W91QVN-17-R-0060_Construction_Solicitation.pdf
PDF 367 KB Posted
- Attached to
- Repair Underground Eletric Main Power Line
- Solicitation number
- W91QVN-17-R-0060
About this file
Construction Solicitation W91QVN-17-R-0060
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A3_Submittal_Register.xls | XLS spreadsheet | |
| A2_Drawings.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W90YG37342N001
This is a Non-Work Plan Task Order for the follow ing MA IDIQ General Construction Contractors only: Contract No. W91QVN-14-D-0031, 0032, 0033, 0035, 0036, 0037, 0038, 0039, 0040, 0041, 0044, 0045, 0046, 0047, 0048, 0049, and 0050.
MS. LEE, ANNA WSW (02) 7914-6565
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
24-Mar-2017
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________150 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
YES X NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________10 Apr 2017 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______180 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
411TH CSB, KOREA - IMB
UNIT#15289
APO AP 96205
W91QVN
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
03:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: 724-6977 TEL: FAX:
W91QVN-17-R-0060 25
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W91QVN-17-R-0060
Section A - Solicitation/Contract Form
LCS NOTICE
LCS PROJECT NOTICE AND REQUIRED DOCUMENTS
This solicitation is being conducted under the Logistics Cost Sharing (LCS) program and will result in a contract between the Government of the Republic of Korea and the contractor. ROK will directly pay the contractor. No appropriated funds of the United States shall be obligated for payment due under this contract.
In accordance with the International Agreement between the United States and the Republic of Korea, titled “Amendment to the Implementing Agreement between the United States Forces Korea and the Republic of Korea Ministry of National Defense Concerning Logistics Cost Sharing” (hereinafter “International Agreement”), signed by the parties on 14 October 2015:
"The parties hereby agree that all LCS work must be accomplished in the ROK or its territorial waters and that all equipment and supplies that are to be acquired with ROK Government funds shall be manufactured in the ROK, and all LCS service work shall be carried out by Korean contractor(s), the Korea Railroad Corporation, or the ROK military. The term ‘Korean contractor(s)’ is defined as an entity, that, including its parent, is a domestic corporation under the Korean Tax Act and whose domestic status is recorded in the Certified Copy of Register or its successor document. A parent is defined as an entity that holds more than 50/100 of the total issued and outstanding shares in another company, as reflected in the Stock Change Certificate.”
In order to establish eligibility to receive the award of this LCS contract, offerors shall submit the three documents listed below with their proposal prior to the closing date/time established in the solicitation. The contracting officer will determine the offeror’s status as a Korean contractor solely on the basis of the documents listed below.
1) The offeror's most recent Stock Change Certificate (주식등변동 상황명세서), as certified and submitted to the ROK Local Tax Office (국세청),
2) The offeror's Certified Copy of Register [등기부 등본 (유효사항)], as certified and submitted to the ROK Supreme Court (대법원), and
3) If the offeror has a Parent (as Parent is defined in the International
Agreement), the Parent's Certified Copy of Register [등기부등본 (유효사항)], as certified and submitted to the ROK Supreme Court (대법원).
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job
(K) Repair Underground Main Power Line
FFP
Repair Damaged Underground Main Power Lines. Replace damaged 22.9KV Underground Main Power Distribution Cable at Camp Carroll.
Work Class: K
See Statement of Work (SOW).
FOB: Destination
PURCHASE REQUEST NUMBER: W90YG37342N001
NET AMT
0002 1 Job
(L) Repair Underground Main Power Line
FFP
Repair Damaged Underground Main Power Lines. Replace damaged 22.9KV Underground Main Power Distribution Cable at Camp Carroll.
Work Class: L
See Statement of Work (SOW).
0003 1 Job Estimated Cost for War Hazard
FFP
IS ZERO (0).
Section C - Descriptions and Specifications
STATEMENT OF WORK
STATEMENT OF WORK
PROJECT NO TITLE LOCATION
HS-00517-5J Replace Damaged 22.9KV Underground Main Distribution Cable Camp Carroll
DESCRIPTION: The work to be performed for completion of this project shall be in general as described below:
a. Work by Contractor:
(1) The contractor shall provide all labor, tools, equipment, supplies and any other resources necessary to accomplish the scope of work contained herein as indicated in the drawings the specifications.
(2) The contractor shall replace damaged 22.9kv underground main distribution cable, Camp Carroll in accordance with the specifications and drawings.
b. Work by In-House Labor: Not applicable to this project.
c. Work by Troop Labor: Not applicable to this project.
(3) Performance Period: Shall be 150 calendar days after Notice to Proceed (NTP) is issued.
PRINCIPAL FEATURES: This project shall include for, but not limited to the following:
General Services:
The contractor shall submit completed material lists and shop drawings to DPW, Engineering Division, Design & Technical Review Branch for approval prior to commencement of work at the jobsite.
Schedule #I, Construction (L): All work shall be in accordance with the attached drawings and specifications.
A. Civil Work
Near Bldg. #622
1. Install concrete protection slab.
Near Bldg. #676
1. Construct concrete retaining wall and handrail.
2. Install guard posts.
Near Bldg. #323
1. Install concrete protection slab.
B. Electrical Work
1. Install new cable junction pedestal (GFM) including 25kv distribution cable, concrete encasement duct, splice kit and necessary associated accessories.
Schedule #II, Repair (K): All work shall be in accordance with the attached drawings and specifications.
A. Civil Work
Near Bldg. #622
1. Remove/replace existing asphalt concrete pavement, base course and subbase course.
2. Remove/replace existing steel grating covered concrete ditch with new steel grating covered concrete ditch.
3. Remove/replace existing drain line with new drain line.
Near Bldg. #676
1. Remove/replace existing asphalt concrete pavement, base course and subbase course.
2. Remove/replace existing water line including necessary fittings and accessories. (GFM: Coupling Adapter)
3. Trim existing trees.
Near Bldg. #323
1. Remove/replace existing asphalt concrete pavement, base course and subbase course.
2. Remove/replace existing water line including necessary fittings and accessories. (GFM: Coupling Adapter)
3. Relocate existing movable digital sign board.
B. Electrical Work
1. Replace existing deteriorated 22.9kv underground main distribution line with new including duct & manhole cleaning and associated accessories.
2. Replace deteriorated existing protection & monitoring equipment including relays, control wires, doors, space heaters and associated accessories at each switch station.
3. Provide operation test & adjust, repair at each switching stations including metering outfit, switchgears, vacuum circuit breakers, distribution lines, equipments and high voltage accessories.
TECHNICAL PROVISIONS - II
TECHNICAL DETAIL SPECIFICATIONS
GENERAL: The specifications are from the "Standard Technical Specifications for O&MA Projects, Korea", dated 30 October 2015, issued by the Department of the Army, Installation Management Command. The most current specifications are available (for referral purposes only) on the USFK’s Web Page http://www.usfk.mil/Resources/ContractingwithUSFK.aspx. The electronic version of the specifications are Acrobat® PDF format and can be read with the Acrobat Reader® software.
TECHNICAL PROVISIONS - III
SPECIAL CONDITIONS
1. GENERAL: In addition to the requirements specified under "GENERAL PROVISIONS" for the Fixed Price Construction Contract for this project, the Contractor shall comply with the following "SPECIAL CONDITIONS" which form a part of the contract.
2. WORK HOURS: The work will be accomplished from 0730 hours through 1730 hours (Monday through Saturday) except for Korean Legal Holidays. Any proposed change in working hours should be approved by the Contracting Officer (KO) and Contracting Officer's Representative (COR).
3. NOTIFICATION OF INSPECTION SECTION: The contractor shall also give the project inspector seven (7) working days notice prior to each concrete placement, field test, weld application, protective coating application, or any other work deemed to require inspection.
4. COORDINATION: The contractor shall coordinate his work with all others (subcontractor and government agencies) involved in this project and shall cooperate with all other contractors and government agencies so as to facilitate the general progress of the work. Before proceeding with any work, the contractor and/or subcontractor shall consult applicable drawings and specifications for each trade involved.
5. CONSTRUCTION: The contractor shall submit a request for the construction permit at least ten (10) working days prior to the starting of work. The request shall be submitted to the COR for approval.
6. MATERIALS COMPLIANCE: The contractor shall make certain all materials used meet the requirements of the contract and proof thereof upon request of the COR. Materials not meeting the requirements of the contract shall not be brought to the job site. All materials shall be new and the standard products of a manufacturer regularly engaged in the manufacturing of such materials.
7. HOISTING AND MOVING EQUIPMENT: The Contractor and each subcontractor shall provide and be responsible for all cranes, lifts, etc., necessary for the proper and efficient movement of materials. The equipment shall be provided with proper guys, bracing, safety devices, etc., as required by law.
8. EQUIPMENT: All contractor equipment shall be subject to functional and safety inspection by the COR.
Equipment not completely safe or functional shall be repaired before work is started.
9. RECORD DRAWINGS: During performance of work, the contractor shall accurately record and delineate on a set of full-size blue line prints of contract drawings all changes in such work which constitute departures from the original contract drawings. The set of drawings (one original and one blue line print), thus corrected and changed, usually referred to as “As-Built Drawings”, shall be delivered to the COR at the final acceptance/inspection of the completed work by the Government.
10. US ORIGIN MATERIALS: If applicable, all US Origin Materials will be ordered immediately after Notice to Proceed.
11. RELEASE OF FACILITIES WITH U.S. ORIGIN MATERIALS: If applicable, Building/facility will not be released to the contractor by the COR until all U.S. origin building construction supplies are available or due within such a time frame that there will be no delay in project completion.
12. UTILITY CUTOVERS AND INTERRUPTIONS: Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and U. S. Government holidays. Conform to procedures required in the paragraph "Work Outside Regular Hours." Ensure that new utility lines are complete, except for the connection, before interrupting existing service. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, shall be considered utility cutovers pursuant to the paragraph entitled "Work Outside Regular Hours." Such interruption shall be limited to 4 hours. This time includes for deactivation and reactivation.
13. WORK OUTSIDE REGULAR HOURS: Work outside regular working hours requires Contracting Officer approval. Make application 14 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During the period of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours on Saturdays, Sundays, and U. S. Government holidays unless directed otherwise.
14. WINTERIZATION: The contractor may be required to perform the work during the winter season, which may cause the contractor for additional cost. These additional costs are the contractor’s responsibility in the event of working during this period. The Contractor shall reflect these costs in the preparation of his proposal.
15. SAFETY: The safety plan must be approved before any work can be performed on this contract. Hard hats, suitable work boots and other necessary personnel protective gear are mandatory. Contractors are required to get a written permission from safety office (POC: Mr. To, Pong Uk, DSN: 768-8971) and fire & Emergency Service (POC: Fire Communication office, DSN: 768-4120) prior to enter confined spaces (i.e. manholes). Contractors should be properly trained and equipped with PPEs, calibrated air monitoring instrument, to work at confined spaces to insure compliance with OSHA (Occupational Safety and Health Administration) 29 CFR 1910.146.
16. SECURITY: All prime contractor and subcontractor personnel will be required to obtain a station pass from the Base Security Office. It is the prime contractor’s responsibility to supply information to security regarding all prime and subcontractor personnel and a list of all vehicles that will be driven on the site.
17. WARRANTY: The contractor shall be responsible for remedy of failure in government contract during the one
(1) year warranty time. The contractor shall be refurnishing services or/and repair and replacement for remedy. The one (1) year warranty starts the day after final inspection approval from the authorized personnel.
18. Environmental Management System (EMS): Recycling all eligible material, including glass, paper (including magazines), plastic, aluminum, and cardboard to the maximum extent practicable;
Reducing the amount of hazardous material and/or solvent used by purchasing fewer hazardous materials and by increasing the use of products with recycled content;
Reducing the amount of solid waste from construction and demolition debris, and scrap metal sent to municipal and rubble landfills by reducing, reusing, and recycling;
Conserving energy and water usage by turning off lights and equipment when not in use and using only the necessary amount of water needed to complete the required tasks. Continuous conservation of our natural resources is a must;
19. Contamination find clause: When contaminated soil is encountered during excavation work, contractor shall report the findings to the Environmental Office immediately and contractor will segregate contaminated soil from clean soil.
20. Inadvertent find clause: When potential cultural or historic items are inadvertently found during construction activities, contractor shall cease activities in the vicinity of the discovery and report the findings to the Environmental Office immediately. (Reference: USFK Reg 201-1, Environmental Governing Standard (EGS) Ch.
12, Para 12-3 J)
21. Fuel Tank and Lines: If applicable, when underground piping associated with POL storage containers shall be tested for integrity and leaks at the time of installation, modification, construction, relocation, or replacement. New underground piping must be protected against corrosion IAW recognized industry standards. (Reference: USFK Reg 201-1, Environmental Governing Standard (EGS) Ch. 9, Para 9-3.b.(5))
22. Non-PCB transformer certification: If applicable, before contractor replace/install any transformer at USAG Daegu, contractor shall submit two copies of non-PCB transformer certification to COR for each to be installed transformer. New transformer will be installed after COR's approval for non-PCB transformer certification for each to be installed transformer.
Section F - Deliveries or Performance
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 150 calendar days after Notice to Proceed (NTP). The time stated for completion shall include final cleanup of the premises.
(End of clause)
Section H - Special Contract Requirements
AT/OPSEC
ANTITERRORISM/OPRATIONS SECURITY REQUIREMENTS.
1. AT Level 1 Training: This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 05 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil.
2. Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 05 calendar days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil
3. For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
4. iWATCH Training. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 05 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.
Section I - Contract Clauses
5152.232-4028 – Funding of ROK MND Contracts
FUNDING OF ROK MND CONTRACTS
(a) This is a contract between the Government of the Republic of Korea (ROK) and the contractor. ROK will directly pay the contractor. No appropriated funds of the United States (US) shall be obligated for payment due under this contract.
(b) Funding advisement: This contract, any modifications (including exercise of option(s)) thereto, and any delivery or task orders thereunder, shall be paid with ROK funds and shall cite “MOA Contract - funded by ROK MND” (in lieu of citing appropriations and accounting data). No U.S. funds, appropriated or other, are or will be obligated under this contract.
(c) Limitation of US liability: The U.S. Government shall incur no liability, and no appropriated or other funds of the United States shall be obligated, for payment for services, supplies, claims, or other costs arising out of or under this contracts, delivery or service orders, exercises of options, or other modifications.
(d) Identification of invoices: Contractor shall state clearly “MOA Contract - funded by ROK MND” on all invoices for performance under contracts, delivery or service orders that are designated as “MOA Contract - funded by ROK
MND.”
(e) Funding carry-over:
(1) The Contractor will make every reasonable effort to obtain completion of all performance under the contract and to obtain, approve, and forward Contractor’s invoices under the contract before the end of the calendar year of the contract. In the event that any work initiated under the contract cannot be completed by the end of the calendar year, the Contractor shall furnish the Contracting Officer and USFK, ATTN: FKJ4-P-G, not later than 30 November, the following information:
(i) A list of work that apparently will not be completed and invoiced by, and apparently will require payments after, the end of the calendar year;
(ii) Estimated price of work that apparently will be carried beyond the calendar year; and
(iii) Date of anticipated completion of the work.
(2) The ROK MND shall seek mutually agreeable procedures for payment for work carried over to the next calendar year.
(f) Availability of ROK Funds for the Next Calendar Year:
(1) This contract is funded with calendar year ROK MND funds, from date of award through 31 December of the year in which the contract is awarded and/or into which the contract is extended. ROK MND funds are not available for performance, under this contract, beyond 31 December of the current contract’s calendar year period. Any obligation and/or legal liability on the part of ROK MND for the next calendar year’s performance, including exercise of any option to extend the services/contract, is contingent upon the Contracting Officer’s explicit notification to the Contractor of availability of that new calendar year’s ROK MND funds, from which contractual payment(s) can be made.
(2) Unavailability of ROK MND funds until a few months into the new calendar year may necessitate a break in performance of the contract until those funds become available. In the event of a break in performance because of unavailability of the new calendar year’s ROK MND funds for obligation under the contract, that break in performance shall not be deemed a breach or default of the contract.
5152.232-4030 – Payments of ROK MND Contracts
PAYMENTS OF ROK MND CONTRACTS
(a) Responsibility for Payment: The ROK Government shall make payment directly to the contractor for performance rendered and accepted under any contract part, or delivery or service order identified as “MOA contract
– funded by ROK MND.” Payments shall be made at the prices specified in the contract.
(b) Performance Certification and Contract Administration: The U.S. Government has sole authority to administer this contract. The U.S. Government, through its designated USFK official(s), has sole authority to inspect and accept goods and services and to determine the Contractor’s entitlement to payment from the ROK under this contract. The administering U.S. Government Contracting Officer will resolve all disputes, claims, and appeals before certifying invoices for payment. Neither ROK MND nor ROK Defense Logistics Agency will pay any invoice or claim under this contract without prior U.S. Government certification of the invoice.
(c) Payment for Partial Deliveries: Unless otherwise specified in this contract, payment shall be made on partial deliveries accepted by the U.S. Government, if (1) the amount due on the deliveries warrants it, or (2) the Contractor requests it and the amount due on the deliveries is at least either the local currency equivalent of $1,000.00 or 50% of the total contract price.
(d) Invoices: An invoice is a written request for payment for supplies rendered. In order to be proper, an invoice must include as applicable the following:
(1) Invoice date;
(2) Name and address of contractor;
(3) Contract number or other authorization for supplies delivered or service performed (including order number and contract line item number);
(4) Description, quantity, unit of measure, unit price and extended price of supplies delivered or services performed;
(5) Shipping and payment terms (e.g. shipment number and date of shipment, prompt payment discount terms). Bill of lading number and weight of shipment will be shown for shipments on Government bills of lading;
(6) Name and address to which payment is to be sent (which must be the same as that in the contract or on a proper notice of assignment);
(7) Name, title, phone number and mailing address of person to be notified in event of a defective invoice; and
(8) Any other information or documentation required by other provisions of the contract (such as evidence of shipment).
(9) Invoices shall be prepared and submitted in five (5) copies (one copy of the invoice shall be marked “Original”) unless otherwise specified.
(e) Procedures for Payment by ROK MND:
(1) The Contractor shall forward to the Contracting Officer’s Representative (COR), for certification of inspection and acceptance, all invoices in five (5) copies.
(2) If the contractor doesn’t receive payment within 35 days of the government’s receipt of the invoices, the contractor should contact the COR.
(f) Payment Addresses:
ROK Ministry of National Defense Defense Logistics Agency (DLA) Seoul, Korea
5152.233-4008 – Choice of Law and Disputes under ROK MND Contracts
CHOICE OF LAW AND DISPUTES, ROK MND CONTRACTS
(a) This contract shall be construed and interpreted in accordance with the substantive laws of the United States of America. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal, or action arising under or relating to this contract shall be a dispute to be resolved in accordance with U.S.
law.
(b) All disputes arising under, or relating to, this contract shall be resolved under this clause.
(c) “Claim,” as used in this clause, means a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to this contract. A claim arising under a contract, unlike a claim relating to that contract, is a claim that can be resolved under a contract clause that provides for the relief sought by the claimant; however, a written demand or written assertion by the Contractor seeking the payment of money exceeding $100,000 is not a claim under the clause until certified as required by subparagraph (e)(2) below. A voucher, invoice, or other routine request for payment that is not in dispute when submitted is not a claim under the clause. The submission may be converted to a claim under the clause, by complying with the submission and certification requirements of this clause, if it is disputed either as to liability or amount or is not acted upon in a reasonable time.
(d) The contractor shall have the right to submit to the Contracting Officer, disputes, demands, and/or claims, relating to or arising under this contract, only on the issue of whether the Government should and will certify performance, for payment by the ROK Government. The contractor shall not submit to the U.S. Government, nor will the Contracting Officer accept, any disputes, demands, or claims for compensation for work, which the U.S.
Government has certified as completed.
(e) Procedures
(1) A claim by the contractor shall be made in writing and submitted to the Contracting Officer for a written decision. A claim by the Government against the Contractor shall be subject to a decision by the Contracting Officer.
(2) For contractor’s claims exceeding $100,000, the contractor shall submit with the claim a certification that –
(i) The claim is made in good faith;
(ii) Supporting data are accurate and complete to the best of the contractor's knowledge and belief; and
(iii) The amount requested accurately reflects the contract adjustment for which the contractor believes the Government is liable.
(3) Individuals
(i) If the contractor is an individual, the certification shall be executed by that individual.
(ii) If the contractor is not an individual, the certification shall be executed by –
(A) A senior company official in charge at the contractor's plant or location involved; or
(B) An officer or general partner of the contractor having overall responsibility for the conduct of the contractor's affairs.
(f) For contractor’s claims of $100,000 or less, the Contracting Officer will, if requested in writing by the contractor, render a decision within 60 days of the request. For contractor-certified claims over $100,000, the Contracting Officer will, within 60 days, decide the claim or notify the contractor of the date by which the decision will be made.
(g) The Contracting Officer's decision shall be final unless the contractor appeals the decision within 30 days of the Contracting Officer's decision, to the Principal Assistant Responsible for Contracting (PARC). In the event that the contractor does appeal the decision of the Contracting Officer, the appeal shall be heard by and decided by the PARC and/or a panel of U.S. officials, chaired by the PARC. The decision of this panel shall be final, and the parties agree that there are no additional appeal rights. The parties waive their rights to pursue any claim, appeal, or action arising from or relating to this contract, before any other civil court, board, authority, or other adjudicative body.
(h) The contractor shall proceed diligently with performance of this contract, pending final resolution of any request for relief, claim, or action arising under the contract, and comply with any decision of the Contracting Officer.
(i) This contract is not subject to the Contract Disputes Act of 1978, as amended (41 U.S. Code, Sections 601-613).
Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal, or action arising under or relating to this contract shall be a dispute to be resolved only in accordance with this local clause, 5152.233-4008.
Section J - List of Documents, Exhibits and Other Attachments
LIST OF APPLICABLE DRAWINGS
LIST OF APPLICABLE CONTRACT DRAWINGS
GENERAL: The work shall conform to the standard detail drawings (dated 30 November 2015, issued by the Department of the Army, Installation Management Agency, Korea Region Office and located USFK’s Web Page http://www.usfk.mil/Resources/ContractingwithUSFK.aspx), all of which form a part of the specifications.
Drawing No. Sheet No. Ref. No. Description Date
D-16-18 1 of 1 R-1 Title Sheet 21 Sep 16
“ 1 of 19 C-1 Location Plan “
“ 2 of 19 C-2 Site Layout Plan-1 “
“ 3 of 19 C-3 Site Layout Plan-2 “
“ 4 of 19 C-4 Site Layout Plan-3 “
“ 5 of 19 C-5 Section and Details “
“ 6 of 19 C-6 Section and Details ”
“ 7 of 19 E-1 Legend, Notes and Scope of Work “
“ 8 of 19 E-2 Electrical Distribution Plan – 1 “
“ 9 of 19 E-3 Electrical Distribution Plan – 2 “
“ 10 of 19 E-4 Electrical Distribution Plan – 3 “
“ 11 of 19 E-5 Electrical Distribution Plan – 4 “
“ 12 of 19 E-6 Electrical Distribution Plan – 5 “
“ 13 of 19 E-7 Electrical Distribution Plan – 6 “
“ 14 of 19 E-8 22.9kv Switching Station No.1 and Pad MTD Junction Details “
“ 15 of 19 E-9 22.9kv Switching Station No.2 “
“ 16 of 19 E-10 22.9kv Switching Station No.1, Incoming Line Station Diagram and Legend “
D-16-18 17 of 19 E-11 22.9kv Switching Station No.2 Single Line Diagram 21 Sep 16
“ 18 of 19 E-12 Cable Junction Pedestal Install Detail “
“ 19 of 19 E-13 Primary Duct & Trench Section and Installation Detail “
SUBMITTAL REGISTER
NOTE. The Submittal Register in Section J above, identifies the documentation that will be made available for approval and review by the Government in the performance of this task order. It is the contractor's responsibility that this data is in compliance with the corresponding OMA specification that is referenced.
Section K - Representations, Certifications and Other Statements of Offerors
52.203-2 CERTIFICATE OF INDEPENDENT PRICE DETERMINATION (APR 1985)
(a) The offeror certifies that --
(1) The prices in this offer have been arrived at independently, without, for the purpose of restricting competition, any consultation, communication, or agreement with any other offeror or competitor relating to –
(i) Those prices,
(ii) The intention to submit an offer, or
(iii) The methods of factors used to calculate the prices offered:
(2) The prices in this offer have not been and will not be knowingly disclosed by the offeror, directly or indirectly, to any other offeror or competitor before bid opening (in the case of a sealed bid solicitation) or contract award (in the case of a negotiated solicitation) unless otherwise required by law; and
(3) No attempt has been made or will be made by the offeror to induce any other concern to submit or not to submit an offer for the purpose of restricting competition.
(b) Each signature on the offer is considered to be a certification by the signatory that the signatory --
(1) Is the person in the offeror's organization responsible for determining the prices offered in this bid or proposal, and that the signatory has not participated and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision; or
(2) (i) Has been authorized, in writing, to act as agent for the following principals in certifying that those principals have not participated, and will not participate in any action contrary to subparagraphs (a)(1) through (a)(3) of this provison ______________________________________________________ (insert full name of person(s) in the offeror's organization responsible for determining the prices offered in this bid or proposal, and the title of his or her position in the offeror's organization);
(ii) As an authorized agent, does certify that the principals named in subdivision (b)(2)(i) above have not participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) above; and
(iii) As an agent, has not personally participated, and will not participate, in any action contrary to subparagraphs (a)(1) through (a)(3) of this provision.
(c) If the offeror deletes or modifies subparagraph (a)(2) of this provision, the offeror must furnish with its offer a signed statement setting forth in detail the circumstances of the disclosure.
(End of Provision)
5152.204-4032 REPRESENTATIONS AND CERTIFICATIONS
(a) SUBCONTRACTING:
If the offeror contemplates subcontracting, it must obtain prior written approval of subcontractor from the PCO or ACO, and list below: (1) the names and addresses of the subcontractor(s), (2) the type of subcontracting, and (3) the estimated price for each subcontract.
(b) AFFILIATED OFFERORS:
(1) Business concerns are affiliates of each other when, either directly or indirectly, one concern controls or has the power to control the other, or a third party controls or has the power to control both.
(2) Each offeror shall furnish, below, the following information:
(i) Whether the offeror has any affiliates;
(ii) The names and addresses of all affiliates of the offeror; and
(iii) The names and addresses of all persons and concerns exercising control or ownership of the offeror and any or all of its affiliates, and whether they are common officers, directors, stockholders holding controlling interest, or otherwise.
AFFILIATED CONCERNS. : (Name, location and, in detail, controlling interest in each)
(c) PRINCIPAL OWNER(S) OR STOCKHOLDER(S):
Each offeror shall list below the name(s) and address(es) of the principal owner(s) or stockholder(s) of the company and percentage of ownership. If a major portion is publicly traded and/or otherwise widely distributed, state that, with the percentage so affected.
(d) STANDARDS OF CONDUCT CERTIFICATION:
This is to certify that, to the best of my knowledge and belief, except as described below, no representative of this firm who deals with US Government employees on any aspect of this procurement is a former US Government employee, to include former US military personnel. I understand that this certification is continuing in nature and places a duty on me and my firm to notify the Contracting Officer of any additional individual(s) who fit the above description prior to the individual's assuming duties.
(i) Name ______________________________________________ Former rank/grade ____________________________________ Last US Government position ___________________________
(ii) Name ______________________________________________ Former rank/grade ____________________________________ Last US Government position ___________________________
(iii) Name ______________________________________________ Former rank/grade ____________________________________ Last US Government position ___________________________
Firm ____________________________________________________ Name _____________________________________________________ Signature __________________________________________________
Title _____________________________________________________ Date of Execution ____________________________________________
(e) TAXES:
(1) References:
(i) Contract clause entitled "FAR 52.229-06 Taxes—Foreign Fixed-Price Contracts (Jan 1991)."
(ii) US-ROK Status of Forces Agreement (SOFA), Articles IX and XVI.
(iii) ROK Customs Law, Law No. 1976, promulgated on 29 November 1967, as amended.
(iv) ROK Value Added Tax Law, Law No. 2934, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.
(v) ROK Special Excise Tax Law, Law No. 2935, promulgated on 22 December 1976 (effective date 1 July 1977), as amended.
(2) Contractor shall state the types and estimated amount of taxes that would normally apply to such transactions but are excluded from this proposal.
(i) Customs Tax (except for ROK MND-funded contracts or delivery orders):
Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total
This item will be imported specifically for this contract? Yes _____ No _____
(ii) Special Excise Tax:
Name Number Cost/Unit of Item of Units w/o Tax % of Tax Tax/Unit Tax Total
Name of item manufacturer
(iii) Value Added Tax (VAT):
Input VAT on materials purchased for this contract. 10% _____ Input VAT on transportation leased/rented for this contract.10% _____ Input VAT on equipment leased/rented for this contract. 10% _____ Input VAT on services purchased for this contract. 10% _____ Output VAT on total contract amount. 10% _____
(iv) Special Excise (Petroleum) Tax:
No. of U/P
Liters w/o Tax Tax/Unit Total Tax Amount Regular Gasoline ________ (L) ________ w________ w_____________ Premium Gasoline ________ (L) ________ w________ w_____________ Diesel ________ (L) ________ w________ w_____________ Other ________ (L) ________ w________ w_____________
(v) Education Tax.
(3) Name of the oil company from which POL products will be purchased:
Oil Company: _________________________________________ (Name only)
(4) I certify by this submission that all supplies and services to be purchased for this contract have been proposed exclusive of Value Added Tax, applicable Customs Tax (except ROK MND-funded contracts and delivery orders), Special Excise Tax, and Education Tax.
Signed (Chop)
(f) CERTIFICATIONS AND REPRESENTATIONS
By submitting an offer, each offeror agrees to be bound by all certifications and representations in this solicitation.
The Government reserves the right to require any and all certifications and representations to be completed and signed in hard copy by the successful offeror prior to contract award. Failure of an offeror to complete the certifications and representations within the time directed by the Contracting Officer may result in a determination that the contractor is not a responsible offeror for this acquisition.
Section L - Instructions, Conditions and Notices to Bidders
INSTRUCTION TO OFFERORS
1. GENERAL INSTRUCTIONS FOR PREPARATION OF PROPOSAL:
a. The Government intends to award without discussion, but reserves the right to conduct discussions if deemed necessary and to establish a competitive range for efficiency in accordance with FAR 52.215- 1(f)(4).
b. Offeror(s) may, at the discretion of the Government, be asked to provide more information and clarification regarding their proposals. The Government may make a final determination as to whether an offer is acceptable or unacceptable solely based on the proposals as submitted, without requesting any further information. However, if it is deemed necessary the Government may, at its sole discretion, request additional information clarifying but not substantially changing any proposal as submitted.
2. SUBMISSION OF PROPOSAL:
a. Offers shall be submitted to Federal Business Opportunities (FBO) https://www.fbo.gov/ , or if FBO is not available, email to anna.w.lee.civ@mail.mil with the evidence document such as screen shot. The FBO unavailability is limited to ONLY FBO server problem not individual failure/problem. All questions should be emailed to anna.w.lee.civ@mail.mil within two (2) days after the site visit. The electronic offer shall be submitted by 1500 hrs on the closing date of RFP.
b. The PRICING PROPOSAL with the detailed cost breakdown shall be submitted by 1500 hours on the closing date of RFP through https://www.fbo.gov/ . The cost breakdown should clearly identify all the significant costs associated with the level of effort prescribed in the statement of work. Any omission of such data may result in the offeror not being considered for award.
c. Section K : Offerors must complete all portions of Section K and submit it through https://www.fbo.gov/ by 1500 hours on the closing date of RFP. The offeror shall review all expenses to ensure that all applicable taxes are excluded from the overall price. In addition, any proposed exemption of a specific ROK tax shall be legitimate, attributable to the contract, and authorized by the applicable stated references.
d. Offeror’s status as a Korean contractor:
1) The offeror's most recent Stock Change Certificate (주식등변동 상황명세서), as certified and submitted to the ROK Local Tax Office (국세청),
2) The offeror's Certified Copy of Register [등기부 등본 (유효사항)], as certified and submitted to the ROK Supreme Court (대법원), and
3) If the offeror has a Parent (as Parent is defined in the International Agreement), the Parent's
Certified Copy of Register [등기부등본 (유효사항)], as certified and submitted to the ROK
Supreme Court (대법원).
Failure to submit the above requirements may be grounds for determining the proposal to be noncompliant and not eligible to be considered for award.
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) An organized site visit has been scheduled for--
Date: Tuesday, 04 April 2017 Time: 1100 hours
(c) Participants will meet POC inside of Gate #2, Camp Carroll
Government POC: Mr. Kim, Chae Kyong (764-4134 / 764-4133)
(End of provision)
5152.236-4011 CONSTRUCTION PRICE RANGE
Pursuant to FAR 36.204 the estimated price range is between $1,000,000 and $5,000,000.
Section M - Evaluation Factors for Award
BASIS FOR AWARD
Award shall be made to the responsible offeror submitting the lowest priced, technically acceptable offer and completed Section K that satisfies all terms and conditions of this solicitation. The Government reserves the right to make a technical acceptability determination without any discussion with the offeror. The tax exemptions stated in Section K will be reviewed by the contracting officer for reasonableness and necessity to complete the Task Order.
The contracting officer may reject a proposal if the offeror appears to improperly overstate any proposed tax exemptions.
File details come from the government source that posted it. Updated .