This is a Questions and Answers document for solicitation W91QVP-26-AS27-BLS, addressing clarifications on Base Life Support and Facility Rehabilitation Services at the Multinational Peacekeeping Force (PKO) Training Center in Kampong Speu Province, Cambodia. The primary place of performance is the PKO Training Center, with additional support locations at Techno/Techo International Airport in Phnom Penh, Hyatt Regency Hotel, and Phum Serey Hotel/Resort. The document clarifies that contractors may disclose Performance Work Statement and Combined Synopsis information to prospective subcontractors for preliminary quotations without sharing the full RFQ itself.
Key technical clarifications address specific CLINs: CLIN 0004 requires an Automatic Transfer Switch (ATS) for generator operation with seamless unmanned switchover—a 24/7 human operator is not considered equivalent; CLIN 0007 permits existing fixed handwash sinks as alternatives to portable stations if they meet capacity and sanitary standards, but contractors must still provide 14 chemical-latrine and 14 handwash station capacity; and CLIN 0009 accepts pricing structures with base costs for non-inverter air-conditioning units plus separate additive pricing for inverter models. The anticipated award date is December 1, 2026, with facility rehabilitation beginning on that same date, though the period of performance will be adjusted if award is delayed. Contractors are welcome to conduct site visits at the PKO Training Center to verify existing transformer ownership, condition, and Electricity of Cambodia application status. Responses were due by November 6, 2026, and proposals were due by November 20, 2026 at 1:00 PM Hawaii Standard Time, submitted to MAJ Pandy and SSG Mbawuike in PDF and Excel formats.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers AS27 Base Life Support/Facility Rehabilitation Services
1. The city, province and specific Government-designated AS27 site location(s) in Cambodia, or the permissible location details for planning delivery and local support. The primary place of performance is the Multinational Peacekeeping Force Training Center (PKO) located at:ភូមិផ្គង់, ផ្លូវលេខ ៤៤, គីឡូម៉ែត្រ ៨, Krong Chbar Mon, Kampong Speu Province, Cambodia. Additional locations specifically identified in the Transportation PWS/RFQ are: Techno / Techo International Airport (Phnom Penh), Hyatt Regency Hotel, Phnom Penh, Phum Serey Hotel / Phum Serey Mongkul Resort, Kampong Speu. All other AS27 requirements (Catering and BLS/Facility Rehabilitation) are performed at or in support of the PKO Training Center in Kampong Speu. Exact delivery/setup points within the PKO will be coordinated by the COR after award.
1. The complete Performance Work Statement (PWS), including any site-specific requirements and schedules. Please see SAM.gov for all documents/information associated with the solicitations.
1. The official Excel pricing sheet referenced in the solicitation. Contractor shall provide excel pricing sheet based on the CLIN structure.
1. Written guidance on whether we may disclose only the minimum technical specifications necessary to prospective Cambodia-based subcontractors for preliminary quotations, without distributing the RFQ itself. You may disclose the PWS/Combined Synopsis and Solicitation information needed to provide estimates with your prospective subcontractor as needed.
We understand the solicitation prohibits sharing the RFQ with other vendors, and will not forward it to prospective suppliers. We appreciate your consideration despite the elapsed questions deadline. You may disclose the PWS/Combined Synopsis and Solicitation information needed to provide estimates with your prospective subcontractor as needed.
Questions and Answers
-CLIN 0004
It says to install ATS “or equal”. Can “equal” be a 24/7 operator for the large generator? No. “Or equal” means a functionally equivalent automatic transfer capability that provides the same seamless, unmanned switchover as an Automatic Transfer Switch (ATS). A 24/7 human operator is not considered equal to an ATS. The Contractor shall provide an ATS (or true automatic equivalent). Separate optional CLINs already exist for continuous 24-hour operation or 0600–2200 daily operation of the generator. Manned operation may be discussed only as an additive service under those options, not as a substitute for the required automatic transfer capability.
-CLIN 0007-
-Our thought is to make existing 14+ handwash sinks operable which will also decrease the number of portable sinks necessary probably to zero and save money. This should be less costly than renting portable sinks and handwash stations. They are already connected to the septic system. Is this an acceptable alternative? The requirement is for fourteen (14) handwash and chemical-latrine units. Making existing fixed handwash sinks fully operable, sanitary, and code-compliant may be proposed as a means to reduce or eliminate portable handwash stations, provided the sinks meet all capacity, hygiene, and connection standards. However, the Contractor must still furnish the required 14 chemical-latrine (toilet) and 14 handwash stations capacity. Any alternative approach must be clearly described in the technical proposal, priced accordingly, and is subject to COR/KO approval before performance. Optional CLINs already exist for alternate wastewater solutions and septic-tank repair if needed.
CLIN 0009-
The quoted cost will be for non-inverter air con units with a sub line for the additional inverter cost. Is this acceptable? Yes. This is the exact pricing structure requested. The PWS requires separate pricing for split-system (non-inverter) and inverter-model air-conditioning units. Quoting a base price for non-inverter units plus a clearly identified additive price for inverter models is fully acceptable and preferred.
Award date and funds. The RFQ includes FAR 52.232-18, Availability of Funds, and the facility rehabilitation period begins 1 December 2026. What is the anticipated award date? If award occurs later than planned, will the Government adjust the facility rehabilitation start date? We are currently planning for the December 01 2026 award date, if changes happen period of performance will be adjusted. Availability of funds still applies.
Existing transformer. The PWS requires the contractor to verify existing-transformer ownership, condition, compatibility and authorization requirements. Is there an existing transformer serving the DFAC and classroom areas, who owns it, and does the Government or the host nation already have an Electricity of Cambodia application or approval on file for the site? This information is required to be verified by the contractor through a site visit at the PKO training center; visitors are welcome to come into the center; they need to let the entrance team that they are coming to conduct a site visit for Angkor Sentinel.
File details come from the government source that posted it. Updated .