This document contains an amendment to a solicitation and questions and answers related to a federal contract opportunity for Very Small Aperture Terminal (VSAT) services. The amendment modifies the solicitation and provides additional clarification on technical and pricing requirements. The U.S. Army Contracting Command is seeking proposals for an Indefinite Delivery Indefinite Quantity contract to provide VSAT supplies and services to support foreign military sales requirements. Proposals are due by December 7, 2018 and must be submitted electronically to the points of contact listed. The contract will have a one-year base period and four one-year options. Pricing is to be provided using the revised VSAT price spreadsheet attached to Amendment 0007. Questions and answers provide additional details on equipment requirements, certifications needed, and evaluation criteria.
AMENDMENT 0010
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_0013.pdf | ||
| Amendment_0012.pdf | ||
| Amendment_0011.pdf | ||
| Amendment_0009.pdf | ||
| Amendment_0008.pdf | ||
| Amendment_0007.pdf | ||
| VSATPRICE_28_November_2018.xlsx | XLSX spreadsheet | |
| Amendment_0006.pdf | ||
| Amendment_0005.pdf | ||
| Amendment_0004.pdf | ||
| Amendment_0003.pdf | ||
| Amendment_0002.pdf | ||
| Amendment_0001.pdf | ||
| W91CRB-19-R-5001.pdf | ||
| APPENDIX_B.docx | DOCX document | |
| APPENDIX_D.docx | DOCX document | |
| VSATPRICE.xlsx | XLSX spreadsheet | |
| VSAT_LPTA_IDIQ-1_CDRLS_18_Oct_18.pdf | ||
| APPENDIX_E.docx | DOCX document | |
| APPENDIX_C.docx | DOCX document | |
| APPENDIX_A.docx | DOCX document |
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code Page Of
2. Amendment/Modification No.
3. Effective Date
4. Requisition/Purchase Req No.
5. Project No. (If applicable)
6. Issued By Code 7. Administered By (If other than Item 6) Code
8. Name And Address Of Contractor (No., Street, City, County, State and Zip Code)
9A. Amendment Of Solicitation No.
9B. Dated (See Item 11)
10A. Modification Of Contract/Order No.
10B. Dated (See Item 13) Code Facility Code
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing items 8 and 15, and returning ____________ copies of the amendments: (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. Accounting And Appropriation Data (If required)
13. THIS ITEM ONLY APPLIES TO MODIFICATIONS OF CONTRACTS/ORDERS
It Modifies The Contract/Order No. As Described In Item 14.
A. This Change Order is Issued Pursuant To: The Changes Set Forth In Item 14 Are Made In
The Contract/Order No. In Item 10A.
B. The Above Numbered Contract/Order Is Modified To Reflect The Administrative Changes (such as changes in paying office, appropriation data, etc.) Set
Forth In Item 14, Pursuant To The Authority of FAR 43.103(b).
C. This Supplemental Agreement Is Entered Into Pursuant To Authority Of:
D. Other (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return _______________ copies to the Issuing Office.
14. Description Of Amendment/Modification (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. Name And Title Of Signer (Type or print)
16A. Name And Title Of Contracting Officer (Type or print)
15B. Contractor/Offeror 15C. Date Signed 16B. United States Of America 16C. Date Signed
By (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITIONS UNUSABLE
30-105-02 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
SEE SCHEDULE
X
Firm Fixed Price
W91CRB
ACC-APG - DIVISION D (W91CRB)
6515 INTEGRITY COURT
APG, MD 21005-3013
REM D NGO
EMAIL: REM.D.NGO.CIV@MAIL.MIL
W91CRB-19-R-5001
2018NOV07
X
X
2 signed
SEE SECOND PAGE FOR DESCRIPTION
1 4
CONTINUATION SHEET
Reference No. of Document Being Continued Page of
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
SECTION A - SUPPLEMENTAL INFORMATION
Buyer Name: REM D NGO
Buyer Office Symbol/Telephone Number: CCAP SCD/(410)306-2667
Type of Contract 1: Firm Fixed Price
Kind of Contract: Supply Contracts and Priced Orders
*** End of Narrative A0000 ***
Q 79:
In your answer to Q33 you state that if an alternate satellite is offered for the Mobile SATCOM Network that the contractor will provide a temporary back-up hub for a 3 month period and the temporary VIPERSAT hub needs to be located in CONUS or EU.
Question - Will IMOD accept local Internet access for the temporary VIPERSAT located in the CONUS or EU, or will all traffic need to be backhauled via terrestrial circuit to the hub located in the Baghdad Green Zone?
Answer:
Local internet access is acceptable
Q 80:
Question - If an award is made to a satellite other than IS-20 for the mobile network (Vipersat network currently on IS-20), how will the additional three months of extension of IS-20 capacity be factored into the LPTA evaluation.
Answer:
IS-20 bandwidth/space segment is contracted through 31 March 2019 under an existing CECOM contract with the incumbent contractor.
During transition, these services will overlap with the capacity the Government will procure using the bandwidth increments ordered under VSATPRICE_28_November_2018.xlsx.
Q 81:
Question - On the IMOD Fixed network, what are the actual Outbound and Inbound carrier configurations (i.e. data rate, modulation, and code rates)? Appendix E was not entirely clear on this point.
Answer:
Outbound and inbound configuration for all sites will be provided after contract award with the first Delivery Order.
Q 82:
Section 2.3.1.3 indicated that rates of 128 to 2048 Kbps are required for the Vipersat mobile network.
Question - Does this refer to the Inbound carriers?
Answer:
Not applicable as this relates to the follow on question (83) and answer.
Q 83:
Question If the above answer (82) is yes, Is it sufficient to provide LBAs for only the 128 Kb and 2048 Kb IB cases for each remote type and best/avg/worst location, plus the aggregate OB cases?
Answer:
Link Budget Analysis is not required for the VIPERSAT/mobile network for this solicitation, for proposal submission or for post-award contract deliverables.
Q 84: Question - Due to changes to the technical solution that have been dictated by amendment 7 and 8 would the gov't approve a request for an extension until 12/14/18 so that proper diligence can be performed with the proposed solution that will be proposed.
Answer:
No, due to time constraints we cannot grant an extension.
Q 85:
Appendix A asks the Offeror to state if it has representation at the functional office and business unit/section levels. Please clarify if the functional office is the Contractors PMO and explain what business unit/section mean.
2 4
W91CRB-19-R-5001
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
Answer:
The offeror shall use the levels specified in Appendix A to describe their program management organization structure. The Government will not dictate an offerors program management structure, organization or approach.
Q 86:
Technical Proposal Contents, Subfactor 10, states that proposals will be rated Acceptable if they include the following: Work locations of iDirect-and CCNA-certified personnel specified for PoP duration. However, IAW Subfactor 5, iDirect-and CCNA-certifications are required only for the satellite transition. Please clarify if the iDirect-and CCNA-certified personnel are needed for the entire PoP or just the Transition Period.
Answer:
Offerors are required to specify work location(s) for their iDirect and CCNA certified personnel during the transition. Offerors who propose iDirect and CCNA certified personnel as part of their labor mix for the entire PoP (not just during transition) shall also indicate work location(s) for their certified personnel. Offerors are reminded that the Government will not dictate an offerors labor mix but will evaluate the labor mix to ensure it is balanced and contains the required skills for meeting the scope of work.
Q 87:
Does the incumbent currently have an in-country PMO (Program Management Office)?
Answer:
This information is procurement sensitive as it relates to an ongoing active contract. Information pertaining to the incumbent contract may be requested through the Freedom of Information Act.
Q 88:
Is Vipersat certification required for any personnel for this IDIQ contract? (Reference PWS 1.4)
Answer: No
Q 89:
PWS 9.4.1 refers to a Contractor-provided certified Level II OPSEC Coordinator, but its not clear if this position is required at the time of award or when the OPSEC Plan is due 90 days post-award. Please clarify.
Answer:
Refer to Amendment 0007 to this solicitation, questions and answers 72 and 73.
Q 90:
Reference: Corporate Experience (Volume I) and Past Performance (Volume II): may Offerors use the same experience for both sections?
Answer:
Yes, as long as the Corporate Experience is relevant to the scope of work.
Q 91:
The training listed under PWS 9.1 appears to be for online training, except for 9.2 (iWatch Training) & 9.3 (Threat Awareness
Reporting). Please clarify if these latter two course are online and if they are Government- or Contractor-provided. Will Contractors be required to maintain training personnel on their staff? [PWS 9.1 9.5 and PWS 4.1 4.2]
Answer:
iWatch training required under PWS paragraph 9.2 can be received only at the following URL http://www.myarmyonesource.com/familyprogramsandservices/iwatchprogram/default.aspx Ensure the website is added to internet compatibility view settings prior to accessing the website. Threat Awareness Reporting Training (TARP) required under PWS paragraph
9.3 must be received annually in person by a Counterintelligence Officer or other trainer. Offerors should consult with their Facility
Security Officer on options for receiving TARP Training or contact their nearest military installation for the annual installation TARP schedule.
Q 92:
Owing to the amount of detailed Q&A and Amendments that have been released, in addition to the revised pricing spreadsheet that was provided today, would the Government please consider granting a 1-2 week extension of the proposal due date?
Answer:
An extension will not be granted.
Q 93:
Question: On the revised VSAT Price Spreadsheet that was issued on 11/28/2018, Year 1 includes equipment for the transition, but Years 2-
3 4
Name of Offeror or Contractor:
PIIN/SIIN MOD/AMD
3-4-5 contain a long list of equipment items which are not included in the RFP/PWS. Could the Government please clarify if these equipment items (CLIN 0004, Years 2-5) are required, and how they relate to the PWS requirements since they are not included in the actual RFP?
Answer:
The previous or original VSAT price spreadsheet and the revised spreadsheet posted with Amendment 0007 to this solicitation contain the same equipment SLINs in years 2, 3, 4, and 5. The only corrections to the revised spreadsheet were formula errors for the fixed bandwidth SLINs. Additional equipment was not added to the spreadsheet. All equipment items listed under CLIN 0004 for years 2, 3, 4, and 5 are required as per PWS paragraph 8.0.
*** END OF NARRATIVE A0011 ***