QUESTIONS & ANSWERS W91WFU-16-T-0017 DATED 23AUG2016:

Answers to contractor questions are as follows:

Q 1. In the PWS 1.6.10 Key Personnel Section it states, “The contractor shall provide a Project/Contract Manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the contractor when the manager is absent shall be designated in writing to the contracting officer.” Do we submit only the name in writing to the Contracting Officer as part of the proposal submission or is this a post award requirement

A 1: SUBMIT AS PART OF PROPOSAL. THIS INFORMATION MAY ALSO BE

REQUESTED POSTAWARD TO ENSURE THE INDIVIDUAL(S) ASSIGNED TO THE

PROJECT HAS THE REQUISITE QUALIFICATIONS LISTED IN THE PERFORMANCE

WORK STATEMENT.

Q 2. Would the Government permit the winning Bidder to use local national skilled workers in order to provide the Government the benefit of lower price resulting from lower local labor rates and lower travel expenses? As required, the Offeror would provide SECRET-cleared escorts IAW to DoD regulations, in order to ensure all members of the installation team understand and comply with security regulations.

A 2. NO – CONTRACTOR PERSONNEL MUST POSSESS THE SECURITY CLEARANCE

REQUIREMENTS LISTED IN THE PWS UNDER 1.6.7.2.

Q 3. Will monitor arms and CPU holders be installed by furniture vendor?

A 3. YES/CONFIRMED.

Q 4. What is the preferred method to run patch cords?

A 4. THIS WILL BE DECIDED ON-SITE WITH THE ON-SITE GOVERNMENT

REPRESENTATIVE (OSGR).

A 5. Have the work area outlet counts in each office been confirmed?

Q 5. YES/CONFIRMED

Q 6. Who will do the AV Programming?

A 6. AV PROGRAMMING WILL BE PERFORMED BY SPAWAR

Q 7. Does this project involve TS/SCI?

A 7. NO (THIS IS DEPICTED IN THE IDP).

Q 8. How should the computers be mounted on desk with 3 computers?

A 8. COMPUTERS WITH SECRET CLASSIFICATION SHOULD BE MOUNTED IN THE

SAME BRACKET AS OUTLINED IN THE DESIGN PACKAGE.