This document is a Request for Proposals (RFP) for a construction contract to install an antenna tower at the Special Operations Command Korea (SOCKOR) headquarters. The RFP is only open to contractors holding existing multiple award IDIQ contracts with the Army.

The scope of work includes excavation, constructing the 20ft x 20ft x 20ft tower, installing stairs and guardrails, establishing power and grounding, and installing antennas and associated equipment. The contractor must complete the work within 90 calendar days after award. The estimated price range for the contract is between $250,000 and $500,000. Proposals are due by September 11, 2024 at 1:00 PM local time. Award will be made to the responsible offeror submitting the lowest priced, technically acceptable proposal. The procuring agency is the 411th Contracting Support Brigade, Korea.

View the file

Other files

File Type Posted
B08 Amendment W91QVN24R0139-0001.pdf PDF
A03 Drawings.pdf PDF
A02 Holiday Schedule.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

0012154890

A. This is a Non-Work Plan Task Order for the follow ing MA IDIQ Construction Contractors only. Contract Numbers W91QVN-24-D-0080, 0021, 0022, 0023, 0024, 0025, 0026, 0027, 0028, 0029, 0030, 0031, 0032, 0033, 0034, 0035, 0036, 0037, 0038, 0083, 0108, 0100, 0104, and 0109.

B. Site Visit: All MATOC offerors w ho intend to propose on this solicitation are strongly encouraged to attend the site visit. See site visit clause in Section L for Schedule.

C. If the Contractor is unable to submit the proposal in response to this RFP, the Contractor shall submit the “No-Offer Letter” by date and time specif ied in this solicitation.

D. Construction Price Range: Pursuant to FAR 36.204 the estimated price range is betw een $250,000 and $500,000.

MS KWON, HYEUN 315-755-0649

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

28-Aug-2024

(RFP)

(IFB)

X

CALL:

Install Antenna Tow er

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________90 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________Section F

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

YES X NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________11 Sep 2024 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______240 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

411TH CONTRACTING SUPPORT BRIGADE, KOREA

HUMPHREYS CONTRACTING DIVISION

UNIT 15289

APO AP 96271-5584

UNITED STATES

W91QVN

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

01:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

300000312280

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W91QVN24R0139 17

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W91QVN24R0139

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job L Work

FFP

Install Antenna Tower

FEWR# 300000312280

FOB: Destination

PURCHASE REQUEST NUMBER: 0012154890

PSC CD: Z2AZ

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0002 1 Lot War Hazard

FFP

Estimated Cost for War Hazard Losses is Zero (0).

FOB: Destination

PURCHASE REQUEST NUMBER: 0012154890

PSC CD: Z2AZ

NET AMT

Section C - Descriptions and Specifications

STATEMENT OF WORK

Statement of Work Tactical Antenna Tower construction at SOCKOR HQ P7626

(SOCKOR SOJ4 ENG)

1.0 Background/Introduction:

Special Operations Command – Korea has a requirement for the construction of a tactical antenna tower to bolster joint Operation Center tactical antenna communications. The current structure at the SOCKOR HQ is inadequate to fulfill this need, despite being a component commander under USFK. This mission is crucial not only to support the Theater Special Operations Command but also to assist the USFK commander in special operation missions within South Korea.

2.0 Scope: The Contractor shall furnish all necessary personnel, labor, supervision, coordination, transportation, materials, and resources to accomplish the construction of a tactical antenna tower as described below:

2.1 Excavate current ground level and prepare new foundation for the antenna tower (Location drawing available).

2.2 Construct a communication tower measuring 20ft (L) x 20ft (W) x 20ft (H) using H-beams (drawing available).

2.3 Build stairs and install safeguard rails (drawing available).

2.4 Establish a power source for antenna connection (Drawing available).

2.5 Implement protective ground systems.

2.6 Install 2 X GFCI 120V 20 Amps Circuit outlets on the tower (Drawing available).

2.7 Mount a 48 X 36 size 1X Junction Box on the tower.

2.8 Install ¾ size conduit from the tower to P7626 Roof to room 101c.

2.9 Provide 10X LMR 400COAX Cables with RJ 45 Plugs.

2.10 Install two FM Antennas - FM DX Antenna Co Long Range Outdoor

Vertical Reception Antenna 88-108 MHz (location per COR directive on tower).

2.11 Mount two Antenna Mounts - FM Antenna Mount, Weather-proof and UV resistant (location per COR directive on tower).

3.0 Incidental Service: The contractor shall perform the following incidental services:

3.1 Construction of the tower.

3.2 Electrical work.

3.3 Provision of network cable materials and pulling services.

3.4 Installation of two FM Antennas - FM DX Antenna Co Long Range Outdoor

Vertical Reception Antenna 88-108 MHz (location per COR directive on tower).

3.5 Mounting of two Antenna Mounts - FM Antenna Mount, Weather-proof and UV resistant (location per COR directive on tower).

4.0 Desired Outcome: The contractor shall be responsible for providing the following materials and incidental services:

4.1 Ensure functional tactical antenna tower requirements for this project.

4.2 Supply material and install network cables.

4.3 Provide power on the tower to operate the antenna.

5.0 Period of Performance: Full performance lead time: 90 days from the date of award. SOCKOR SOJ4 Engineer will approve the work schedule.

6.0 Place of Performance: USAG-H P 7626 SOCKOR HQ

7.0 Codes and Regulations: All work will be done in accordance with Army, DoD, federal, country, safety and environmental codes and regulations; and as per the following electrical and environmental standards (as applicable):

Environment Governing Standard (EGS) 201-1 UFC 3-500: electrical IEEE C2-2012 National Electrical Safety Code (NESC)

EM 385-1-1

O&MA 2014

8.0 Site Visit: Contractor shall examine the site and determine for themselves the existing conditions and general character of the site. Claims for additional costs due to conditions that could have been verified by site investigation will not be authorized. Contractor shall contact the COR to schedule the Site Visit.

9.0 Government Furnished Property (GFP) and Services: The US Government will not provide any equipment, fuel, personnel, utilities or facilities to the contractor for the execution of this contract. Should an emergency arise, only the necessary basic lifesaving and life support measures will be provided during the emergency.

10.0 Work Week and Hours of Operation:

10.1 The contractor will provide services during normal working hours excluding US and ROK holidays.

10.2 Normal working hours are 0800-1700, Monday through Friday, unless requirements dictate otherwise.

10.3 The COR can permit exceptions upon request and at the COR’s discretion.

10.4 Attached is a list of holidays observed by the US and ROK Governments.

11.0 Security and Access Requirements:

11.1 Contractor shall adhere to current installation security policies. All necessary permits, passes and other security/access requirements shall be obtained prior to commencing the applicable stage of work.

12.0 General Requirements:

12.1 Materials for this project shall meet all applicable Korean and U.S.

Standards. Manufacturer’s plan of installation will be submitted to the government/customer POC listed for review and approval prior to installation. Material shall all be new (no refurbished items).

12.2 Pre-final/Final inspection will be conducted upon completion of work. The United States Government will perform the inspection within 2 working days after notification by the Contractor.

12.3 The contractor shall provide a One Year Warranty of installation and provide the standard material warranty from the manufacture. Warranty should start the day of final inspection and acceptance.

12.4 The contractor shall be responsible for the protection of existing equipment, landscape, structures and surrounding facilities. Any damages shall be repaired to match conditions prior to damage at no additional cost to the government.

12.5 The contractor shall provide a contract manager who shall be responsible for the performance of the work. The contract manager shall have full authority to act in behalf of the contractor on all contract matters relating to daily operations of this contract. The contract manager shall be able to read, write, speak, and understand English.

12.6 Contractor personnel shall present a neat appearance and be easily recognized as contractor employees. This may be accomplished by wearing distinctive clothing bearing the company name or by wearing appropriate badges which contain the contractor’s company name and the employee’s name.

12.7 Smoking is not allowed inside and within 50 feet of the entrance of any facility. The contractor or the contract manager is responsible to enforce the smoking policy for all employees engaged in the performance of this contract work.

12.8 The telephone number for Security Police, Fire Protection, Emergency

Medical Service, and other emergencies is 911.

12.9 The contractor shall properly dispose of all existing parts and equipment in accordance with Korean/local laws upon completion of work.

13.0 Points of Contact:

13.1 Customer POC: CPT Korey D. Jordan II, Engineer DSN: 757-7913

13.2 POC for Acceptance of Deliverables: CPT Korey D. Jordan II, Engineer DSN:

757-7913

13.3 Alt POC for Acceptance of Deliverables: Maj Jonathan Barnes DSN:

757-3592

13.4 Financial POC: Ms. Maria Parente DSN: 315-757-1033

Section F - Deliveries or Performance

CLAUSES INCORPORATED BY FULL TEXT

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 90 calendar days after notice to proceed (NTP) is issued. The time stated for completion shall include final cleanup of the premises.

(End of clause)

Section I - Contract Clauses

252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)

(a) Definitions. As used in this clause—

“Department of Defense Activity Address Code (DoDAAC)” is a six position code that uniquely identifies a unit, activity, or organization.

“Document type” means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

“Local processing office (LPO)” is the office responsible for payment certification when payment certification is done external to the entitlement system.

“Payment request” and “receiving report” are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232- 7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall—

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.

(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.

(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:

(1) Document type. The Contractor shall submit payment requests using the following document type(s):

(ii) For fixed price line items—

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.

Invoice 2in1

(2) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF Data to be entered in WAWF

Pay Official DoDAAC HQ0490

Issue By DoDAAC W91QVN

Admin DoDAAC** W91QVN

Inspect By DoDAAC W81HME

Ship To Code W81HME

Ship From Code ____

Mark For Code ____

Service Approver (DoDAAC) ____

Service Acceptor (DoDAAC) ____

Accept at Other DoDAAC ____

LPO DoDAAC ____

DCAA Auditor DoDAAC ____

Other DoDAAC(s) ____

(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.

(g) WAWF point of contact.

(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity’s WAWF point of contact.

TBD

E-mail:

DSN: (315), Com:

(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.

(End of clause)

Section J - List of Documents, Exhibits and Other Attachments

DRAWINGS AND OTHER ATTACHMENTS

Please see the attachments.

1. A02 Holiday Schedule.pdf

2. A03 Drawings.pdf

Section K - Representations, Certifications and Other Statements of Offerors

ATTACHMENT: CONTRACTOR’S TAX EXEMPTION DECLARATION

(1) References:

(i) Contract clause, "FAR 52.229-06 Taxes—Foreign Fixed-Price Contracts (Jan 1991)."

(ii) US-ROK Status of Forces Agreement (SOFA), Articles IX and XVI.

(iii) ROK Customs Law, Law No. 1976, promulgated on 29 November 1967, as amended.

(iv) ROK Value Added Tax Law, Law No. 2934, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.

(v) ROK Special Excise Tax Law, Law No. 2935, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.

(2) Contractor shall state the types and estimated amount of taxes that would normally apply to such transactions but are excluded from this proposal.

(i) Customs Tax (except for ROK MND-funded contracts or delivery orders):

Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total

This item will be imported specifically for this contract? Yes _________ No ________

(ii) Special Excise Tax:

Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total

Name of item manufacturer

(iii) Value Added Tax (VAT):

Input VAT on materials purchased for this contract. _________ Input VAT on transportation leased/rented for this contract. _________ Input VAT on equipment leased/rented for this contract. _________ Input VAT on services purchased for this contract. _________ Output VAT on total contract amount. _________

(iv) Special Excise (Petroleum) Tax:

No. of Unit Price Total Tax Liters w/o Tax Tax/Unit Amount

Regular Gasoline __________ (L) ₩_________ ₩________ ₩_________

Premium Gasoline __________ (L) ₩_________ ₩________ ₩_________

Diesel __________ (L) ₩_________ ₩________ ₩_________

Other __________ (L) ₩_________ ₩________ ₩_________

(3) Name of Oil Company Refinery from which POL products will be purchased:

Oil Company: _________________________________________ (Name only)

(4) I certify by this submission that all supplies and services to be purchased for this contract have been proposed exclusive of Value Added Tax, applicable Customs Tax (except for ROK MND-funded contracts and delivery orders), and Special Excise Tax.

Contractor’s Signature

52.203-2 CERTIFICATE OF INDEPENDENT PRICE DETERMINATION (APR 1985)

(a) The offeror certifies that --

(1) The prices in this offer have been arrived at independently, without, for the purpose of restricting competition, any consultation, communication, or agreement with any other offeror or competitor relating to –

(i) Those prices,

(ii) The intention to submit an offer, or

(iii) The methods of factors used to calculate the prices offered:

(2) The prices in this offer have not been and will not be knowingly disclosed by the offeror, directly or indirectly, to any other offeror or competitor before bid opening (in the case of a sealed bid solicitation) or contract award (in the case of a negotiated solicitation) unless otherwise required by law; and

(3) No attempt has been made or will be made by the offeror to induce any other concern to submit or not to submit an offer for the purpose of restricting competition.

(b) Each signature on the offer is considered to be a certification by the signatory that the signatory --

(1) Is the person in the offeror's organization responsible for determining the prices offered in this bid or proposal, and that the signatory has not participated and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision; or

(2) (i) Has been authorized, in writing, to act as agent for the following principals in certifying that those principals have not participated, and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provison ______________________________________________________ (insert full name of person(s) in the offeror's organization responsible for determining the prices offered in this bid or proposal, and the title of his or her position in the offeror's organization);

(ii) As an authorized agent, does certify that the principals named in subdivision (b)(2)(i) above have not participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) above; and

(iii) As an agent, has not personally participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision.

(c) If the offeror deletes or modifies subparagraph (a)(2) of this provision, the offeror must furnish with its offer a signed statement setting forth in detail the circumstances of the disclosure.

(End of Provision)

Section L - Instructions, Conditions and Notices to Bidders

INSTRUCTION TO OFFEROR

1. GENERAL INSTRUCTIONS FOR PREPARATION OF PROPOSAL:

a. The Government intends to award without discussion, but reserves the right to conduct discussions if deemed necessary.

b. Offeror(s) may, at the discretion of the Government, be asked to provide more information and clarification regarding their proposals. The Government may make a final determination as to whether an offer is acceptable or unacceptable solely based on the proposals as submitted, without requesting any further information. However, if it is deemed necessary the Government may, at its sole discretion, request additional information clarifying but not substantially changing any proposal as submitted.

2. SUBMISSION OF PROPOSAL:

a. EMAIL SUBMISSION REQUIRED: Offers shall be submitted to email to hyeun.kwon.ln@army.mil. All questions shall be submitted to hyeun.kwon.ln@army.mil in writing be within five (5) days after the solicitation is issued or no more than two (2) business days after any scheduled site visit, whichever is later. The government reserves the right to extend the time period for submission of documents.

3. CLOSING DATE: The electronic offer shall be submitted by 1300 hours on the closing date of RFP.

4. SUBMISSION REQUIREMENTS:

a. PRICING PROPOSAL: The pricing proposal must clearly indicate prices for each Contract Line Item Number in Section B - Supplies or Services and Prices.

b. DETAILED OFFER BREAKDOWN: The detailed offer breakdown must clearly identify all costs that can materially impact the statement of work.

5. SECTION K:

a. SECTION K-TAXES: Offerors must complete all tax portions of SECTION K. The offeror shall review all expenses to ensure that all applicable taxes are excluded from the overall price. In addition, offerors shall propose exemptions of specific ROK taxes that are legitimate, attributable to the contract, and authorized by the applicable stated references.

b. SECTION K-OTHER: Offerors must complete all Non-Tax related portions of SECTION K.

6. COMPLIANCE WITH SOLICITATION: Failure to submit the above requirements under SECTION L may be grounds for determining the proposal to be non-compliant. For example, if a detailed offer breakdown is not submitted, the contracting officer will be unable to find the offeror's pricing proposal acceptable and the offeror's proposal will be ineligible for award. Non-compliance will only be cured if the government holds discussions as detailed in SECTION L.

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for--

Date: 5 September 2024 Time: 1000hours

(c) Participants will meet at--

In front of B#7626, Camp Humphreys POC: 1LT Ronald Phillips at (Phone) 0503-357-7619

* Contractors who want to attend the site visit shall email your name, company name, and telephone number to Ronald.A.Phillips.mil@socom.mil no later than 4 September 2024, 1000hours.

(End of provision)

Section M - Evaluation Factors for Award

EVALUATION FACTORS FOR AWARD

Electronic offers submitted by 1300 hours on the closing date of RFP shall be considered timely.

1. EVALUATION CRITERIA:

a. The pricing proposal shall be evaluated to determine whether it is complete, balanced, and reasonable. A complete, balanced, and reasonable pricing proposal will be deemed acceptable.

b. The detailed offer breakdown will be used by the contracting officer to determine whether proposed prices are complete, balanced, and reasonable. A detailed offer breakdown may be used by the contracting officer to determine whether an offeror is able to complete the requirements under the contract, and/or whether discussions will be conducted pursuant to instructions to the offerors.

2. SECTION K - Representations, Certifications and Other Statements of Offerors

a. SECTION K-TAXES will be evaluated to determine whether it is complete. In addition, propose exemptions of specific ROK taxes will be evaluated to determine whether they are legitimate, attributable to the contract, authorized, and reasonable. A complete SECTION-K that only proposes exemptions of specific ROK taxes that are legitimate, attributable to the contract, necessary to complete the Task Order, do not improperly overstate any proposed tax exemption, authorized, and reasonable will be deemed acceptable.

b. SECTION K-OTHER will be evaluated to determine whether it is complete. A complete SECTION K-OTHER will be deemed acceptable.

3. BASIS FOR AWARD: Award shall be made to the responsible offeror submitting the lowest priced offer that is evaluated as acceptable for all evaluation criteria.