APPENDIX_A.docx

DOCX document 52 KB Posted

Attached to
VERY SMALL APERTURE TERMINAL (VSAT) Federal contract opportunity
Solicitation number
W91CRB-19-R-5001
Issued by
Department of the Army Materiel Command Army Contracting Command Aberdeen Proving Ground

About this file

This document contains a project plan review checklist and a federal contract opportunity notice. The project plan review checklist outlines 38 questions for contractors to address in their project plans. It covers overall project plan requirements, scope, approach, assumptions, constraints, risk, organization, estimates, schedules, change management, issue management, risk management, quality management, communication management, configuration management, and closeout.

The related federal contract opportunity is a notice for a Very Small Aperture Terminal solicitation seeking a firm fixed price IDIQ contract under FMS. Interested parties must submit proposals by email to the listed Army contracting personnel by December 7th, 2018 at 3pm EST and request confirmation of receipt. The opportunity involves supplying VSAT terminals and the contracting agency is the Department of the Army Materiel Command Army Contracting Command located at Aberdeen Proving Ground.

View the file

Other files for this federal contract opportunity

Other files attached to VERY SMALL APERTURE TERMINAL (VSAT), newest first.
File Type Posted
Amendment_0013.pdf PDF
Amendment_0012.pdf PDF
Amendment_0011.pdf PDF
Amendment_0010.pdf PDF
Amendment_0009.pdf PDF
Amendment_0008.pdf PDF
VSATPRICE_28_November_2018.xlsx XLSX spreadsheet
Amendment_0007.pdf PDF
Amendment_0006.pdf PDF
Amendment_0005.pdf PDF
Amendment_0004.pdf PDF
Amendment_0003.pdf PDF
Amendment_0002.pdf PDF
Amendment_0001.pdf PDF
W91CRB-19-R-5001.pdf PDF
VSATPRICE.xlsx XLSX spreadsheet
VSAT_LPTA_IDIQ-1_CDRLS_18_Oct_18.pdf PDF
APPENDIX_E.docx DOCX document
APPENDIX_C.docx DOCX document
APPENDIX_B.docx DOCX document
APPENDIX_D.docx DOCX document
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Appendix A – Program Management Plan Checklist

Project Plan Review Checklist

Project Name

ID
Plan Req
Items to be considered
Contractor to provide

Overall Project Plan Questions

1.

Have all required sections been addressed in the Project Plan?

2.

Deliverables Identified?

3.

QC Reviews identified?

Project Scope Questions

4.

Scope clearly defined?

5.

Scope consistent with Initial Scope in Project Charter?

6.

Project Approach defined?

7.

Are the baseline requirements numbered or easily identifiable for use in a requirements traceability matrix (RTM)?

8.

Project Assumptions addressed?

9.

Project Constraints addressed?

10.

Risk Identified?

Management Plan Questions

Project Organization Questions

11.

Does the project organization have representation for management, functional office and business unit/section?

12.

If the project needs District participation, are there District people in the project organization?

13.

Are roles defined?

Estimate/Schedule/Resource Questions

14.

Baseline Estimate established? Estimate method defined?

15.

Baseline Schedule established? Match major milestone date with Project Charter and work breakdown structure (if applicable)

16.

Project > 600hours? Work Breakdown Structure included?

Change Management Questions

17.

Change Management process defined?

18.

Project Change Control Team (CCT) members identified?

19.

Frequency of Government Contractor meetings defined?

20.

Change Log?

Issue Management Questions

21.

Issue management process defined

22.

Issue escalation process identified

23.

Issue Log Provided

Risk Management Plan Questions

24.

Risk Management process defined?

25.

Project Risk Review Team (PRRT) members identified

26.

Risk Register Initiated

27.

Risk Response Strategy established for each identified risk

28.

Has the Risk Tolerance Threshold been established for the project?

29.

Is there a Risk Item form or equivalent present, for each risk identified that has a risk severity rating >= the project risk tolerance threshold?

30.
Quality Management Plan Questions

Quality Management Process defined?

31.

QC Reviews identified for deliverables established/addressed in project plan?

32.
Communication Management Plan Questions

Communication plan established

33.

Status reports addressed (frequency, audience)

34.

Project Distribution groups identified

35.
Configuration Management Plan Questions

Application documents that will be controlled identified? (Requirements, System Design, etc)

36.

Project Documents that will be controlled identified (Project Charter, Project Plan, etc)

37.
Project Closeout Questions

Does project have close out plan?

38.

If project is delivering an application, does the project have a transition to maintenance plan?