This is a Questions and Answers document for federal contract W91QF426BA008, issued by DPW on 21 August 2026, concerning the replacement of exterior doors at Building B635 and Building B636.

The project scope requires replacement of 24 total door leaves across three locations: 16 doors on B635 Floor 2 (Main Level), 6 doors on B635 Floor 1 (Basement), and 2 doors on B636 Ground Level. All replacement doors and frames must be commercial-grade aluminum (6063-T6 architectural aluminum extrusions) per ASTM B209, not steel or hollow metal frames. New door sizes must match existing dimensions rather than standard 3'0" × 7'0" dimensions. Sidelights and toplights must be removed and replaced with insulated 6063-T6 aluminum sheet plate infill panels; full glass doors must be replaced with half-light doors. All existing doorstops must be replaced in-kind with 2 5/8" Goose Neck floor mounts in oil rubbed bronze or matte black finishes. Door installation must be performed by contractors certified and trained by the door manufacturer, with certification documentation submitted after contract award but prior to installation. All door swings must remain unchanged from existing conditions. Mechanical room doors are excluded from the total count.

The contractor is responsible for providing and having Best 7-pin lock cores pinned (M Keyway), with DPW locksmith installing cores and coordinating delivery with the Contracting Officer's Representative. The contractor must furnish all labor and materials to deliver a complete, functioning system including synchronization of new locks to the existing Vanderbilt Access Control System (version 6.4.2). For B635, existing Schlage 302 wired controllers are installed; for B636, Schlage 402 wireless controllers are installed. Existing access control devices must be replaced with new units and salvaged equipment returned to DPW. Existing access control wiring may be reused; if removal, extension, repair, or replacement is required, the contractor must notify the COR and submit an RFI. Power and control wiring transfer methods must match existing installations. The contractor must assume adequate power and capacity for the access control system; if existing conditions differ, an RFI must be submitted. The Access Control System operates as a standalone system with no network integration, IT infrastructure work, cybersecurity requirements, Authority to Connect, Authority to Operate, or RMF compliance required. The contractor must follow ACS hardware manufacturers' operations and testing procedures and notify the COR of pre-final and final acceptance tests and inspections.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

21 Aug 2026

Questions and Answers for

W91QF426BA008

B635 Exterior Doors

1. Does the government require new door stops with the new door installation? If so, does the government want to stay with the example of a 2 5/8" Goose Neck floor mounts oil rubbed bronze, matte black range of finish?

DPW Response: Affirmative, replace existing doorstops with new in-kind.

2. Are the new frames being installed remaining "New exterior doors shall be commercial-grade aluminum stile-and-rail doors, fabricated from 6063-T6 architectural aluminum extrusions", or will they be 12-gauge, 14 gauge, or 16-gauge Hollow Metal dimpled frames?

DPW Response: Affirmative. Doors and frames shall be commercial grade aluminum as specified in the project Statement of Work (SOW).

3. The SOW states "Remove all existing sidelight and top light framing, glazing, and associated components. Provide new insulated metal infill panels, factory-finished to match the adjacent door assembly. Is it the government's intention to infill all areas that are currently containing glass with insulated metal panels?

DPW Response: Negative. Review the SOW. Sidelights and toplights shall be replaced by metal infill. Full glass doors shall be replaced by half-light doors.

4. Please specify the "metal infill assembly" DPW Response: 6063-T6 aluminum sheet plate complying with ASTM B209.

Match aluminum door and frame.

5. Assumption that all door swings will remain the same. Is this a correct statement?

DPW Response: Affirmative.

6. Will the contractor be responsible for keying the Best 7 pin cores on new locks?

DPW Response: Contractor is responsible for providing cores and having them pinned. DPW to install cores. Cores are typically sent directly from Best to DPW locksmith after pinning. Coordinate delivery with Contracting Officer’s Representative (COR).

7. What keyway does the government want on this building?

DPW Response: M Keyway.

8. SOW Section SW-2.b covers the seven basement doors and says they shall comply with all requirements in Section 1. Do any of the basement openings include sidelights or toplights that require removal and insulated infill panels like the main floor doors, or are the basement openings door and frame only?

DPW Response: Affirmative, comply with all requirements in Section1 and remove sidelights and toplights, to be replaced by infill panel.

9. SOW SW-2.a.15 requires doors to be installed by an installer certified and trained by the door manufacturer. Is documentation of that certification required with the bid, or submitted after award with the product submittals?

DPW Response: Submit certification and training documentation after contract award but prior to installation.

10. Conformation of Total Door Count DPW Response: Total Door Count is 24. Each leaf is counted as a door.

See diagrams attached for locations (Attachment A).

B635 Floor 2 (Main Level) = 16 B635 Floor 1 (Basement) = 06 B636 Ground Level = 02

11. Will these be steel doors & frames our aluminum storefronts?

DPW Response: Aluminum doors and frames.

12. Do you want glass in the mechanical room doors?

DPW Response: Mechanical room doors have been excluded from the total count. See Attachment A.

13. Is Bldg. 636 included in this project?

DPW Response: See response to Question 10.

14. Do you want to go with standard door slabs 3'0 X 7'0 or match what is existing there?

DPW Response: Match existing.

15. Total Door Count: Please confirm the total number of doors included in the project scope.

DPW Response: See response to Question 10.

16. Door and Frame Material: Based on the existing conditions observed during the site visit, please confirm whether the replacement doors and frames are to be steel or aluminum storefront, as specified in the SOW.

DPW Response: See response to Question 11.

17. Building 636: Please confirm whether any doors at Building 636 are included in the project scope.

DPW Response: See response to Question 10.

18. Door Sizes: Please confirm whether the new door slabs are intended to all be standard 3’-0” × 7’-0”, or whether the replacement doors are to match the existing field-verified dimensions. A few doors are custom.

DPW Response: See response to Question 14.

19. Are the exterior door stops mounted into the concrete to be removed and replaced?

DPW Response: See response to Question 1.

20. Please clarify if the access control devices are to be disconnected and reconnected using existing or if the access control devices will be removed and replaced new, while salvaging existing.

DPW Response: Replace access controls with new and salvage existing. Return salvaged to DPW.

21. Are the doors to remain aluminum as specified, or will the scope of work be revised for steel as recommended at the site walk?

DPW Response: See response to Question 11.

22. Are the doors installed to be 36” per ADA requirements, or will the doors at each location match existing?

DPW Response: See response to Question 14.

23. Are there additional door locations that were not identified at the site visit? The statement of work states there is a total of 28 doors to be replaced, while only 24 were located on the site visit.

DPW Response: See response to Question 10.

24. Are the vestibule doors at the main entrance to be replaced along with the exterior doors?

DPW Response: Negative. See response to Question 10.

25. Can you provide as-built drawings?

DPW Response: See Attachment B and C for As-Builts

26. What Vanderbilt platform/version is installed?

DPW Response: Software version is 6.4.2.

27. What controller model numbers are installed?

DPW Response: For B635: Schlage 302 wired. For B636: Schlage 402 wireless.

28. Are existing locks/readers being reused or replaced?

DPW Response: Replaced.

29. Is Vanderbilt database programming included?

DPW Response: If the question pertains to synchronization of new locks, yes, the locks must be synced to the existing Vanderbilt access control system as part of the Contractor’s SOW.

30. Are software licenses required?

DPW Response: Each lock comes with its own license.

31. Who performs final commissioning and acceptance testing?

DPW Response: Contractor shall follow project Close Out procedures of the contract and notify the COR of pre-final and final acceptance tests and inspections.

32. Provide ACS riser/network drawings.

DPW Response: Drawings unavailable.

33. Confirm Total Door Count DPW Response: See response to Question 10.

34. Steel Doors and Frames or Aluminum Storefront DPW Response: See response to Question 11.

35. Is Building 636 included in the project DPW Response: See response to Question 10.

36. Standard door slabs, 3’0 x 7’0 or match sizes of what is existing DPW Response: See response to Question 14.

37. Is the government locksmith going to key the doors or is it a contractor responsibility?

DPW Response: See response to Question 6.

SOW SW-2.a.14 and SW-5 SD-02 Please confirm whether existing access control wiring may be reused. Where door and frame replacement requires existing wiring to be removed, extended, repaired, or replaced, please define the required cable types, quantities, pathways, and limits of replacement.

DPW Response: Affirmative. Reuse existing access control wiring. During construction, notify the COR and submit an RFI if door and frame replacement requires existing wiring to be removed, extended, repaired, or replaced.

SOW SW-2.a.4, SW-2.a.14, and SW-5 SD-02/SD-03 Please identify the required method of transferring power and control wiring from each new frame to each electrified door, including whether electrified hinges, concealed power transfer devices, or armored door loops are required, and provide approved manufacturers or models.

DPW Response: Match existing method.

SOW SW-2.a.14.111 and SW-5 SD-06 Please clarify who is responsible for Vanderbilt system programming, database changes, point mapping, credential configuration, final integration, and manufacturer-authorized commissioning. If a Government access control vendor is required, identify whether that vendor will be Government-furnished or contractor furnished.

DPW Response: Contractor shall furnish and procure all labor and materials necessary to deliver a complete, useable and fully functioning system upon project completion.

SOW SW-2.a.14.111 and SW-5 SD-03

Please confirm whether existing access control panels, controllers, and power supplies have adequate capacity for the final door hardware configuration. If modifications or new equipment are required, please provide equipment requirements, locations, available branch circuits, and circuit identification.

DPW Response: Assume adequate power and capacity. During construction, notify the COR and submit an RFI if existing conditions differ from assumption.

SOW SW-5 SD-06

Please define the required access control testing and acceptance procedure, including required test reports, responsible witnessing authority, and whether testing must be performed by a Vanderbilt-authorized technician.

DPW Response: Contractor shall follow ACS hardware manufacturers’ operations and testing procedures and instructions and shall notify the COR of pre-final and final acceptance tests and inspections. Contractor shall furnish and procure all labor and materials necessary to deliver a complete, useable and fully functioning system upon project completion.

SOW SW-2.a.14 and SW-5 SD-01 Temporary Security / Boarding Plan During daily door replacement, is the contractor required to provide temporary electronic access control or monitoring, or is temporary physical security and maintenance of existing circuit continuity sufficient?

DPW Response: Refer to section SW-2 a. 14) II. and SW-2 a. 14) II. (1) of the SOW.

SOW SW-2.a.1, SW-2.a.14, and SW-5 SD-02/ SD-03 Please clarify trade responsibility for furnishing and installing electrified locking hardware and access control door components. Specifically identify items furnished or installed under the door hardware scope versus the electrical/ access control scope.

DPW Response: Contractor shall furnish and procure all labor and materials necessary to deliver a complete, useable and fully functioning system upon project completion.

SOW SW-2.a.14 .III Please confirm, whether any cybersecurity requirements, Authority to Connect (ATQ , Authority to Operate (ATO), RMF, STIG compliance, or cybersecurity documentation are required for work associated with the Vanderbilt Access Control System. If required, please provide applicable specifications and identify the responsible party.

DPW Response: Not required. ACS is a standalone system.

SOW SW-2.a.14.III Please clarify whether the contractor is required to access, modify, connect to, or program any Government networked equipment associated with the Vanderbilt Access Control System. If so, please provide all applicable EC, cybersecurity, and network accreditation requirements.

DPW Response: Negative, no network access anticipated. ACS is a standalone system.

SOW SW-2.a.14 .III and SW-5 SD-06 If software programming, controller modifications, database changes, or network integration are required, please identify whether this work will be performed by the contractor, the NEC, DPW, or a Government-furnished access control vendor.

DPW Response: New locks are to be synchronized to exiting ACS as part of the SOW.

ACS is a standalone system. Network integration not required.

SOW SW-2.a.14 Please confirm that no CAC-enabled, IP-based, network switch, fiber, copper backbone, server, workstation, or other IT infrastructure work is required under this project beyond reconnecting existing door access control devices.

DPW Response: Affirmative, IT infrastructure work not anticipated beyond connecting new door access control devices to existing Vanderbilt system/ACS.