This document is a solicitation (W91QVN24R0046) for the overhaul of chillers and cooling towers at the US Army Garrison Humphreys in Pyeongtaek, South Korea. The government is seeking a contractor to provide all personnel, equipment, tools, vehicles, materials, supervision, and other resources necessary to overhaul 18 chillers and 38 cooling towers across 11 buildings.
The overhaul work includes repair, replacement, cleaning, inspection, testing, and calibration, and must be completed between August 1, 2024 and April 30, 2025. Pricing must be submitted in Korean Won. The contractor will be responsible for proper disposal of all waste and hazardous materials. The government will provide access to utilities, but the contractor must furnish all other required materials and equipment. Award will be made on a firm-fixed-price basis. This is an unrestricted procurement, but the contractor must obtain the necessary business licenses directly from the Republic of Korea government.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE ADDENDUM
(No Collect Calls)
W91QVN24R0046 23-Apr-2024
b. TELEPHONE NUMBER
315-755-3363
8. OFFER DUE DATE/LOCAL TIME
01:00 PM 22 May 2024
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W91QVN9. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
MS. CHO, YE-SIK
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
0012089603
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED ORX
SMALL BUSINESS
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
411TH CONTRACTING SUPPORT BRIGADE, KOREA
HUMPHREYS CONTRACTING DIVISION
UNIT 15289
APO AP 96271-5584
UNITED STATES
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE WT4KBR 16. ADMINISTERED BY
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
W3BH USA GARRISON HUMPHREYS
WT4KBR
0194 DSSB CO A SRA
BLDG P6953, CAMP HUMPHRESY
PYONGTAEK 17982
KOREA, SOUTH
TEL: 011-82-53-470-65 FAX:
FAX:
TEL: SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
$19,000,000
NAICS:
238220
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF56
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
W91QVN24R0046
Section SF 1449 - CONTINUATION SHEET
NOTICE TO OFFERORS
All sources may submit a proposal as applicable. However, the Republic of Korea (ROK)-United States (U.S.) Status of Forces Agreement (SOFA), precludes the U.S. Government from granting Invited Contractor or Technical Representative Status to any offeror, for this requirement. All sources submitting a proposal, as applicable, including U.S. sources, must already have, or obtain the requisite business licenses directly from the ROK Government, and conduct business in accordance with all applicable ROK laws, including but not limited to, rules and policies regarding labor, taxation, and immigration. Any contractor not already doing business in Korea, must submit adequate verification in its initial proposal - that it has the requisite business licenses directly from the ROK Government to perform the contract and the capacity to conduct business in accordance with all applicable ROK laws, including but not limited to, rules and policies regarding labor, taxation, and immigration. If an initial proposal does not fully demonstrate this authorization and capacity, it will not be further considered for award. Whether an offeror demonstrates this authorization and capacity shall be determined by the Contracting Officer. “All offerors interested in competing for this requirement are required to submit their price proposal in Korean Won(KW) only. A proposal submitted in currency other than Korean Won will not be considered for award.”
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 18 Job Perform Overhaul Chillers
FFP
The Contrctor shall provide all personnel, equipment, tools, vehicles, materials, supervision, and any other re-sources necessary for overhaul of eighteen (18) each chillers as listed in Technical Exhit 02 in accordance with PWS.
FOB: Destination
PURCHASE REQUEST NUMBER: 0012089603
PSC CD: J049
NET AMT
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0002 38 Job Perform Overhaul Cooling Towers
FFP
The Contrctor shall provide all personnel, equipment, tools, vehicles, materials, supervision, and any other re-sources necessary for overhaul of thirty eight (38) each cooling towers ers as listed in Technical Exhit 01 in accordance with PWS.
FOB: Destination
PURCHASE REQUEST NUMBER: 0012089603
PSC CD: J049
NET AMT
PWS
Performance Work Statement (PWS) Overhaul Cooling Towers and Chillers at USAG Humphreys
1.0 Introduction. This is a non-personal services contract to provide overhaul cooling towers and chillers at the US Army Garrison Humphreys. The Government will not exercise any supervision or control over the contract service providers. The Contractor shall perform to the standards specified in this Performance Work Statement (PWS). Contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government. The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary as defined in this PWS. The Contractor is responsible for providing all parts required for overhaul cooling towers and chillers.
1.1 Background. The Government is in need of overhaul cooling towers and chillers to the buildings. The United States Army Garrison (USAG) Humphreys is located in Pyeongtaek city, Gyeonggi Province, Korea, and consists of approximately 3,370 acres and 954 buildings. The population base consists of approximately 40,000 military, Government civilian, and Contactor personnel, as well as resident family members. 32 cooling towers and 28 chillers supporting HVAC cooling system in 11 buildings are reached to economical operational hours that require manufacturer recommended maintenance.
1.2 Objectives. The Contractor shall ensure all work accomplished in the performance of this PWS meets all applicable Federal, State, and Local Laws, Regulations, and Directives to include, but not limited to, the publications in Section 7, Related Documents. The Government anticipates the subject service contract supports efficient operation of building and facility systems, reduction in energy consumption, reduced operating and maintaining costs and increased security, and comfortable indoor air quality.
1.2.1 The Contractor shall compile historical data, prepare required reports, and submit all information as specified by the Deliverables presented in the contract. The Contractor shall ensure all work in support of mission requirements tendered to the Government for acceptance conform to the measurable performance standards of quality, timeliness, and quantity specified in the PWS of this contract.
The intent is to establish work requirements that are performance-based and results-oriented. The Contractor shall determine the best and most cost-effective ways to fulfill operation and maintenance of facility automation system and their component needs, emphasizing innovation and commercial best practices.
1.3 Climatic Conditions. N/A
1.4 Facility Access. N/A
1.5 Traffic Flow. N/A
1.6 Drainage. N/ A
1.7 Restoration of Landscape Damage. Trees or other landscape features damaged by the Contractor’s operations shall be restored to the original state at no additional cost to the Government.
1.8 Dust Suppression. The Contractor shall perform dust suppression when necessary, during maintenance and repair activities or as directed by the Contracting Officer or COR.
1.9 Utility Location. The Contractor shall perform utility cuts in pavements as required to repair existing utilities after obtaining a digging permit to do so. The Contractor shall locate and stake out underground utility pipes/cables prior to digging operations required by any contract on Garrison property. The Contractor shall be responsible for having the proper equipment to locate all underground utilities. Mechanical digging shall not be permitted within ten (10) feet of identified underground utilities.
1.10 Excavation Permits. N/A.
1.11 Work Clearance. For work involving digging/excavation operations, the Contractor shall obtain a properly approved diffing permit before ground disturbance.
2.0 Requirements.
2.1 Description of Services. The Contractor shall provide all personnel, equipment, tools, vehicles, materials, supervision, and any other resources necessary for overhaul cooling towers and chillers at the USAG Humphreys which listed in the Technical Exhibit 01, in strict compliance with all the provisions of the contracts as specified in performance work statement.
2.1.1 Non-Personal Services. The personnel rendering the services are not subject; either by the contract’s terms or by the manner of its administration, to the supervision and control usually prevailing in relationships between the Government and its employees. Non-personal service contracts are authorized by the Government in accordance with (IAW) Federal Acquisition Regulation (FAR) Subpart 37.104, under general contracting authority, and do not require specific statutory authorization.
2.1.2 General Information. Period of Performance (PoP). The period of performance shall be during 1 August 2024 and 30 April 2025. All overhaul work should be completed prior to 30 April 2025.
2.1.3 Place of Performance and Hours of Operation.
2.1.3.1 Place of Performance. The work to be performed under this contract will be performed at eleven (11) buildings at the USAG Humphreys.
Building 12400 Command and Control Facility, HQ 8A
Building 12410 Command and Control Facility, HQ USFK Building 6400 Admin General Purpose, Garrison HQ Building 6100 Simulation Center Building 6110 General Instruction Building Building 6120 General Instructional Building Building 6315 Admin General Purpose, Brigade HQ Building 6145 Admin General Purpose, Brigade HQ Building 6807 Community Center Building 12600 Admin General Purpose Building, HQ FED Building 12601 Admin General Purpose Building, HQ 411th CSB
2.1.3.2 Hours of Operation. The Government's regular (normal) hours are from 0800 – 1700 hours, excluding ROK holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. The Contractor shall maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons.
2.1.4 ROK Holidays. The Contractor’s performance shall not be required on the ROK holidays listed below, unless there is a requirement to respond to a Priority 1, Emergency.
New Year’s Day: 1 January Lunar New Year’s Day: 31 December, 1 and 2 January on the Lunar Calendar Independence Movement Day: 1 March Buddha's Birthday: 8 April on the Lunar Calendar Labor Day: 1 May Children's Day: 5 May Memorial Day: 6 June Liberation Day: 15 August Chu-Sok: 14, 15, and 16 August on the Lunar Calendar National Foundation Day: 3 October Hangul Day: 9 October Christmas Day: 25 December
U.S. Federal Holidays.
New Year’s Day 1st day of January Martin Luther King Jr.'s Birthday 3rd Monday of January President’s Day 3rd Monday of February Memorial Day Last Monday of May Juneteenth 19th day of June Independence Day 4th day of July Labor Day 1st Monday of September Columbus Day 2nd Monday of October Veterans Day 11th day of November Thanksgiving Day 4th Thursday of November Christmas Day 25th day of December
2.1.4.1 The Contractor shall provide personnel support within two (2) hours of notification outside the normal hours of operation as required, including holidays, to support the Directorate of Public Works (DPW) mission. Prior to performance of services outside the locally established hours of operation, the Contractor shall request and obtain, in writing, approval from the KO. The Contract Manager shall be available after normal hours to serve as the central point of contact for Contractor operations. Contractor personnel shall not be scheduled for overtime work.
2.1.4.2 Installation Closures.
When an unforeseen Installation closure occurs on a regularly scheduled day of work, the Contractor shall reschedule the work to be performed the next business day following the closure unless the following day is a Saturday, Sunday, a recognized Federal Holiday, and when routine work is not scheduled for that day.
2.1.4.3 Inclement Weather Delay. If the Contractor determines unsafe weather conditions for continued operations, then the Contractor shall notify the KO if inclement weather suspends operations within two (2) hours.
The Contractor shall resume operations with KO/COR approval.
2.1.4.4 Curtailment of Operations. When operations are curtailed due to manmade or natural conditions on a working day, it may be necessary for the Government to interrupt that day’s work under this contract. The Contractor shall reschedule the work on any day acceptable to the Government. If the KO agrees, the Contractor may continue the work as scheduled. The KO will provide verbal announcements of immediate curtailment of operations to the Contractor.
2.1.4.5 Days of No Scheduled Activities (DONSA). The Installation has historically granted Military personnel (Enlisted and Officers) DONSA, for example, the Friday after Thanksgiving, in addition to the listed Federal Holidays above.
DONSA are not considered a day of excused absence for the Government civilian work force or Contractor employees.
If a DONSA affects scheduled contract work or access to facilities, the work in affected facilities may be rescheduled to compensate for the DONSA.
However, announced DONSA or exodus of Military personnel may provide the Contractor with an opportunity for unrestricted access to facilities and areas or uninterrupted performance of work (i.e., training facility and area maintenance and supply inventories).
The Contractor shall vary work schedules to take full advantage of such opportunities by planning maintenance that is better accomplished when personnel are not using facilities during those times.
2.1.5 Travel/Temporary Duty. N/A
2.1.6 Emergency Services.
2.1.6.1 Emergency Medical Treatment. The Contractor or their employees shall immediately notify their supervisor of any accident requiring emergency medical treatment. The Contractor shall notify the KO or COR/ACOR immediately, not later than (NLT) two (2) hours of the incident. The Contractor shall be responsible for the emergency medical treatment services for Contractor personnel.
2.1.6.2 Accident Reporting. The Contractor shall comply with Operational Safety and Health Administration (OSHA) for record keeping and reporting of all accidents resulting in death, injury, occupational disease, or adverse environmental impact. A completed typed original plus one (1) copy of ENG FORM 3394 United States Army Corps of Engineers Accident Investigation Report shall be delivered to the KO within five (5) calendar days of occurrence, whenever an accident involving personal injury or government owned property occurs.
2.1.7 Contract Administration and Management.
2.1.7.1 Post Award Conference/Performance Evaluation Meetings. The Contractor shall attend the post award conference convened by the contracting activity or contract administration office IAW FAR Subpart 42.5, Post-award Orientation. The KO and COR/ACOR will meet quarterly with the Contractor to review the Contractor's performance. Written minutes of meetings will be recorded by the Government and signed by both the Contract Manager and the KO. The written minutes will be distributed within five (5) calendar days after the meeting. If the
Contractor does not concur with any portion of the minutes, recorded by the Government, the non-concurrence shall be provided in writing to the KO within two (2) calendar days following receipt of the minutes.
2.1.7.2 Notwithstanding the Contractor’s responsibility for total management during the performance of this contract, the administration of the contract requires maximum coordination and cooperation between the Government and the Contractor.
2.1.7.3 The following provides the roles and their respective authority during the performance of the contract:
2.1.7.3.1 Contracting Officer (KO). The KO is the only person authorized to direct changes in any of the requirements under this contract, and, notwithstanding any provisions contained elsewhere in this contract, said authority remains solely with the KO. In the event the Contractor makes any change at the direction of any person other than the KO, the change shall be considered to have been made without authority and solely at the risk of the Contractor. All contract administration will be affected by the KO. Communications pertaining to contractual administrative matters shall be addressed to the KO. No changes in or deviation from the terms and conditions shall be affected, without a written modification to the contract, executed by the KO authorizing such changes.
The KO will approve all submittals and plans required in this PWS.
2.1.7.3.2 Contracting Officer’s Representative (COR). The KO will appoint a COR during the performance of this contract. Additional Government personnel may be assigned to assist in contract oversight IAW AR 70-13, Management and Oversight of Service Acquisitions. Other surveillance personnel may be designated as COR or Alternate Contracting Officer’s Representative (ACOR), and shall be trained and appointed IAW DoDI 5000.72, DoD Standard for Contracting Officer’s Representative (COR) Certification and DFARS 201.602-2. The Alternate Contracting Officer Representative (ACOR) will serve as on-site representatives of the COR in performance of actual contract surveillance, if they meet all COR training, experience requirements, and are appointed by the KO as an ACOR. The COR/ACOR will provide assistance in identification and resolution of problems, conflicts in priority, subtask requirement definitions, and other operations type problems. The COR/ACOR will perform IAW the responsibilities and duties identified in the appointment letter.
2.1.7.3.2.1 COR Authority. A letter of designation will be issued to the COR/ACOR by the KO. A copy of the letter will be sent to the Contractor. The letter of designation states the responsibilities and limitations of the COR/ACOR, especially with regard to changes in cost, price estimates, or changes in delivery dates. The COR/ACOR is not authorized to change any of the terms and conditions with regard to cost, quantity, or schedule of the resulting order.
2.1.7.3.3. The Contractor shall not in any way represent the United States (U.S.) Government, or that it has the authority to contract or procure supplies for the account of the United States of America (USA).
2.1.8 COR/ACOR Functions. The COR/ACOR monitors all technical aspects of the contract and assists in contract administration. The COR/ACOR is authorized to perform the following functions: assure the Contractor performs the technical requirements of the contract; perform inspections necessary in connection with contract performance; maintain written and oral communications with the Contractor concerning technical aspects of the contract; issue written interpretations of technical requirements; monitor, document, and report Contractor's performance and notify both the KO and Contractor of any deficiencies; coordinate availability of Government- Furnished Property, and coordinate site entry of Contractor personnel.
2.1.9 Quality Control (QC). Quality Control is the responsibility of the Contractor. The Contractor shall provide a Quality Control Plan (QCP) five (5) business days before contract start. The Contractor shall provide and maintain a QCP that is acceptable to the KO. Changes to the Contractor’s QCP shall be submitted to the KO for review and approval within five (5) business days prior to implementation.
2.1.10 Subcontract Management. If the Contractor subcontracts part of the work to be executed within this contract, the Contractor (Prime) has total responsibility of subcontractor’s performance and the U.S. Government will not supervise subcontractor. The contract is between the prime Contractor and the U.S. Government and will be administered and executed as such. The Contractor shall submit the subcontract management plan to the COR within five (5) working days after contract award if subcontract is required. The subcontract management plan shall contain at a minimum, but not limited to the:
1. Name of subcontract
2. Past performance and experiences of subcontract
3. Business Licenses or Permit
4. Responsibilities in this contract
5. Quality Control plan for subcontractor’s performance
2.1.11 Contractor Employees.
2.1.11.1 Key Personnel. The following personnel are considered key personnel by the Government: Contract Manager and HVAC Mechanic. The contractor shall notify any changes in writing to the KO and COR before the changes in personnel become effective. Upon notification of a vacancy of key personnel, the contractor has up to 15 calendar days to fill the position with an individual that meets or exceeds the requirements for that key position and the qualifications of the person they are replacing. In interim (while a back-fill is being sourced), the deputy may fulfill those roles to ensure contract performance. The Contractor shall notify the KO and COR and obtain the Government concurrence for the replacement of key position. Qualifications for all key personnel are listed below:
2.1.11.1.1 Contract Manager (CM). The Contractor shall provide a CM who is responsible for the performance of the work. The CM shall have full authority to act for the Contractor on all contract matters relating to daily operation of the contract. The CM shall have three (3) years of successful and proven track record of contract/project management experiences in maintenance support management or a contract similar in scope and breadth to this solicitation during last five (5) years. The name of the CM shall be provided by the Contractor to the KO. In the circumstances when the CM is not available, the Contractor shall designate an alternate who can perform the same duties during the absence of the CM. The name of this person and an alternate who shall act for the Contractor when the manager is absent shall be designated in writing to the contracting officer at the start of the contract. The CM shall be available between 0800 - 1700 hours, Monday through Friday except ROK holidays or when the Government facility is closed for administrative reasons. The CM and any individuals designated as key personnel shall be able to understand, speak, read, and write the English language.
2.1.11.1.2 HVAC Mechanic: The HVAC Mechanic shall have minimum three (3) years relevant experiences in working with overhaul cooling towers and chillers. Also, the HVAC Mechanic shall have a valid license on
Craftsman Air-Conditioning and Refrigeration Machinery (공조냉동 기능사), or higher grade issued by ROK Government or United States Government.
2.1.11.2 GFEBS Certification. N/A.
2.1.11.3 Common Access Card (CAC). N/A.
2.1.11.4 U.S. Residency. N/A.
2.1.11.5 Qualification Standards. The Contractor shall inspect, repair, and maintain systems and components associated with facilities listed in Technical Exhibit 01 and 02, Equipment Information, as required throughout this contract utilizing properly trained, skilled, and qualified employees or Sub-contractor personnel.
2.1.11.6 Contractor Identification. The Contractor shall ensure all personnel be identified as a Contractor to distinguish themselves (e.g., badge, company logo, or uniform) from Government employees. The Contractor shall ensure all correspondence and reports produced are marked as Contractor products or that Contractor participation is disclosed.
2.1.11.7 Standards of Conduct. Contractor personnel’s conduct shall not reflect discredit upon the Government. The Contractor shall ensure all personnel present a professional appearance while working on the Government Installation. The Contractor’s employees shall observe and comply with all local policies and procedures concerning fire, safety, environmental protection, sanitation, security, and possession of firearms or other lethal or illegal weapons or substance. The Contractor shall ensure all Contractor employees, providing services under this contract, conduct themselves and perform services in a professional, safe, and responsible manner. The Contractor shall remove, from the job site, any employee for reasons of misconduct or security. The Contractor shall ensure employee conduct complies with 41 USC 423, Procurement Integrity. The Contractor shall also ensure that no Contractor employees conduct political related activities or events on the Installation. The removal of such a person shall not relieve the Contractor of the requirement to provide personnel to perform adequate and timely service.
2.1.11.8 Contractor Hiring Restrictions. The Contractor shall not hire or sub-contract with off duty or former Government employees whose employment would result in a conflict with Joint Ethics Regulation (JER) DoD 5500.07-R.
2.1.12 Business Relations. The Contractor shall successfully integrate and coordinate all activity needed to execute the requirement of this PWS. The Contractor shall manage the timeliness, completeness, and quality of problem identification to a degree acceptable to the Government. The Contractor shall provide to the COR/ACOR corrective action plans, timely identification of issues, and effective management of Subcontractors within two (2) days or at a mutually agreed upon date. The Contractor shall ensure customer satisfaction and professional and ethical behavior of all Contractor personnel.
2.2 Work Management. N/A
2.3 As-Builts and Geospatial Information System (GIS). N/A
2.4 Historic Property or Archaeological Site. N/A
2.5 Special Requirements.
2.5.1 Security.
2.5.1.1 Access and General Protection/Security Policy and Procedures. The Contractor and all associated Subcontractors’ employees shall comply with applicable Installation, facility, and local security policies and procedures. The Contractor workforce shall comply with all personal identity verification (PIV) requirements as directed by Department of Defense (DoD), Headquarters Department of the Army (HQDA), and local policy. The COR will request changes in Contractor security matters or processes if the Force Protection Condition (FPCON) at any individual facility or Installation changes.
2.5.1.2 Motor Vehicle Operators. Contractor’s personnel, whose tasks require operation of any vehicles, shall possess a valid driver’s license, certificates, and permits applicable for the type and class of vehicle being operated.
2.5.1.3 Contractor Vehicle Registration. The Contractor shall register all Contractor-owned or operated vehicles and trailers operating on the Installation within seven (7) working days of contract start date. The Contractor shall complete all applications with the Provost Marshal Vehicle Registration section. Evidence of vehicle ownership and vehicle liability insurance must be presented upon application of vehicle registration. All vehicles must be registered IAW current ROK Government requirements.
2.5.1.3.1 Contractor and Vendor Access. All privately-owned vehicles or motorcycles or Contractor or vendor-furnished vehicles and equipment must enter the Installation through the designated secure access control points (ACP). Under the present Installation FPCON, vehicle and equipment operators and passengers must possess identification documents as required by DES to access the Installation. Vehicle and equipment operators must also possess and be ready to show a valid ROK Government and/or commercial driver's license, current vehicle registration, and proof of ROK Government required minimum liability insurance. As determined by the Installation FPCON, an elevated FPCON may require additional security screening and/or limited Installation access. All vehicles must be registered IAW current ROK Government requirements in which they are registered.
2.5.1.3.2 All Contractor personnel, not possessing a Common Access Card (CAC), requesting access to USAG Humphreys will enter through the designated Visitor Control Center (VCC). All Contractor personnel will be required to present a ROK Government issued identification that is capable of being scanned for valid entry.
Contractor personnel will receive a visitor’s Defense Biometric Identification System (DBIDS) at the VCC with the length of access allowed. The maximum access length for visitor DBIDS is one year. Once issued a valid visitor’s DBIDS Contractor personnel may enter any Manned Access Control Point/Gate. All Contractor personnel and their vehicles, equipment, and packages are subject to inspection or examination (search) at entry/exit of the USAG Humphreys.
2.5.1.4 Physical Security. The Contractor shall safeguard all Government equipment, information, and property provided for Contractor use IAW AR 190-13, The Army Physical Security Program. The Contractor shall maintain a physical security checklist or log (e.g., Standard Form (SF) 701, Activity Security Checklist), which will be forwarded to the KO and COR, NLT the 10th of each month, following the month of surveillance. The Contractor shall secure Government facilities, equipment, and materials at the close of each work period.
The Contractor will be provided Government furnished on-site staging area for necessary equipment and materials. The Contractor shall secure the area at the close of each work period. The Contractor shall be solely responsible for any loss or damage of equipment and material. The Contractor shall ensure debris of any type will be disposed of according to local policies and directives.
2.5.1.5 Secure Area Access. Portions of the work under the contract are performed in secure areas and all persons requiring access to a secure area will be escorted by the activity or Government personnel. In the case of escort, forty-eight (48) hours advance notice to the activity shall be required except in emergency or urgent work.
Contractor employees requiring access to secure areas shall be free of felony convictions, and prior Military Service Members shall have an honorable discharge (See DD Form 254, Department of Defense Contract Security Classification Specification).
2.5.1.6 Employee Terminations. When an employee is terminated from employment on the contract for any reason, the Contractor shall have an out-processing checklist that identifies the Government issued CAC card and Installation Access Pass has been turned in to the COR and property items accounted for and back in proper custody. A signature shall be required on the checklist from the appropriate person acknowledging receipt of the items. Checklists shall be retained for the duration of the contract.
2.5.1.7 Departing Employees. The Contractor shall ensure Contractor employees return security photographic identification cards, permits, CAC, GFP, keys, photo passes, range passes, sensor access (slide) cards and that access to the LAN email has been canceled. All out-processing Contractor employee CACs must be returned to the COR no later than close of business on the last workday. A formal termination or departing memo must be submitted to the COR and security office with the requested items stating they have been collected.
2.5.1.8 Key Control. The Contractor shall establish a control system to ensure no keys issued to the Contractor by the Government are lost, misplaced, or used by unauthorized persons. Government keys shall not be duplicated by the Contractor without the COR's authorization. Procedures developed to control Government keys shall be included in the Contractor's QCP. The Contractor shall comply with AR 190-13 The Army Physical Security Program and AR 190-51 Security of Unclassified Army Property (Sensitive and Non-sensitive, applicable to key and lock).
2.5.2 Security Training.
2.5.2.1 iWATCH Training. The Contractor shall brief the local iWATCH program (training standards provided by the USAG Humphrey’s Anti-Terrorism Officer (ATO) to all of the Contractor’s employees and associated Subcontractors. This training is used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. The Contractor shall complete the training within thirty (30) calendar days of contract award and within five (5) calendar days of new employees commencing performance with the results reported to the COR NLT thirty (30) calendar days after contract award.
2.5.2.2 Anti-Terrorism (AT) Level 1 Awareness Training. All Contractor employees, to include Subcontractor employees, requiring access to the USAG Humphreys Installation, facilities and controlled access areas shall complete AT Level I awareness training within thirty (30) calendar days of contract start date and within five (5) calendar days of new employees commencing performance and send to the COR via both electronic and paper copy. The Contractor shall complete the training within thirty (30) calendar days of contract award AT level I awareness training is available at the following website: http://jko.jten.mil.
2.5.2.3 Operational Security (OPSEC) Awareness Training. IAW AR 530-1, Operations Security, Contractor employees shall complete Level I OPSEC Awareness training within thirty (30) calendar days of contract award and send to the COR via both electronic and paper copies. All Contractor personnel shall complete Level I OPSEC Awareness training annually. Level I OPSEC training is available at the following website:
https://securityawareness.usalearning.gov/opsec/index.html.
2.5.2.3.1 All Contractor employees must complete the DoD Cybersecurity Awareness Training before issuance of network access and annually thereafter (Deliverable 005, IA Awareness Training). Upon completion of training, the Contractor shall submit training certificates to the COR.
2.5.3 Safety. The Contractor shall safeguard and maintain all Government and Contractor property, as well as provide for the safety and well-being of personnel employed under this contract. The Contractor shall comply with AR 385-10, The Army Safety and Occupational Health Program. All Contractor employees shall wear a reflective vest or suitable substitute while working during darkness hours. Contractor shall be responsible for any injury to any Contractor’s representative, or others, as well as for any damage to any personal or public property that occurs during the performance of this contract that is caused by the Contractor’s fault or negligence.
2.5.3.1 Safety Plan. The Contractor shall develop and implement a safety program for its employees. The Contractor shall submit the Safety Plan to the KO and Garrison Safety Office for review and acceptance within ten
(10) days of commencement of work. Revisions shall be submitted five (5) calendar days prior to the effective date of change.
2.5.3.2 Occupational Safety and Health Administration (OSHA). The Contractor shall comply with the OSHA standards. The Contractor shall comply with all applicable Federal, State, and Local Laws, Regulations, and Directives. If the Contractor fails or refuses to comply promptly with safety requirements, the Government may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to any such order shall be made the subject of claim for extension of time or for excess costs or damages to/by the Contractor. The Contractor shall be responsible for enforcement of all safety requirements by the Contractor and his Subcontractors/teaming partners and/or joint venture partners.
2.5.3.3 Hot Work Permit.
A Hot Work Permit is required any time heat producing devices are used and shall be issued by the Fire Department prior to ANY work being started.
Example, welding, grinding, cutting, brazing, etc.
Hot Work Permits will be closed by the Fire Department, after hot-work is completed, and before personnel responsible for the work clears the job site.
2.5.4 Training, Physical Requirements, or other Expertise Required.
2.5.4.1 Certification and Licensure. The Contractor shall ensure all Contractor’s employees and associated Subcontractors are certified or licensed in the specific areas required by the Republic of Korea. The Contractor shall ensure employees are certified or licensed in the appropriate Environmental Protection Agency (EPA) areas required. The Contractor shall ensure all required documentation of certification or licensure for Contractor personnel are filed with the COR within twenty-four (24) hours prior to employees commencing performance.
2.5.5 Environmental Requirements.
2.5.5.1 Green Procurement. Section 6002 of the Resource Conservation and Recovery Act of 1976 (RCRA) requires the use of recycled and recovered products identified in the EPA’s Comprehensive Procurement Guidelines.
2.5.5.2 The Contractor shall use these recycled or recovered products unless they cannot be procured within a reasonable period of time not to exceed seven (7) calendar days; at prices not to exceed five (5) percent of prevailing rates; or the product(s) does not meet technical or performance standards. EPA Guidelines are the minimum requirement. The Contractor shall use materials and products commonly used in industry. The Contractor shall maintain records and submit an annual report to the COR, along with the annual certification required by FAR 52.223-9 (Certification and Estimate of Percentage of Recovered Material Content for EPA Designated Items), upon completion of the base year and each option year.
2.5.5.3 Environmental Compliance. The Contractor shall comply with all Federal, State, Local, and Installation Environmental Laws, Rules, Plans, and Policies. The Contractor shall use and store all materials, chemicals, and equipment used in the performance of services on the Installation IAW with Industry Standards, Local, State and Federal Laws. The Contractor shall be financially responsible for all fines and associated costs for hazardous waste management, transportation, and disposal of waste due to the Contractor's non-compliance. The Contractor shall submit Safety Data Sheets (SDS) for approval on all materials, five (5) days before delivery of the material, to the COR. The Contractor shall provide upon request from the COR all required data to meet environmental-mandated reporting requirements (e.g., air emission data, hazardous material storage/usage, herbicide/pesticide usage, solid/hazardous waste generation). The Contractor shall provide data to meet reporting deadlines and during compliance inspections upon request from the COR.
2.5.5.4 Spill Plan. The Contractor shall notify the COR within one (1) hour, if the Contractor spills or releases any hazardous substances, i.e., substances listed in 40 CFR 302, Designation, Reportable Quantities, and Notification. The Contractor shall submit a Spill Plan to the KO for approval within thirty (30) calendar days of contract award IAW Spill Prevention Control and Countermeasure Plan.
2.5.6 Contingency Plans.
2.5.6.1 General. The Contractor shall establish, maintain, and implement contingency plans for mobilization, disaster, and labor dispute contingencies. The plans shall assume no Government support to the Contractor workforce. The Contractor shall, within thirty (30) calendar days of contract award, designate in writing a single contact Designated Contingency Coordinator (DCC) within the Contractor’s organization. The DCC shall participate and coordinate with the Installation contingency and mobilization planning activities. The DCC shall participate in the Installation mobilization planning and execution conferences; and shall modify and maintain appropriate Contractor contingency plans to compliment or enhance corresponding Installation plans. The Contractor shall submit all plans to the KO for approval.
2.5.6.2 Mobilization Contingency Plan. N/A
2.5.6.3 Disaster Contingency Plan. N/A
2.5.6.4 Labor Dispute Contingency Plan. N/A
2.5.6.5 Plan Updates. N/A
3.0 Performance Requirements and Standards.
3.1 Performance Task Requirements, Standards and Acceptable Quality Levels (AQLs).
3.2 Quality Assurance (QA). The Government will evaluate the Contractor’s performance under the contract IAW the Government’s Quality Assurance Surveillance Plan (QASP). QASPs are considered to be "living documents," dynamic, adaptable, and subject to modification based on Contractor performance surveillance results. The QASP is not part of the PWS and will not be issued with the solicitation. The QASP focuses on the procedures and processes the Government will implement to assure the Contractor is performing IAW the performance standards within the PWS. The Government plan defines the criteria of how the Contractor’s performance will be evaluated, the frequency of surveillance, and the items to be inspected. Although the Government will develop a QASP, Government surveillance of Contractor performance is not limited to the QASP, or the performance objectives, outlined in the Performance Requirements Summary (PRS). The Government retains the right to evaluate all services required by the contract. The Government will perform inspections and tests in a manner that will not unduly delay the work. If any of the services performed do not conform to contract requirements, the Contractor shall perform the services again at no additional cost to the Government.
3.3 Quality Control Plan (QCP). Quality control is the responsibility of the Contractor. The Contractor shall develop, implement, and maintain an effective quality control program which shall be documented in a QCP to ensure services are performed IAW this PWS. The Contractor shall develop and implement procedures to identify and prevent the recurrence of defective services. The Contractor’s QCP is the means by which they assure themselves that the work conforms to contract requirements. The basic principle of the plan is that the Contractor is responsible for quality control. The QCP shall be constructed in such a manner that each service can be extracted and used for that function only and not contain extraneous information. The Contractor's QCP shall include a separate section, which addresses the Contractor's method of managing quality of work. The QCP shall include a description of the inspection system to address services listed in this PWS, and a description of the methods to be used for identifying and preventing defects in the quality of services performed. The plan shall include a description of the Contractor’s inspection system to include specifics as to areas to be inspected on a scheduled and unscheduled basis, frequency of inspections, and the title and organizational placement of the Contractor’s inspectors. No lead person or first line supervisor shall be considered a Quality Control Inspector.
The Contractor shall develop, maintain, and submit a QCP to the KO for acceptance within thirty (30) calendar days after the contract is awarded. The Contractor shall submit any proposed changes in the QCP to the KO for written approval five (5) working days prior to implementation.
3.4 Quality Control Files. The Contractor shall maintain files of all inspections or tests conducted by the Contractor, to include any corrective actions taken. These files shall be subject to Government review at the COR’s discretion during the contract term, to include any extensions of contract term. The Quality Control Files will be the property of the Government and shall be turned over to the Government upon completion or termination of the contract.
3.5 Customer Feedback Program. The Contractor shall establish and operate a customer feedback program as part of the QCP. Performance Requirements Summary (PRS) Matrix.
4.0 Performance Requirements Summary (PRS) Matrix.
The contractor service requirements are summarized into performance objectives related to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.
Required Services
Performance Standard
Acceptable Quality Level
(AQL)
Method of
Surveillance Incentive (Positive and/or Negative)
#1. Dispose Trash and hazardous waste
The contractor shall perform IAW PWS Para 8.2.3
Zero Deviation from Performance
100% Inspection
Re-Perform within one (1) week after notification from the COR
#2. Overhaul Chillers The contractor shall perform IAW PWS Para 8.3
Zero % Deviation from Performance Standard
Periodic Surveillance/ Random Sampling day after notification from the COR
#3. Chemical Cleaning and descale condenser part of chillers
The contractor shall perform IAW PWS Para 8.3.1
Zero % Deviation from Performance Standard
Periodic Surveillance/ Random Sampling
Re-Perform within one (1)
#4. Overhaul Cooling Towers
The contractor shall perform IAW PWS Para 8.4
Zero % Deviation from Performance
100% Inspection
#5. Operation Test The contractor shall perform IAW PWS Para 8.5
Zero % Deviation from Performance Standard
Periodic Surveillance/ Random Sampling
Re-Perform within one (1)
5.0 Common Levels of Service.
The Contractor shall provide overall management, supervision, personnel, labor, generalized or specialized equipment necessary to maintain, repair, operate, and perform all the service functions of the Base Operations specified below. This shall be done IAW all the Terms, Conditions, General and Special Provisions, Specifications, Drawings, Attachments, and Exhibits contained herein or incorporated by reference.
The Contractor shall ensure that all work meets or exceeds the specifications for the listed service.
SERVICE Service Title Annex No.
411 Facility Maintenance - Vertical Annex A
6.0 Deliverables.
DELIVERABLE FREQUENCY # OF
COPIES
MEDIUM/FORMAT DISTRIBUTION
A001 (PWS, para. 2.1.11.1) Changes in Key Personnel
Fill the position within 15 days of vacancy with individual that meets or exceeds the requirements
Electronic Copy
MS Word KO
A002 (PWS, para. 2.5.1.3) Contractor Vehicles Registration
Register vehicles within seven (7) working days of contract start
Coordinate with Provost Marshal Vehicle Registration Section.
COR
A003 (PWS, para. 2.5.2.1) iWATCH Training Report
Initial: within 30 days after contract award
New Employee: Five
(5) Calendar days of
Electronic Copy
Portable Document Format (Pdf) with CM’s Signature
COR/ACOR
new employees commencing performance
A004 (PWS, para.2.5.2.2) AT Level I Training
Initial: within 30 days after contract started
Electronic Copy
Portable Document Format (Pdf)
COR/ACOR
A005 (PWS, Para 2.5.2.3) OPSEC Training
Within thirty (30) days after 30 calendar days after contract started.
Electronic Copy
Portable Document Format (Pdf) with CM’s Signature
COR/ACOR
A006 (PWS, para. 2.5.3.1) Safety Plan
Within ten (10) days of commencement of work.
Revision: five (5) calendar days prior to effective date of change
Portable Document Format
A007 (PWS, para. 2.5.5.4) Spill Prevention Plan.
Submit within thirty
(30) days after contract award.
Electronic Copy
A008 (PWS, Para. 3.3) Quality Control Plan
Within thirty (30) Calendar days after contract started.
Changed: Five (5) Working days prior to implementation.
Electronic Copy
A009 (PWS, Para. 8.2.1) Overhaul Schedule
Submit no later than ten (10) calendar days after contract award.
A010 (PWS, Para. 8.6) Equipment Plan
Submit within thirty
(30) calendar days after contract award.
A011 (PWS, Para. 8.8) Completion Report
Within two (2) working days after completing the overhaul
Electronic Copy
KO
7.0 Related Documents.
7.1 Definitions and Acronyms.
7.1.1 Definitions.
7.1.1.1 Acceptable Quality Level (AQL). The AQL is the maximum percent defective (or the number of defects per hundred units) for the purposes of sampling inspection can be considered satisfactory.
7.1.1.2 Alternate Contracting Officer’s Representative (ACOR). An employee of the U.S. Government provided by the RA and appointed by the KO to provide support to CORs in monitoring and documenting the Contractor’s performance.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .