W91QVN21R0031

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

1. The purpose of this amendment is to provide response to questions received from the offeror. The Question (Q) and Response (R) are as follows:

Q1. If you have an existing contract, please provide the solicitation number and further information. If there was no same contract, I would like to know of any similar contract which can be referenced.

R1. This is a new requirement so there is no existing contract. Appliance repair service contract is similar requirement with this contract.

Q2. How many Technicians does this contract need? Please provide an estimated number of Technicians, even if it's not the exact number.

R2. The Government will not specify the number of technicians required to perform the service. The Contractor shall provide a sufficient number of technicians who can meet the contractual demand at 20 different sites on time.

Q3. Do you have any On-call service record regarding this maintenance service? and can you share that information with us?

R3. Number of On-call services for recent (1) year: 234 each (LRC-North), 121 each (AFSBn-Korea), 13 each (LRC-Daegu)

Q4. Do you require each CM/SM/Technician to stay on each site(camp) during the regular work hours everyday?

R4. No. Refer to the Para. 1.7.3. and Para. 5. of the PWS for the response time, work hours and schedule. The contractor shall provide sufficient man power to meet requirements IAW para 1.7.3. and para 5. of the PWS.

Q5. Should all technicians have each of the above certifications?

R5. No. At least, every single technician shall possess one of the listed licenses. Overall, the contractor shall provide the four (4) different type licensed technicians to perform the service.

Q6. Will office/workspace be provided at each site office location?

R6. No. Workspace is where the PM/repair take place. Government will not provide office/Work space.

Q7. How many technicians should we have at each site?

R7. Refer to the R2 of this page.

Q8. Price in KW?

R8. Refer to the page 3 of the solicitation; “All offerors interested in competing for this requirement are required to submit their price proposal in Korean Won (KW) only. A proposal submitted in currency other than Korean Won will not be considered for award.”

2. All other terms and conditions remain unchanged.

SUMMARY OF CHANGES

(End of Summary of Changes) image1.wmf