QUESTIONS AND ANSWERS AMENDMENT (6-12-18):

QUESTION: The SOW states work hours are only on Saturday or Sunday between 8am – 4pm.

Will there be no exception to this work schedule? Will any weekday or weeknight work be allowed during the regular work week in order to complete the project faster?

ANSWER: Yes, there can be exceptions. There were concerns about the dust generated from the grinding process but will support any operating hours that will expedite the time of completion.