI will be on-site for a minimum of one year, this 12’X70’ transportable building offers much more internal space for personnel and needed emergency equipment.The MRI is required to be a trailer, 8.5'x48', for mobility.
2Can you provide contact information to setup a barge/transport ship
contract to transport the Mobile MRI from Jacksonville, FL to GTMO?PWS: "The government will NOT provide transportation assets to assist in the delivery from CONUS to NSGB. The barge the government typically uses to transport equipment from Jacksonville, FL to NSGB cannot be used to transport the MRI Machine." RQConstruction.com 1620 Faraday Avenue, Carlsbad, CA 92008, Phone: 760-631-7707 Imcconstructiongroup.com 3070 Blanding Blvd. Middleburg, FL 32068 Phone:(904) 406-6100 Schuylerline.com 130 Severn Ave #201 Annapolis, MD 21403, Phone: 732-904-3882
3Can you provide contact information to secure property insurance to
cover the barge/transport ship transportation of the Mobile MRI?RQConstruction.com 1620 Faraday Avenue, Carlsbad, CA 92008, Phone: 760-631-7707 Imcconstructiongroup.com 3070 Blanding Blvd. Middleburg, FL 32068 Phone:(904) 406-6100 Schuylerline.com 130 Severn Ave #201 Annapolis, MD 21403, Phone: 732-904-3882
4Will NAVHOSP GTMO MRI technologists operate the MRI or must we
supply MRI technologists that will live on GTMO for the duration of the contract?YES, we will NOT require MRI technologists to live in GTMO.
5If NAVHOSP GTMO MRI technologists will operate the Mobile MRI, how
many days of applications training will they requirePlease submit option CLIN for application training.
6Can you provide how we can achieve having Dewars of Helium delivered to NAVHOSP GTMO to be installed when Preventive Maintenance is performed?RQConstruction.com 1620 Faraday Avenue, Carlsbad, CA 92008, Phone: 760-631-7707 Imcconstructiongroup.com 3070 Blanding Blvd. Middleburg, FL 32068 Phone:(904) 406-6100 Schuylerline.com 130 Severn Ave #201 Annapolis, MD 21403, Phone: 732-904-3882
7If the Mobile MRI must be moved to a different location during the term
of the agreement, is there an available tractor on GTMO to move the Mobile MRI?YES
8Do we need to supply a driver to move the Mobile MRI if it must be
moved or can GTMO drivers move the MRI?NO, GTMO drivers will move the MRI however "It is the contractor’s responsibility to inform the Government exactly what equipment is necessary to move the MRI and what technical specifications/ space requirements are needed."
9Who pays for the Diagnostic Medical Physicist to perform the required tests and evaluations?MRI validation by the Diagnostic Medical Physicist will be completed internally by DoD. However, the third party machine technician program initationa and confirmation must be provided by the MRI machine prime contractor.
101. 1.6.13 Contractor Travel, states we need to get 30 days prior approval from the COR for service. What if there is an emergency repairs that need to be made to the MRI so to avoid damage to the machine, is there a contingency plan with that?Yes there is a emergency contingency plan for urgent requests.
115.1.5 mentions that the Mobile MRI will use 2 separate locations during the period of the lease. Will there be a cost line item for the move to the second location, do you know when the move will occur?The potential for two locations is meant as a contingency in case we need to move the MRI trailer in case of construction nearby the existing unit. We do not know when the move will occur. GTMO drivers will move the MRI using our own trucks and equipment. However "It is the contractor’s responsibility to inform the Government exactly what equipment is necessary to move the MRI and what technical specifications/ space requirements are needed."
12Is the contractor expected to provide staff or will you provide your own staff to operate the MRI?No, Yes we will provide our own MRI imaging techincian staff when required.
13Is there a mobile MRI on site now, if so what type of system is it?Yes, Philips 1.5T Achieva
14Can you provide the suggested method of getting the Mobile MRI on the base for the U.S.?RQConstruction.com 1620 Faraday Avenue, Carlsbad, CA 92008, Phone: 760-631-7707 Imcconstructiongroup.com 3070 Blanding Blvd. Middleburg, FL 32068 Phone:(904) 406-6100 Schuylerline.com 130 Severn Ave #201 Annapolis, MD 21403, Phone: 732-904-3882
15Would you be interested in a GE MRI system?No preference as long as it meets PWS standards.