Amendment 01 - Solicitation Questions and Answers JPMRC 26-01 Maui Crane and Stevedore.pdf
PDF 107 KB Posted
- Solicitation number
- W91QVP-26-Q-5008
About this file
This document is a Questions and Answers (Q&A) file for solicitation W91QVP-26-Q-5008, a U.S. Army logistics contract for crane and stevedore services at Kahului Harbor in Hawaii. The primary scope involves a Lift On/Lift Off (LOLO) operation to unload and reload 18 pieces of military equipment/vehicles from a Logistics Support Vessel (LSV) operated by the 8th Transportation Support Command (TSC). Key requirements include the contractor being responsible for finding a shoreside crane vendor, safely lifting units with crane pick points, and delivering cargo to a staging area. All units are operable, with no special handling requirements, and will be staged on November 16th.
Vendors must submit quotes no later than 12:00 PM Hawaii Standard Time on October 22, 2025, referencing the Unit Deployment List (UDL) spreadsheet for vehicle/equipment quantities, dimensions, and weights. The contract will be awarded to a prime contractor who will manage subcontractors, and any changes in unit quantities after award will be managed through contract modifications. The operation involves a direct ship-to-pier process at Kahului Harbor, with specific grid coordinates provided in the Request for Quote (RFQ). Supporting documentation includes a Unit Deployment List (Attachment 1) and an LSV Load Plan Diagram (Attachment 2) to provide detailed information about the equipment and loading sequence.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 1 - JPMRC Load Plan.png | PNG image | |
| Attachment 2 - 25TH CAB JPMRC UDL AS OF 20OCT25.xls | XLS spreadsheet | |
| A02 PWS Maui Crane and Stevedore v4.pdf | ||
| B08 Pricing Sheet- 26-Q-5008 JPMRC 26-01 Kahului Harbor Maui v2.xlsx | XLSX spreadsheet | |
| B08 Pricing Sheet- 26-Q-5008 JPMRC 26-01 Kahului Harbor Maui.xlsx | XLSX spreadsheet | |
| A02 PWS MAUI Crane v3.docx | DOCX document | |
| B08 RFQ 25-Q-5008 JPMRC 2026 SVC Maui Crane.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W91QVP-26-Q-5008 – Maui Crane and Stevedore Question and Answers
1. Question: To verify, the scope of work is to offload (10) pieces of equipment from the boat onto the land at Kahului Harbor?
Answer: There are 18 pieces of equipment/vehicles that will need to be unloaded and loaded at Kahului Harbor. (Refer to Attachment 1 – Unit Deployment List). Posting updated to reflect current unit quantities.
2. Question: Do you know the weights of the equipment being lifted?
Answer: Refer to Attachment 1 - Unit Deployment List for vehicle/equipment weights.
3. Question: Location of vehicles on deck of ship.
Answer: Refer to Attachment 2 – LSV Load Plan Diagram
4. Question: Number of vehicles being unloaded?
Answer: Refer to Attachment 1 - Unit Deployment List
5. Question: Height of deck where vehicles are stored above sea level.
Answer: Refer to Attachment 2 – LSV Load Plan Diagram
6. Question: As much information as possible of rigging points of vehicles.
Answer: Please refer to all supporting documents contained in RFQ.
7. Question: Will this operation be Roll On/Roll Off (RORO) or Lift On/Lift Off
(LOLO)?
Answer: Lift On/Lift Off
8. Question: If operation is LOLO will offeror be responsible for finding a shoreside crane vendor?
Answer: Yes
9. Question: If operation is LOLO, do all units have pick points to safely lift with a crane?
10. Question: How many units will be discharged and loaded back?
Answer: Please refer to Attachment 1 – Unit Deployment List for list of all equipment and vehicles that need to be unloaded and loaded.
11. Question: Is there a detailed cargo list with the dimensions and weight of each unit?
Answer: Please refer to Attachment 1 – Unit Deployment List for dimensions and weight of each unit.
12. Question: Is there a stow plan available?
Answer: Refer to Attachment 2 – LSV Load Plan Diagram
13. Question: Are units operable?
14. Question: Will any machines be needed to move inoperable units if any?
Answer: Wrecker on UDL
15. Question: Are there any special handling requirements for any of the cargo?
Answer: No.
16. Question: Will units be delivered off the pier the same day as discharge?
Answer: Cargo will download then be driven by provided personnel to staging area.
17. Question: Will units be received and stored on the pier prior to loading back?
Answer: Units will be staged on November 16th.
18. Question: If unit count changes after quote is submitted, how will that be accounted for?
Answer: Please submit quotes NLT 1200PM Hawaii Standard Time 22 October 2025. Refer to the Unit Deployment List (UDL) Spreadsheet for vehicle/equipment quantities, dimensions, and weight. Any changes in quantity after award will be added/removed to the contract via modification.
19. Question: Does this operation fall under military contract with Hawaii Stevedores Inc?
Answer: This contract has not been awarded.
20. Question: Please confirm which specific pier(s) at Kahului Harbor will be used for the LSV operations?
Answer: Please refer to grid coordinates located on RFQ.
21. Question: Should the crane contractor furnish the stevedore crew as part of CLIN 0001 and 0002, or will stevedoring support be provided separately by the Government?
Answer: The contract is awarded to the prime contractor and will only deal with the prime contractor. Subcontractors work for the prime contractor, not for the government.
22. Question: If contractor-provided, does the Government have a list of cleared or previously approved stevedore companies that have supported JPMRC or similar Army vessel operations in Hawaii?
Answer: No.
23. Question: Please confirm that the vessel is a U.S. Army LSV conducting direct ship-to-pier operations (not offshore lightering).
Answer: This is correct. We have an LSV with 8th TSC that’s conducting this mission.
24. Question: If available, could you provide any stow plan or representative load/offload sequence to support safe and efficient lift planning?
Answer: Refer to Attachment 2 – LSV Load Plan Diagram
25. Question: Will the contractor be responsible for obtaining this permit directly, or will the Government assist or coordinate with the Harbors Division to expedite approval given the short timeline between award and performance?
Answer: Please refer to PWS section 5.2.3