B08 Amendment W91QVN24R0139-0001.pdf

PDF 487 KB Posted

Attached to
(MATOC ONLY) Install Antenna Tower SOCKOR
Solicitation number
W91QVN24R0139
Issued by

About this file

This document is an amendment to a solicitation for a construction contract to build a tactical antenna tower at the Special Operations Command Korea (SOCKOR) headquarters in South Korea. The key details are:

The contractor shall provide all necessary labor, materials, and resources to construct a 20x20x20 ft tactical antenna tower, including excavation and site preparation, construction of the tower, electrical work, network cabling, and installation of two FM antennas. The period of performance is 90 days from the date of award. The solicitation closing date has been extended to September 23, 2024 at 8:00 AM. The work must be performed in accordance with applicable electrical, environmental, and safety standards. The government will not provide any equipment, utilities, or facilities. The contractor shall provide a one-year warranty on the installation and materials.

View the file

Other files

File Type Posted
A03 Drawings.pdf PDF
B08 RFP W91QVN24R0139.pdf PDF
A02 Holiday Schedule.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

411TH CSB, KOREA - HUMP CONTRACTING DIV

POC: MS. KWON, HYEUN

DSN: 315-755-0649

EM AIL: HYEUN.KWON.LN@ARMY.MIL

APO AP 96271

UNITED STATES

0012154890 300000312280

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provi ded herei n, all t erms and condit ions of t he document refere nced in Item 9A or 10A, as heretofore change d, remai ns unchanged and in ful l force and effect .

15A. NAME AND TIT LE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

ST ANDARD FORM 30 (Rev. 10-83) Prescr ibed by GSA

FAR (48 CFR) 53.243

- The purpose of this amendment is to revise SOW. Please see next pages.

- Closing date and time is extended to 23 Sep 24, 08:00AM.

1. CO NTRACT ID CODE P AGE OF P AGES

J 1 5

16A. NAME AND T ITLE OF CONTRACTING OFFICER (Type or print)

16C. DAT E SIGNED

BY 10-Sep-2024

16B. UNITED ST AT ES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contract ing Officer )(Signature of person authorized t o sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, Count y, Stat e and Zip Code) X W91QVN24R0139

X 9B. DAT ED (SEE IT EM 11)

28-Aug-2024

10B. DAT ED (SEE IT EM 13)

9A. AMENDMENT OF SOLICITAT ION NO.

11. THIS IT EM ONLY APPLIES T O AMENDMENT S OF SOLICITATIONS

X The above numbered soli cit ati on i s amended as set forth in It em 14. The hour and date specified for rece ipt of Offer X is ext ended, is not extended.

Offer must acknowl edge rece ipt of t his amendment pri or to the hour and date specified in the sol ici tat ion or as amended by one of t he fol lowing methods:

(a) By compl eti ng Items 8 and 15, and returning copi es of the amendment ; (b) By acknowledgi ng recei pt of thi s a mendment on each copy of t he offer submit ted;

or (c) By s epara te let ter or t elegram whi ch i ncludes a refe rence t o t he s olic ita tion and amendment numbers . FA ILURE OF YOU R A CKNOWLEDGMENT TO BE RECEIVED AT TH E P LACE D ESIGNATED FOR TH E RECEIPT OF OFFERS P RIO R TO THE HOUR AN D DATE SP ECIFIED MA Y RESULT IN

REJECTIO N OF YOUR OFFER. If by vir tue of thi s amendment you desire t o change an offer already submit ted, s uch c hange ma y be made by t ele gram or let ter, provided each t elegram or l ett er makes reference to the sol ici tat ion and this amendment , and is re ceived prior to the openi ng hour and dat e speci fi ed.

12. ACCOUNTING AND APPROPRIATION DAT A (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORT H IN ITEM 14 ARE MADE IN THE

CONT RACT ORDER NO. IN ITEM 10A.

B. T HE ABOVE NUMBERED CONT RACT /ORDER IS MODIFIED T O REFLECT THE ADMINIST RATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORT H IN ITEM 14, PURSUANT TO T HE AUTHORITY OF FAR 43.103(B).

C. T HIS SUPPLEMENT AL AGREEMENT IS ENT ERED INTO PURSUANT TO AUTHORITY OF:

D. OT HER (Specify type of modification and authorit y)

E. IMPORTANT: Contract or is not, is required to sign this document and return copies t o the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/cont ract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/ MODIFICATION NO. 5. P ROJECT NO .(If appli cable)

6. ISSUED BY

3. EFFECTIVE DATE

10-Sep-2024

CODE

411TH CONTRACTING SUPPORT BRIGADE, KOREA

HUMPHREYS CONTRACTING DIVISION

UNIT 15289

APO AP 96271-5584

UNITED STATES

W91QVN 7. AD MINISTERED BY (If other t han item 6)

4. REQUISITION/PU RCHASE REQ. NO.

CODE W91QVN

FACILITY CODECODE

EMAIL:TEL:

W91QVN24R0139

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION A - SOLICITATION/CONTRACT FORM

The required response date/time has changed from 11-Sep-2024 01:00 PM to 23-Sep-2024 08:00 AM.

SECTION C - DESCRIPTIONS AND SPECIFICATIONS

The following have been modified:

STATEMENT OF WORK

Statement of Work Tactical Antenna Tower construction at SOCKOR HQ P7626

(SOCKOR SOJ4 ENG)

1.0 Background/Introduction:

Special Operations Command – Korea has a requirement for the construction of a tactical antenna tower to bolster joint Operation Center tactical antenna communications. The current structure at the SOCKOR HQ is inadequate to fulfill this need, despite being a component commander under USFK. This mission is crucial not only to support the Theater Special Operations Command but also to assist the USFK commander in special operation missions within South Korea.

2.0 Scope: The Contractor shall furnish all necessary personnel, labor, supervision, coordination, transportation, materials, and resources to accomplish the construction of a tactical antenna tower as described below:

2.1 Excavate current ground level and prepare a new foundation for the antenna tower (Location drawing available).

2.2 Construct a communication tower measuring 20ft (L) x 20ft (W) x 20ft (H) using H-beams and install safeguard rails. (drawing available)

2.3 Build stairs and install safeguard rails (drawing available).

2.4 Implement protective ground systems.

2.5. Establish a power source for antenna connection with adjacent building 7626, room 101D, for 2x 20 Amp 120v GFCI outlets (Drawing available).

2.6 Install 2x 20 Amp 120V GFCI outlets on the tower (Drawing available).

2.7 Mount a 48”x36” size 1X Junction Box on the tower.

2.8 Install ¾” size conduit from the tower junction box along building 7626 roof and/or wall to room 101c 105C junction box.

2.9 Provide, pull, and terminate 10x LMR-400 Coax cables with RJ 45 Plugs BNC connectors from the antenna tower to room 105C junction box.

2.10 Provide, pull, and terminate 4x Shielded CAT6 Ethernet cables with shielded CAT6 RJ45 connectors from the antenna tower to room 105C junction box.

2.11 Install two FM Antennas - FM DX Antenna Co Long Range Outdoor Vertical Reception Antenna 88-108 MHz (location per COR directive on tower).

2.12 Mount two Antenna Mounts - FM Antenna Mount, Weather-proof and UV resistant (location per COR directive on tower).

3.0 Incidental Service: The contractor shall perform the following incidental services:

3.1 Construction of the tower.

3.2 Electrical work.

3.3 Provision of network cable materials and pulling services.

3.4 Installation of two FM Antennas - FM DX Antenna Co Long Range Outdoor

Vertical Reception Antenna 88-108 MHz (location per COR directive on tower).

3.5 Mounting of two Antenna Mounts - FM Antenna Mount, Weather-proof and UV resistant (location per COR directive on tower).

4.0 Desired Outcome: The contractor shall be responsible for providing the following materials and incidental services:

4.1 Ensure functional tactical antenna tower requirements for this project.

4.2 Supply material and install network cables.

4.3 Provide power on the tower to operate the antenna.

5.0 Period of Performance: Full performance lead time: 90 days from the date of award. SOCKOR SOJ4 Engineer will approve the work schedule.

6.0 Place of Performance: USAG-H P 7626 SOCKOR HQ

7.0 Codes and Regulations: All work will be done in accordance with Army, DoD, federal, country, safety and environmental codes and regulations; and as per the following electrical and environmental standards (as applicable):

Environment Governing Standard (EGS) 201-1 UFC 3-500: electrical IEEE C2-2012 National Electrical Safety Code (NESC)

EM 385-1-1

O&MA 2014

8.0 Site Visit: Contractor shall examine the site and determine for themselves the existing conditions and general character of the site. Claims for additional costs due to conditions that could have been verified by site investigation will not be authorized. Contractor shall contact the COR to schedule the Site Visit.

9.0 Government Furnished Property (GFP) and Services: The US Government will not provide any equipment, fuel, personnel, utilities or facilities to the contractor for the execution of this contract. Should an emergency arise, only the necessary basic lifesaving and life support measures will be provided during the emergency.

10.0 Work Week and Hours of Operation:

10.1 The contractor will provide services during normal working hours excluding US and ROK holidays.

10.2 Normal working hours are 0800-1700, Monday through Friday, unless requirements dictate otherwise.

10.3 The COR can permit exceptions upon request and at the COR’s discretion.

10.4 Attached is a list of holidays observed by the US and ROK Governments.

11.0 Security and Access Requirements:

11.1 Contractor shall adhere to current installation security policies. All necessary permits, passes and other security/access requirements shall be obtained prior to commencing the applicable stage of work.

12.0 General Requirements:

12.1 Materials for this project shall meet all applicable Korean and U.S.

Standards. Manufacturer’s plan of installation will be submitted to the government/customer POC listed for review and approval prior to installation. Material shall all be new (no refurbished items).

12.2 Pre-final/Final inspection will be conducted upon completion of work. The United States Government will perform the inspection within 2 working days after notification by the Contractor.

12.3 The contractor shall provide a One Year Warranty of installation and provide the standard material warranty from the manufacture. Warranty should start the day of final inspection and acceptance.

12.4 The contractor shall be responsible for the protection of existing equipment, landscape, structures and surrounding facilities. Any damages shall be repaired to match conditions prior to damage at no additional cost to the government.

12.5 The contractor shall provide a contract manager who shall be responsible for the performance of the work. The contract manager shall have full authority to act in behalf of the contractor on all contract matters relating to daily operations of this contract. The contract manager shall be able to read, write, speak, and understand English.

12.6 Contractor personnel shall present a neat appearance and be easily recognized as contractor employees. This may be accomplished by wearing distinctive clothing bearing the company name or by wearing appropriate badges which contain the contractor’s company name and the employee’s name.

12.7 Smoking is not allowed inside and within 50 feet of the entrance of any facility. The contractor or the contract manager is responsible to enforce the smoking policy for all employees engaged in the performance of this contract work.

12.8 The telephone number for Security Police, Fire Protection, Emergency

Medical Service, and other emergencies is 911.

12.9 The contractor shall properly dispose of all existing parts and equipment in accordance with Korean/local laws upon completion of work.

13.0 Points of Contact:

13.1 Customer POC: CPT Korey D. Jordan II, Engineer DSN: 757-7913

13.2 POC for Acceptance of Deliverables: CPT Korey D. Jordan II, Engineer

DSN: 757-7913

13.3 Alt POC for Acceptance of Deliverables: Maj Jonathan Barnes DSN:

757-3592

13.4 Financial POC: Ms. Maria Parente DSN: 315-757-1033

(End of Summary of Changes)