Revised Q A

View the file

Other files

File Type Posted
W9133L-15-R-0034.docx DOCX document
CAFDEx_Industry_Day_Briefing_-_FINAL_for_Projection.pptx PPTX presentation
CAFDEX__Revised_PWS_F0100_New_Contract_for_FY15.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Repair Building 909, Buckley AFB, CO

CRWU 06-2003

W9133L-16-R-0043

Questions & Answers 26 July 2016

1. QUESTION: Will a second site visit be available?

ANSWER: No. A second site visit will not be scheduled for this project.

2. QUESTION: Once we have installed the temporary construction fence will contractors / subcontractors be allowed to work freely within the hanger and the surrounding area within the construction site without escorts even though the hanger is technically still within the flight line?

ANSWER: Yes. It will be set up as a construction zone and an escort will not be required inside the construction fence.

3. QUESTION: Will an official Lead and Asbestos report be made available to help with the bidding process?

ANSWER: Yes. It was posted to FBO on 14 Jul 2016 under Amendment 0003.

4. QUESTION: On similar projects asbestos has been found under the spray coating on the hanger doors. Do these doors have asbestos containing materials as well?

ANSWER: The facility asbestos report will be posted. The test and report show the hangar door does not contain asbestos.

5. QUESTION: On the bid form W9133L-16-R-0043 page 3 of 73 please confirm that the Net

Amount for Item No 0001 should equal the Total Project Cost from Page 5 of 73 and that Item No 0002 should equal line item 4 under Base Bid on page 4 of 73.

ANSWER: Please complete the bid schedule on page 4. The CLINS on page 3 are for Accounting Purposes Only – and should NOT be filled in.

6. QUESTION: Should we provide roller shades @ hatched areas to receive translucent panels, reference window elevations A404, WF-04, for example?

ANSWER: No. The hatched areas are to be a translucent panel. Roller shades are not allowed.

7. QUESTION: Please clarify what RS-1 and RS-2 are referring to specifically.

ANSWER: Suggested answer: Refer to Specification section 090640 Finish Material Schedule for RS-01 and RS-02. Provide roller shades where indicated by Remark 8 and 9 on Sheet A401 “Room Finish Schedule”.

8. QUESTION: In Section 010600 – Safety Policies & Procedures, the contractor is instructed to reference 29 CFR 1910 (OSHA General Industry) for compliance, training, and guidance in development of a Safety & Health Plan. The scope of this project is construction and which falls under the jurisdiction of 29 CFR 1926 (OSHA Construction). Construction contractors are required to follow applicable OSHA 1910 standards as they apply or are not covered in the construction standard, but are required by law to follow all applicable standards in OSHA 1926. Is this requirement to comply with OSHA 1910 intentional?

REVISED ANSWER (18 July 2016) Specification Section 010600 has been revised in amendment 0004 to include 29 CRF 1926

9. QUESTION: Under Spec Section 00110 section 2.5.3. addresses Offeror past/present performance information. 2.5.3.4 states “Offerors shall discuss their performance using the Performance Relevancy Questionnaire format, Exhibit A, Part 1. Prepare not more than 4 of these documents.” When Exhibit A is referenced, under Part 1 it states “Provide the following information requested in this format for each of the projects/contracts being described. Prepare not more than three (3) of these documents.” Please clarify are we to prepare 3 or 4 questionnaires?

ANSWER: Prepare not more than three (3) of these documents. This was clarified in Amendment 0002.

10. QUESTION: On sheet A021 and A022, there are no notes that address what ceilings are to be removed. Please clarify what ceilings are to be demolished and what ceilings are to remain.

ANSWER: Remove all ceilings. Refer to Note 27 D. of Demolition General Notes on sheet A022. Remove existing ceiling finish and support system in its entirety. Patch & repair walls to accept scheduled ceiling finish at height indicated. Refer to Reflected Ceiling Plans and Room Finish Schedule for required finishes.

11. QUESTION: Sheet P004 and P005 list general notes that state demolish all existing plumbing fixtures, piping, hangers and supports, and all appurtenances, and associated accessories. Is there a set of as built drawings that can be provided that would show what plumbing is existing that is to be demolished?

ANSWER: Drawings from 1956 are not specific – demolish all. Contractor shall remove and reuse existing electric water cooler located by the restrooms on the 1st floor, south side of building.

12. QUESTION: If no plumbing as built drawings can be provided, can another site visit be held?

ANSWER: Reference Question No. 1. A second site visit will not be scheduled for this project.

13. QUESTION: Sheet M006 and M007 list general notes that state demolish all mechanical equipment, ductwork, mechanical piping, hangars and supports, and all appurtenances, and associated accessories. Is there a set of as built drawings that can be provided that would show what HVAC is existing that is to be demolished?

ANSWER: Drawings from 1956 are not specific – demolish all.

14. QUESTION: If no HVAC as built drawings can be provided, can another site visit be held?

15. QUESTION: There are several in wall AC units that are to be removed. Are these units to be disposed of or are they to be returned to the government?

ANSWER: All window and wall AC units are to be removed and disposed of by the contractor.

16. QUESTION: The geothermal loops are designed to a depth of 500’. Most contractors in the area only drill to a depth of 300’. Is it possible to do a field with 300’ – 1” loops?

ANSWER: In order to meet the cooling and heating requirements for this building and do to limited space for the geothermal wells, the geothermal wells need to be 500’ deep.

17. QUESTION: Due to the complexity of the project many subcontractors are unable to turn bids in by the current bid due date. Allowing for more time on the bids will result in more competitive bids with better pricing. We request a 2-3 week bid extension. We propose a new bid due date of 9 Aug 2016.

ANSWER: Amendment 0003 extended the proposal due date to 28 Jul 2016.

18. QUESTION: Project schedule is set for 320 days. With the demolition of the interior of the building, including abatement of multiple items, and the time for commissioning, this is a short time line for new construction. We request the project duration be changed to 395 days.

ANSWER: The project performance period will not be changed. The performance period will remain at 320 days.

19. QUESTION: When will the pre-bid meeting attendees list be posted?

ANSWER: The attendees list was posted on July 8, 2016.

20. QUESTION: Drawing C002 Demolition Note 9 indicates that the soil may contain asbestos and that it is to be disposed of at a certified landfill. Should it be assumed that the soil is considered regulated asbestos containing soil (RACS), and if so is the asbestos friable or non-friable, and what is the level of contamination?

ANSWER: The areas in the region are former facilities areas and not definitively RACS areas. Please find the BAFB Specific Regulated Asbestos Contaminated Soil Management Plan posted to the FedBizOpps website for guidance and procedures to follow.

21. QUESTION: Drawing C002 Demolition Note 9 also states that a “certified asbestos building inspector shall be onsite at all times involving contaminated waste”. Will this inspector be contracted as a third party directly with the owner?

ANSWER: The certified asbestos building inspector shall be provided by the contractor and be included in the contractors bid for this project.

22. QUESTION: Can the asbestos and/or lead survey performed for the building be provided?

ANSWER: The facility lead and asbestos reports was posted to FedBizOpps under Amendment 0003.

23. QUESTION: (Ref S101) Please provide section details relevant to A thru F/S600.

ANSWER: Refer to sheet S600 for sections.

24. QUESTION: (Ref S111, S112, S113) Please provide section details relevant to A/S500, B/S500, C/S500, D/S500, E/S500, F/S500, G/S500, N/S500, A/S600, G/S600, H/S600, M/S600.

ANSWER: Refer to sheets S500 and S600 for sections.

25. QUESTION: (Ref S121) Please confirm the metal roof deck is to receive concrete infill, if so is thickness similar to the decks below?

ANSWER: The metal roof deck does not receive concrete infill. Just the metal roof deck and new insulation to match existing as indicated on drawing A103.

26. QUESTION: (Ref A113, A011) Please clarify the exterior partition type along ‘M’ line – ECM

Pod Shop C110.

ANSWER: Provide partition type S-1 against existing exterior masonry wall. Refer to details 3/A412 and 3/A551 for similar applications.

27. QUESTION: (Ref A113, A011) Please clarify the exterior partition type along 13’ line – Foam

Room B107.

ANSWER: Provide partition type S-1 against existing exterior masonry wall. Refer to details 3/A412 and 3/A551 for similar applications.

28. QUESTION: (RFP page 10 of 73) Please confirm that the submission of Volume 2 will be one original and (3) three hard copies

ANSWER: Correct original and 3 copies.

29. QUESTION: (RFP page 12 of 73) Please confirm that only (1) one CD/DVD electronic copy is required and that it shall only contain Volume 2 proposal information.

ANSWER: Correct.

30. QUESTION: (Ref Spec 018000) Please provide the LEED score card specific to this project

ANSWER: The LEED Score Card has been posted to FBO.

31. QUESTION: (Ref Note 12/A111) Drawing A111 note 12 makes reference to a deduct alternate to remove the raised access floor system. Please clarify, on the RFP – Bid Schedule, which option should this value be carried.

ANSWER: Note 12 on sheet A111 is in reference to item 2 in the Base Bid, Raised Floor System. The raised floor will be installed as part of the base bid; the cost just needs to be broken out in the base bid line 2 as shown on the bid schedule. There is no deduct associated with the raised floor.

32. QUESTION: (Ref A402, A021, A022) Note 15 on A021 & A022 indicates that the existing door frames (A111, S001A, S002A, S002B, S003A, S004A, & S004B) are to remain, however there is no indication on the door schedule that any door frames are to remain.

Please clarify which direction is correct.

ANSWER: Frames are labeled as “Existing” in the Door Frame column for Type, Material, Head Detail, and Jamb Detail on A402 as well as A403 for all frames which are to remain.

33. QUESTION: (Ref Spec 102226) Please indicate the locations of the operable partitions, or confirm that they are not included on this project.

ANSWER: Operable partitions are part of this contract. See note on plan on sheets A121 and A122, “Coordinate Dimensions of Demountable Partition with Manufacturer”.

34. QUESTION: (Ref A401, A113, Spec 096900): Room C123, ECM STG, is scheduled to receive Sealed Concrete as a Deduct Alternate per Remark 10. Please indicate which type of Floor Panel Covering is to be used on the Raised Access Flooring for the base bid in this room.

ANSWER: Room C123 does not receive a raised floor. Room C123 should be sealed concrete. The Remarks on sheet A401 for C123, Remark 10, is incorrect and should be deleted. This will be corrected in Addendum 2.

35. QUESTION: (Ref A113, A123, Spec 142400) Spec Section 142400 indicates that there is 1 Landing and 1 Front opening for Elevator E001. Please confirm that there are 2 Landings and 2 Front Openings per drawings A113 and A123.

ANSWER: This is a 2 Story Elevator, 2 Stops (Main/1st and Upper/2nd). The specification landing description for landings may seem confusing but bid a 2 stop elevator, lower and upper.

36. QUESTION: (Wood Façade) Please confirm WF-16, WF-24 and WF-25 are to be fire rated.

ANSWER: A fire rating is not required as this is not an egress. Refer to Life Safety Plans for required ratings.

37. QUESTION: (Ref Spec 084113) Please confirm locations of SF-01, SF-02, and SF-03 as they are not called specified on the elevation drawings.

ANSWER: Refer below for Storefront Schedule. All interior are SF-01. All North, South, and East elevations are SF-02. The West elevation is SF-03.

SF-01: WF-16, WF-17, WF-24, WF-25, WF-27

SF-02: All other WF

SF-03: WF-06, WF-07, WF-07A, WF-08, WF-09, WF-10, WF-11

38. QUESTION: We would like to request a second walk through for subcontractors to attend, please confirm if this is feasible and provide a date and time for interested subcontractors.

39. QUESTION: (Ref A123, A114) Please confirm all lockers are GFGI. Locker are noted as such on page A123 but no note appears on page A114

ANSWER: All lockers are shown in light print, not bold, and are GFGI.

40. QUESTION: (Ref Bathroom Accessories Schedule) Please confirm Bradley items noted

GFGI on Toilet Accessories Schedule are accurately noted, it seems odd that some Bradley items would be sourced GFGI and others CFCI.

ANSWER: The items noted as GFGI on the Accessories Schedule, on sheet A522, are correct. The GFGI items may or may not be manufactured by Bradly Corporation. This is up to the Government.

41. QUESTION: (Ref A551) Please confirm corner guard height. Detail 2/A551 shows material and wing size but does not mention height, nor does note CG-01 in Finish Material Schedule

ANSWER: Provide 8’ high corner guards.

42. QUESTION: (Ref Spec Section 010100) Section 1.3 - A.2.c.indicates that the relocation of the existing crane from B801 is to be included in the Base Bid. Please provide information for the existing crane (size, type, attachment details, etc.) and the location to where the crane is to be relocated.

ANSWER: The crane will be relocated to room C110, the ECM Pod Shop, as shown on sheets A133, S110, and S114. The crane is a 1 ton crane manufactured by Anchor Crane & Hoist in Dallas and motor is provided by Coffing, Model no ED-2012-3, Serial Number EC1- C-437-VGD. See dwg S114 for crane runaway and associated details. Contact crane manufacturer for attachment details to runway beams. See photos posted.

43. QUESTION: (Ref A581) Please provide a signage schedule or indicate where the signage on A581 is intended to be placed.

ANSWER: Provide (1) type “A” sign for each toilet, (2) type “B” signs for each stair, (1) type “C” sign for each egress stair, and (1) type “D” at the west entry door. Location to be determined in shop drawings. Final location to be determined in field with contracting officer.

44. QUESTION: (Ref A401, A563, A564) In room C102 on page A563 and room C131 on page

A564 it shows that there are grills/mats in front of the doors that lead into the Vestibules, however neither of these grills/mats are labeled on page A401. Please confirm is these mats are FG-01 and if they’re not please identify and label which ones they are.

ANSWER: Correct, provide FG-01 as dimensioned on A563 and A564.

45. QUESTION: (Ref 7/A011) Please provide specification for acoustic foam shown to be installed in the cavity of partition types S4, S7, S9 & S10.

ANSWER: Provide “Open Cell Spray Foam” in all Cavities of S4, S7, S9, and S10 wall type construction. USI, Soft polyurethane, open cell spray foam or similar are acceptable products. This is interior wall construction only.

46. QUESTION: Please confirm floor leveling will be required at existing surfaces to remain.

ANSWER: Where necessary to install floor finish within manufacturer required tolerance, and as required for any floor sloped to drain.

47. QUESTION: In specification section 104416 – FIRE EXTINGUISHERS, paragraph 1.1 SUMMARY it indicates “Section includes portable, hand-carried fire extinguishers, PROVIDED BY OWNER/Contracting Officer.” The drawings indicate (Paragraph 19, Sheet LS001) that SOME of the extinguishers will be provided by the user: “FIRE

EXTINGUISHERS WITHIN THE HANGAR BAYS WILL BE SPACED ALONG THE WALLS

AT A MAXIMUM OF 50 FT ON CENTER. THE USER WILL BE RESPONSIBLE FOR

PROVIDING EXTRA FIRE EXTINGUISHERS THAT SUPPORT THE AIRCRAFT.” Please clarify who is responsible for providing bracket mounted fire extinguishers and cabinet mounted fire extinguishers in Fire Extinguisher Cabinets shown on the LS 101 and LS 121 Drawings.

ANSWER: Government provides the extinguisher. Contractor provides and mounts cabinets and/or brackets

48. QUESTION: Do fluorescent bulbs need to be recycled or disposed of separately to comply with LEED construction waste requirements?

ANSWER: Yes

49. QUESTION: Sheet E003 and E004 list general notes that state demolish all lights fixtures, electrical devices, communication outlets, conduit, boxes, supports, conductors, devices and accessories unless otherwise indicated. Is there a set of as built drawings that can be provided that would show what electrical is existing that is to be demolished?

ANSWER: Drawings from 1956 are not specific – demolish all.

50. QUESTION: If no electrical as built drawings can be provided, can another site visit be held?

ANSWER: No

51. QUESTION: Is the government removing the network equipment and DMARK in the existing communication room?

ANSWER: The Government will remove its network equipment. Anything remaining is to be demolished.

52. QUESTION: At the site walk, it appeared that there are multiple communication rooms that are not shown on the plans. Are we to demo all comm that the government leaves in these rooms?

ANSWER: Yes. Anything remaining is to be demolished.

53. QUESTION: The LEED spec outlines all the LEED construction credits. Can the entire

LEED scorecard be provided for reference?

ANSWER: Yes. It has been posted to FBO.

54. QUESTION: In section 018000 under item 2.3 B there are no products listed. Please clarify what products can be used and what the VOC content limits are.

ANSWER: The VOC Content limits are listed in each spec section that has those requirement for each product.

55. QUESTION: Please provide an Asbestos and Lead Report/Survey for Building 909.

ANSWER: The facility lead and asbestos reports will be posted to FedBizOpps.

56. QUESTION: Is there an industrial hygienist (air monitoring specialist) already hired for this project? If so, who is it?

ANSWER: No. The certified asbestos building inspector/industrial hygienist shall be provided by the Contractor and be included in the contractors bid for this project.

57. QUESTION: Please provide a Geotechnical Report.

ANSWER: Geotechnical report was posted under Amendment 0003.

58. QUESTION: Does the hangar door work have to be performed and/or supervised by representatives or employees of the existing hangar door manufacturer? If so, please provide the name of the manufacturer of the existing hangar doors.

ANSWER: No.

59. QUESTION: None of the bollards shown on the plans match the specified bollard in 12 93

00. Plans show round steel bollards (concrete-filled and painted), but section 12 93 00 2.1A lists a 14” square concrete bollard. Please advise.

ANSWER: Refer to 1/C500 and 21/C504 for round bollard details. There will be no 14” square concrete bollards or light bollards in the project, delete spec reference to precast bollard and light bollard spec section 129300 para 2.1. A. 4 & 5.

60. QUESTION: Please confirm that the 14” square concrete bollards listed in section 12 93 00

2.1A are to be surface mounted.

ANSWER: N/A. There will be no 14” square concrete bollards, delete spec reference, product not used.

61. QUESTION: 12 93 00 2.1A lists an ash receptacle/urn that is not found on the plans.

Please advise.

ANSWER: Locate (1) urn in field with contracting officer. Must be more than 25’ from a building entrance. RE: Civil for all Trash Receptacle locations.

62. QUESTION: Please provide detail for screen wall shown on C100

ANSWER: The screen wall detail is shown on the structural drawing S603 and on A111, A112, and A551.

63. QUESTION: What government furnished items will the contractor be required to install?

ANSWER: All items noted in the drawings or specifications as GFGI (Government Furnished /Government Installed). Of those shown on the Government Furnished Materials list shown in 52.245-2, page 51 of the solicitation, all 11 items shall be contractor installed.

64. QUESTION: Will WF-16, WF-24, WF-25 window systems need to be a fire rated system?

ANSWER: Refer to question 36.

65. QUESTION: The specifications identify 3 different window systems:

Please designate what specification to use for each window type.

ANSWER: Refer to question 37.

66. QUESTION: Please provide the charge weight and standoff distance for the blast criteria.

ANSWER: Please refer to spec section 081113, 084113 and 085123 have the necessary requirements.

67. QUESTION: Translucent Wall Panel 3/A-551. Would the government consider making the lami interlayer frosted and completely remove this extra item?

ANSWER: Bid per drawings and specs.

68. QUESTION: Geothermal Wells: Would the engineer consider drilling more wells and only going to a depth of 400’?

ANSWER: Due to limited space (due to other utilities in the area), we had to design to the 500’ depth for the wells.

69. QUESTION: A103 shows a continuous fall protection system but the plans do not provide any details and or other information to estimate this. No specifications are given either.

Please provide more information so accurate pricing can be given.

ANSWER: Refer to S121 protection rail requirements.

70. QUESTION: Will on site personnel be allowed to handle multiple roles? For example will the on-site superintendent also be allowed to handle safety or quality control?

ANSWER: The contractor must be able to perform and meet all the requirements of the contract with the personnel provided. Please see revised specification section 010000, General Requirements, paragraph 1.51 (in Amendment 0004)

71. QUESTION: What type of circuit configuration is the engineer’s intention? Plan C101 shows a Reverse Return design while plan M503 shows a Horseshoe configuration.

ANSWER: The circuit configuration is a reverse return design, the detail on M503 does show the reverse return design, but since it is a piping schematic it will look different than the piping layout but the concept is the same.

72. QUESTION: Will the engineer please provide a circuit detail showing pipe graduations for designed flow? i.e., at which well(s) does the 3” step down to 2” and so forth

ANSWER: Graduations are as follows: 3” for the first three wells, reduce to 2”, then reduce to 1 ¼’ after well six. On the return, 1 ¼” for the first two wells, increase to 2” for the next three wells, then increase to 3” for the last three wells.

73. QUESTION: Plan C101 shows (32) wells while plan M503 depicts (64) wells. Please confirm the number of geothermal wells.

ANSWER: C101 shows 64 wells. 32 are located under part of the parking lot (Loops A, B, C, and D are under the parking lot and Loops E, F, G, H are located NW of the parking lot).

74. QUESTION: Do to the number of outstanding questions, will contracting consider extending the proposal due date?

ANSWER: The proposal due date has been extended to 28 Jul 2016. See amendment 0003.

75. QUESTION: The plans reference a soils report for the project. I did not see the soils report included in the documents provided. Can the government provide the soils report for the project?

ANSWER: The Contaminated Soil Management Plan was posted to FBO under Amendment 0003.

76. QUESTION: SECTION 018000 SUSTAINABLE DESIGN MEASURES references Table 1 for a list of LEED-NC 2009 credits/prerequisites. This table is not found. Please provide so we can review which credits the construction team is responsible for.

ANSWER: The LEED Table has been posted to FBO.

77. QUESTION: Are the bid options to be additive to or deductive from the base bid price?

ANSWER: Bid Options are additive (addition to the base bid). However it is possible to be a negative number, for instance, if to install “Bid Option 6: Install ECM POD Shop Low Profile Crane” cost less than the base bid to relocate the crane from Hangar 801.

78. QUESTION: Please provide specifications/size/information on existing crane to be relocated from Hangar 801.

ANSWER: See question 42 above.

79. QUESTION: Will a building permit be required for this project and has the owner submitted drawings for approval by the AHJ (Authority Having Jurisdiction)?

ANSWER: A building permit is not required. However, Specification Section 010020 identifies other required permits i.e. digging permits, FAA, environmental, welding, equipment, etc. QC and testing shall be provided by the contractor, and the government will provide QA and shall be allowed to conduct any testing and inspections as desired.

80. QUESTION: Based on the extensive set of construction documents and from feedback form our subcontractors providing a comprehensive and accurate estimate for the work involved in the Hanger upgrades we would like to request a bid extension. Please confirm if an extension will be approved.

ANSWER: The proposal due date has been extended to 28 Jul 2016. See Amendment 0003.

81. QUESTION: Will the government please designate what areas are going to be occupied by the Air National Guard, Air Force Space Command, and Army National Guard for bid options 7A, 7B, 7C."

ANSWER: The Air Force Space Command area is the same as identified in Bid Option 1 and in Specification Section 010100 paragraph 1.3. B. 1. (Rooms A103, A104, A105, A106, A107, A112, A114, A115, B106, B108, B110, C129, C130, A206, A207, B202, C202, C203, C212, D202, and D203). The Army National Guard area is the same as identified in Bid Option 2 and in Specification Section 010100 paragraph 1.3. B. 2. (Rooms B104, B109, D206, and D207).

The Air National Guard area is all other remaining rooms and portions of the building.

82. Spec 010100 section 1.2 A 1 states that "Mission Training Center (MTC) shall be fully function and ready for the government to move in by April 15, 2017. This would include all power and communications is in place and fully functional and HVAC equipment is in place, tested and balanced, commissioned and connected to the Base wide BACnet system." The April 15, 2017 date is earlier than the completion date than the completion date for the rest of the project. The following factors need to be considered:

- Mechanical and Electrical equipment have long lead times and have to be approved through the submittal process prior to ordering

- Support facilities such as restrooms, breakroom for employees to allow the MTC to be ready for the government to occupy

- Life safety and egress requirements for occupants

- LEED certification after a portion of the building is occupied

- Government or other contractor access to building while construction is under way

- Asphalt paving cannot be completed until late spring or summer

- Construction site is not scheduled to be completed until the end of the project

Due to these factors several items need to be clarified:

a) Is it the governments intent to occupy the MTC on April 15, 2017 or will government be doing more construction/installation activities after April 15, 2017?

ANSWER: The government will not occupy (with personnel) the MTC until the project is completed. The MTC equipment will be delivered and stored in this area following 15 April 2017.

b) Can the April 15, 2017 date be extended?

ANSWER: No.

c) Can the level of finish of the MTC area on the April 15, 2017 date be reduced?

ANSWER: No.

d) Which room numbers are included in the MTC area?

ANSWER: Room C113 (MTC Sim Area 1), C120 (Brief), C125 (MTC Sim Area 2), D101 (Server), and D102 (Brief).

e) Will bathrooms, hallways, breakrooms or other support facilities adjacent to the MTC, in the building, be required to be completed by the April 15, 2017 date to allow for the government to occupy the MTC?

ANSWER: No.

f) If these areas are not required, who is responsible for providing temporary facilities for government employees?

ANSWER: The area will not be occupied by personnel. No temporary facilities will be required.

g) What will be the means of egress for government personnel from the MTC area during the remaining construction process?

ANSWER: The area will not be occupied by personnel. No egress required.

h) What safety requirements are there to keep government personnel safe while the construction process is being completed?

ANSWER: The area will not be occupied by personnel. Not required.

i) How will government personnel be moving through the construction zone to access the

MTC?

ANSWER: The area will not be occupied by personnel. Only government inspectors will be moving through the site as in any other government project.

j) MTC is to be commissioned prior to April 15, 2017. Will the MTC area be required to be re-commissioned upon substantial completion when the entire project is commissioned?

ANSWER: No. Unless the startup of the remainder of the facility effects the systems in that area.

k) LEED certification for clean air will take place at project completion not at MTC turnover.

Will we be required to do duct cleaning and maintain clean air levels in MTC during the period between April 15, 2017 and project completion?

ANSWER: Yes, you will need to provide filters at the return-air and the system filters, and a final duct cleaning if needed for LEED certification. You should only need limited access back into the MTC area after 15 April 2017, as it is on its own system.

l) Will a portion of the construction site be required to be completed prior to April 15, 2017 to allow access?

ANSWER: No.

m) Are we to have the parking lot complete before April 15, 2017 to allow for government parking?

ANSWER: No.

83. What is the typical approval duration for personnel listed on the Entry Authorization list as described in Specification Section 010000 General Requirements?

ANSWER: The approval time to allow access on base (through DBID) is a minimum of 72 hours, and should not take much longer than that. Once approved they will have access as long as they are required to complete their work on the project. For instance the project superintendent will be approved for the duration of the project, where a subcontractor installing the temporary fencing may only be approved for a week or two. The duration is task specific.

84. QUESTION: The blast window manufacturer has stated they will need an additional two weeks in order to provide a firm fixed price proposal for the storefront window system required by the drawings. Will the gov't grant an extension so that proper pricing can be received and provided in our bid to the gov't?

ANSWER: The storefront window systems has not changed since the original posting of the plans and specs on June 17. The due date will not be extended.

85. QUESTION: The amendments have issued changes and clarification to the bid schedule. Can an updated bid schedule be provided?

ANSWER: The amendment only made changes to the CLINS that are for accounting purposes.

The Bid Schedule has not been changed. A new bid schedule will not be issued since it had not changed.

86. QUESTION: Section 08342 Hangar Door Repair, Insulation on interior of Hangar Door:

Insulation will be removed in areas that will require work. Does it need to be replaced in kind? Can a specification covering insulation be provided?

ANSWER: Yes, the insulation shall be replaced. A minimum of R-11 Insulation in these doors which might just require 2” of spray foam. Amendment 0005 has been issued to address this.

87. QUESTION: Section 08342 Hangar Door Repair, Explosion Proof Specification:

a. Drawing S700 (and S701), General Hangar Door Notes, #5: Replace all electrical devices below the height of the top of the hangar door with devices rated for use in Class 1 Division 2 Area. Is this accurate (prices on explosion proof components are significantly higher than standard)? Does this apply to the electrical cable reel mounted at the top of the door but wired to the lower leaf?

ANSWER: Hanger door electrical equipment to remain. Refer to drawing E107 for new power connection to existing hangar door equipment. Remove Note 5 from drawings S700 and S701. Amendment 0005 has been issued to address this.

b. Drawing S700 (and S701), General Hangar Door Notes, #3: Replace Hangar Door

Stops. Is the expectation for the entire bumper to be replaced or the rubber bumper on each unit?

ANSWER: Both, the entire bumper and the rubber bumper on each unit.

88. QUESTION: Section 08342 Hangar Door Repair, 1.03: Performance Requirements.

a. Existing sliding doors (two on each side of the vertical lift door) – Bottom rail: Facility personnel stated during the site visit that weather changes cause the bottom rail to curve up and makes door operation very difficult. There’s no mention of repairing or replacing of bottom rails in specifications. Do we provide repairing or replacement of bottom rails as an option?

ANSWER: No option will be provided for the repairing/replacement of bottom rail.

b. Existing sliding doors (two on each side of the vertical lift door) are manually operated. Ref. “a” (above) – Adding a manual drive/hand crank would ease operation of the doors. Can this be added as a line item option?

ANSWER: No option will be provided for a manual drive/ hand crank.

c. Vertical Lift Door – Section 1.03, A GENERAL: Door does not have a safety edge which would stop door when closing and made contact with foreign object (aircraft, equipment parked in clear opening, etc.). We recommend this be added to the hangar door scope of work and integrated into the existing door controls.

ANSWER: The safety edge integrated in the existing door controls will not be added to the scope of work.

89. QUESTION: It appears that power is to be disconnected to the building at the beginning of the project, and that the existing electrical gear, MV XFMR, and generator/enclosure are to be removed, so all civil work can begin and then the new service and generator enclosure reinstalled after all new concrete and asphalt is finished. Is temporary power required within Building 909 during construction, the electrical drawing E002 references two different sets of trailers requiring temporary power and where to obtain the power, but nothing is indicated for the building itself; if temporary power for Building 909 is required, what is the source for the temporary power and are there any other specific requirements or specifications?

ANSWER: The generator and enclosure will be removed and stored to complete the equipment and concrete pad. Temporary power is not required in building 909 for the government’s purpose. Only what is required by the Contactor. Contractor is to provide temporary power and power panel to distribute power to lights and other construction needs while electrical SWBD and primary feed is being demolished and replaced.

90. QUESTION: As mentioned above it appears that the existing generator/enclosure is to be removed and reinstalled per C002, yet E003 states the generator is to remain and not part of the scope of work, also electrical one-line on E701 references that the generator is to be by others at a later date,

a. Will the new generator be installed, after the project is finished?

ANSWER: Yes. Drawing C002, is correct. The generator shed needs to be removed to allow the pad to be replaced. The new generator is not part of this project and will be installed after this contact by others.

b. Please clarify the generator scope of work, is it the electrical contractor’s responsibility to remove the existing generator and enclosure, and then re-install the existing and perform all necessary startup & testing procedures?

ANSWER: The generator scope is to:

1) The electrical contractor is responsible for removing and re-installing the generator and enclosure.

2) Disconnect existing generator from existing ATS. Do not demolish.

3) Remove conductors and conduit between generator and existing ATS.

4) Install new ATS in existing generator enclosure as shown on drawings with feeds to SWBD and EP1 located in Bldg 909.

5) Reference drawing E003 for additional demolition scope for generator enclosure.

6) Reference drawing E100 and E200 for additional installation scope for generator enclosure.

Testing:

1) No testing is required to the existing generator.

2) The new ATS is to be tested before construction completion. To test ATS, a temporary generator is to be provided.

c. Is just the enclosure to be removed and reinstalled?

ANSWER: Yes, the enclosure and all contents is to be removed and reinstalled. With keeping in mind the additional scope for this enclosure.

d. Will all generator work be performed by others with the exception of the new ATS & Panel EM-1?

ANSWER: Refer to one-line diagram on drawing E701, dashed area with keyed note #3. All work with the exception of the installation and testing of generator and conductor and conduit between ATS and generator are to be part of the scope of work

91. QUESTION: If the generator is to remain in place during the project, can it be utilized for any temporary power if necessary, and/or during the replacement of the MV XFMR?

ANSWER: The generator will not be used during the period of construction.

92. QUESTION: Both electrical drawings E007 & E110, Detail 4, reference Fire Pump XFMRs, but electrical one-line on E701 does not indicate any XFMRs associated to the Fire Pumps, are there any XFMRs to be installed for the pumps?

ANSWER: There are no XFMRs for the fire pumps. Just disconnects as shown on the one-line diagram E701. The feeder tag is incorrect. Instead of XFMR-FPCX, it should be DISC-FPCX (see amendment 0006).

93. QUESTION: Are the new feeders for the fire pumps to be routed overhead once they enter the building similar to the condensing unit feeds shown on E101, or is the intent for saw cutting of the existing slab and these new feeders be routed underneath?

ANSWER: Within building 909, route all conduit overhead. It is not intended to saw cut the floor.

94. QUESTION: Is testing & certification of the grounding system required at every location of the new grounding bus bars?

ANSWER: Yes, it is.

95. QUESTION: Are all the new structural columns being installed within the building to be grounded per E403, Detail #3?

ANSWER: Yes, all new columns need to be grounded per detail 3 on dwg E403. All new columns only: route bare copper to foundation rebar and connect with exothermic weld (see amendment 0006).

96. QUESTION: The grounding riser schematic on E402, Detail #1 indicates new 4/0 bare copper to be installed from the main building ground bus in the basement under the first floor, is all of the existing 1st floor slab to be removed during construction allowing us to install the grounding cables this way? S009 indicates concrete saw cutting & removal of the slab to accommodate the new structural & plumbing work, but not any electrical, if the existing slab is to remain with minimal removal, should these new grounding cables be installed overhead and in conduit to protect from damage?

ANSWER: It is not the intent to install in floor slab. Install overhead in conduit to protect from damage and support.

97. QUESTION: Is the electrical contractor responsible for any Arc Flash or Coordination Studies and labeling of all gear with specific arc flash ratings & PPE required, or just the NETA Testing per specs?

ANSWER: NETA testing per specs only.

---End of Questions and Answers as of 26 Jul 2016---