Pavement Crack Repair and Seal Coating, Thomaston Dam, Thomaston, CT
Solicitation number
W912WJ26QA111
Issued by

About this file

This is a Request for Quotation (RFQ) issued by the U.S. Army Corps of Engineers, New England District for pavement crack repair and seal coating services at Thomaston Dam in Thomaston, Connecticut. The contract number is W912WJ26QA111, with a Request Number W912WJ26QA111 issued on March 3, 2026. This is not a small business set-aside. The work is classified under Product Service Code Y1LB and NAICS 237310 (Highway, Street, and Bridge Construction). The estimated contract value is between $25,000 and $100,000. Quotations are due by June 17, 2026, and the contract performance period is 210 calendar days from award. A mandatory site visit has been scheduled for Tuesday, June 9, 2026 at 10:00 AM Eastern at Thomaston Dam Project Office, 331 Hill Road, Thomaston, Connecticut 06787.

The scope of work requires the contractor to provide all labor, materials, equipment, and transportation to repair approximately 1,000 linear feet of cracks on the 2,000-foot dam crest road and apply asphalt emulsion seal coating to the entire surface. Specific work includes mechanical crack routing, high-pressure cleaning, filling cracks exceeding 1 inch with epoxy-based asphalt mortar, and application of water-based asphalt emulsion sealer (flat black color). All materials must comply with ASTM standards and withstand temperatures below 0°F after curing. Work shall be performed Monday through Friday, 7:00 AM to 3:30 PM, with no weekend or holiday work permitted. The contractor must submit pre-construction documentation including an Accident Prevention Plan (ENG Form 6293), Activity Hazard Analysis (ENG Form 6206), Site Safety and Health Officer Designation Letter (ENG Form 6282), and First Aid/CPR certificates within 21 days of award. Payment will be made on a per-job basis after final inspection and acceptance. For contracts valued at $35,000 to $150,000, a payment bond or irrevocable letter of credit (100% of contract price) is required within 10 days of award. For contracts $150,000 or above, both a payment bond/letter of credit and a performance bond are required. Contract Specialist contact: Alicia N. LaCrosse, 978-318-8902, Alicia.N.LaCrosse@usace.army.mil. Technical Point of Contact: Marc D'Amato, marc.a.damato@usace.army.mil, 978-318-8898. Quotations must be submitted via email, signed on SF18 Form blocks 14-16, and include completion of the mandatory solicitation survey. All responsive quotes must demonstrate adequate technical capability, fair and reasonable pricing, and acceptable past performance for contract award.

View the file

Other files

File Type Posted
Amendment W912WJ26QA111-0001.pdf PDF
Attachments 26QA111_Revised.pdf PDF
Attachments 26QA111.pdf PDF
Solicitation W912WJ26QA111.pdf PDF
Solicitation Survey 26QA111.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR QUOTATION

(THIS IS NOT AN ORDER)

THIS RFQ IS IS NOT A SMALL BUSINESS SET-ASIDE

15. DATE OF QUOTATION

16. SIGNER

a. NAME (Type or print)

c. TITLE (Type or print)

b. TELEPHONE

AREA CODE

NUMBER

STANDARD FORM 18 (REV. 6-95)

Prescribed by GSA-FAR (48 CFR) 53.215-1(a)

AUTHORIZED FOR LOCAL REPRODUCTION

Previous edition not usable

8. TO:

b. COMPANYa. NAME

c. STREET ADDRESS

d. CITY e. STATE f. ZIP CODE

9. DESTINATION

a. NAME OF CONSIGNEE

b. STREET ADDRESS

c. CITY

d. STATE e. ZIP CODE

7. DELIVERY

FOB DESTINATION

OTHER

(See Schedule)

10. PLEASE FURNISH QUOTATIONS TO THE

ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS (Date)

IMPORTANT: This is a request for information and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or service. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotation must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State and local taxes)

ITEM NO.

(a)

SUPPLIES/ SERVICES

(b)

QUANTITY

(c)

UNIT

(d)

UNIT PRICE

(e)

AMOUNT

(f)

12. DISCOUNT FOR PROMPT PAYMENT

a. 10 CALENDAR DAYS (%) b. 20 CALENDAR DAYS (%) c. 30 CALENDAR DAYS (%) d. CALENDAR DAYS

NUMBER PERCENTAGE

NOTE: Additional provisions and representations are are not attached.

13. NAME AND ADDRESS OF QUOTER

a. NAME OF QUOTER

b. STREET ADDRESS

c. COUNTY

d. CITY e. STATE f. ZIP CODE

14. SIGNATURE OF PERSON AUTHORIZED TO

SIGN QUOTATION

PAGE OF PAGES

1. REQUEST NO. 2. DATE ISSUED 3. REQUISITION/PURCHASE REQUEST NO. 4. CERT. FOR NAT. DEF.

UNDER BDSA REG. 2

AND/OR DMS REG. 1

RATING

5a. ISSUED BY 6. DELIVER BY (Date)

5b. FOR INFORMATION CALL (NO COLLECT CALLS)

NAME TELEPHONE NUMBER

AREA CODE NUMBER

Section A - Solicitation/Contract Form

Pavement Crack Repair and Seal Coating, Thomaston Dam, Thomaston, CTInstrument Name:

Product Service Code : Y1LB

W912WJ26QA111

Section B - Supplies or Services & Prices or Costs

Additional Information/Notes

Item Supplies/Service Quantity Unit Unit Price

Amount

0001 Contractor shall provide all labor, materials, equipment, and transportation to provide pavement crack repairs and seal coating to the dam crest road at Thomaston Dam, Thomaston, CT in accordance with the Statement of Work.

Product Service Code: Y1LB North American Industry Classification System (NAICS): 237310 Pricing Arrangement: Firm Fixed Price

1 Job

Section C - Description/Specifications/Statement of Work

INTERESTED VENDORS SHALL REVIEW SECTION L AND SECTION M OF THE

SOLICITATION FOR INSTRUCTIONS AND EVALUATION CRITERIA. VENDORS ARE

RESPONSIBLE FOR ENSURING THEIR QUOTE SUBMISSION MEETS ALL REQUIREMENTS.

FAILURE TO DO SO MAY RESULT IN QUOTES BEING DEEMED NON-RESPONSIVE AND

REMOVED FROM CONSIDERATION.

THE MANDATORY SOLICITATION SURVEY SHALL BE COMPLETED IN ITS ENTIRETY AND

RETURNED WITH QUOTES. FAILURE TO DO SO MAY RESULT IN QUOTES BEING DEEMED

NON-RESPONSIVE AND REMOVED FROM CONSIDERATION.

STATEMENT OF WORK:

PAVEMENT CRACK REPAIR & SEAL COATING

U.S. ARMY CORPS OF ENGINEERS

THOMASTON DAM

THOMASTON, CONNECTICUT

STATEMENT OF WORK

I. GENERAL

1. Summary:

Provide all labor, materials, equipment, and transportation necessary to repair pavement cracks and seal coat the dam crest road at Thomaston Dam in accordance with the Statement of Work.

2. Location:

Thomaston Dam is located at 331 Hill Road, Thomaston, CT 06787. See the attached informational photos for more detailed location information.

3. Site Visits:

Site visits are strongly recommended to gauge the full scope of work and provide an accurate quote.

A scheduled site visit for interested vendors will be listed in the solicitation. Interested vendors should attend the site visit to confirm understanding of the scope, inspect field conditions, access, and existing utilities prior to bidding. No extra payment will be allowed for perceived additional work caused by unfamiliarity with site conditions and requirements.

Please note, site visits outside of these specific date and time are not permitted unless additional site visit dates/times are publicized in an amendment. All questions during site visit will be sent to the Contract Specialist as indicated in the Instructions to Vendors and responses will be provided in an amendment. Information incorporated into the solicitation via amendment will become binding.

4. Technical Point of Contact:

The Technical Point of Contact for this project is Civil Engineering Technician Marc D'Amato, marc.

a.damato@usace.army.mil (978)318-8898.

5. Schedule:

The period of performance shall be 210 days from Contract Award date. Work shall be performed Monday through Friday between the hours of 7:00 AM and 3:30 PM unless otherwise approved by the Technical Point of Contact. Any proposed changes to an approved schedule must be submitted to the Technical Point of Contact in writing and are not finalized until approved. No work shall be done on weekends or Government holidays.

All pre-construction submittals shall be submitted within 21 days of Contract Award. The Government reserves up to 21 days for review and acceptance on each submittal/resubmittal from the date of receipt. If revisions are necessary to the submittals, the Contractor shall make such revisions and shall be resubmitted to the Government in an acceptable form within 14 days of the Government's response, unless additional time is granted by the Government in writing.

No field work may proceed prior to the acceptance of pre-construction submittals.

6. Safety Requirements:

a. General:

All work shall be conducted in accordance with the U.S. Army Corps of Engineers (USACE) Safety and Occupational Health Requirements (EM 385-1-1, most recent edition), and all applicable Occupational Safety and Health Administration (OSHA), federal, state, and local safety and health requirements. A copy of EM 385-1-1 can be accessed electronically at the following link:

https://www.publications.usace.army.mil/Portals/76/EM%20385-1-1%20_EFFECTIVE% 2015March2024.pdf

Project staff reserve the right to cease work at any time should the safety of employees, Contractors, and/or the public become jeopardized.

b. Accident Prevention Plan (APP):

The Contractor shall prepare a site-specific Accident Prevention Plan. The APP must be written by a Competent Person (CP) and document the specific work processes, equipment, materials to be used, hazards and applicable control measures.

The mandatory ENG Form 6293 (Accident Prevention Plan Worksheet) must be submitted and accepted prior to beginning on site work:

https://www.publications.usace.army.mil/Portals/76/Eng_Form_6293_2023Aug31.pdf

A preparatory meeting shall be conducted by the Prime Contractor to discuss the APP contents with all effected onsite employees. The Prime Contractor is responsible for informing the subcontractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.

Daily safety meetings shall be held and documented. Records shall be available to the Technical Point of Contact upon request.

c. Activity Hazard Analysis (AHA):

An AHA shall be submitted and accepted for each definable feature of work (DFOW) in accordance with EM 385-1-1, Chapter 2-6. A DFOW is defined as any task, which is separate and distinct from other tasks, has separate control requirements, or is identified as different trades or disciplines. The AHA shall be continuously reviewed and revised to address changing site conditions as appropriate.

For a non-mandatory formatted outline of an AHA, see ENG Form 6206 (Activity Hazard Analysis) https://www.publications.usace.army.mil/Portals/76/Eng_Form_6206_2023Aug24.pdf

d. Site Safety and Health Officer (SSHO) Requirements:

The Contractor shall employ a minimum of one person to function as a Level 3, SSHO. A Level 3 SSHO is a designated Qualified Person (QP) or Competent Person (CP) with Safety and Occupational Health (SOH) responsibility that meets the requirements of EM 385-1-1, Chapter 2-3.

b and 2-4.b.

Level 3 SSHOs must have training, knowledge, and/or experience identifying hazards and implementing controls for the work being performed.

The SSHO shall be present at the project site and be responsible for overseeing the implementation of the Prime Contractor's SOH program. Contractor shall designate all SSHOs on a mandatory ENG Form 6282 (Site Safety and Health Officer Designation Letter):

https://www.publications.usace.army.mil/Portals/76/Eng_Form_6282_2023Aug28.pdf

e. First-Aid and CPR Personnel Requirements:

For shifts with multiple employees, provide at least two employees that are certified to administer First Aid and CPR. When employees work alone, they must be certified in First Aid and be provided an effective means of communication to call for assistance in the event of an emergency.

Minimum First Aid and CPR qualifications are outlined in EM 385-1-1, Chapter 3-3.

f. Additional Personnel Requirements:

Other Competent Person (CP) or Qualified Persons (QP) may be required per EM 385-1-1 and/or other sections of this Scope of Work, based on the definable features of work for this project.

g. Accident Reporting:

All accidents and near misses shall be investigated by the Contractor and reported to the Technical Point of Contact in accordance with EM 385-1-1, Table 2-1.

The mandatory ENG Form 3394 shall be completed and submitted to the Technical Point of Contact within seven (7) days of an incident: https://www.publications.usace.army.mil/Portals/76 /Publications/EngineerForms/Eng_Form_3394_2021Aug.pdf

h. Employee Exposure Data:

The Contractor shall electronically report total employee work hours (including subcontractors) to the Technical Point of Contact by close of business on the 10th calendar day of the following month.

7. Pre-Construction Conference:

Prior to the start of any site work, the Technical Point of Contact will schedule and conduct a pre-construction conference. The Contractor's Project Manager and Quality Control Personnel will be physically present to attend this meeting. The Contractor shall directly oversee all work on the project, and the Project Manager and Quality Control Personnel shall have the authority to act on behalf of the Contractor. This conference will be held at the time and location agreeable to the Government and Contractor. No site work may be performed under this contract prior to this conference. The purpose of the conference is to enable the Technical Point of Contact to outline the procedures that will be followed by the Government in its administration of the contract, and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government's administration and inspection of contract work or obtain other pertinent information that might be required. At the pre-construction conference the Contractor shall provide the name of the project superintendent with a telephone number for project coordination.

The following is a general list of items for discussion during this pre-construction conference:

Authority of the Technical Point of Contact

Contractor's Safety Program (including sub-contractors)

Accident Prevention Plan and Activity Hazard Analysis

Accident Reporting (ENG Form 3394)

Correspondence, Communication and Administrative Procedures

Invoice and payment

8. Permits:

The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable federal, state, county, and municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.

9. Security:

The Contractor will comply with all established security policies at the project. Due to periods of heightened security that may affect the access to the areas covered under this contract, areas may be subject to periodic closures, which in turn may reduce or inhibit the Contractor's ability to access certain areas. During periods of heightened security, the Government reserves the right, at any time, to close any property or portion of property and reschedule and/or cancel any subsequent work in an area. The Contractor shall be given at least 24-hour notice of any such closure.

10. Payment:

Payment shall be made on a per job basis. After final inspection and acceptance by the Government, the Contractor must submit an invoice to the Technical Point of Contact. The invoice shall include the invoice date, contract number, dates of work, description of work, quantities, process, and total amount due per line item. For jobs greater than 30 days the Contractor may request multiple payments.

II. TECHNICAL

1. Submittals:

Although the Government reviews submissions required by this Statement of Work, it is emphasized that the Contractor's work must be completed using proper internal controls and review procedures. The Government reserves up to 21 days for review and acceptance on each submittal/resubmittal from the date of receipt. If revisions are necessary to the submittals, the Contractor shall make such revisions and shall resubmit to the Government within 14 days of the Government's response, unless additional time is granted by the Government in writing.

The documents identified below must be prepared in accordance with the applicable standards, submitted to the Technical Point of Contact for review and accepted by the Government.

Pre-construction Submittals: Submitted within 21 days of Contract Award. Submittals must be accepted before the commencement of any field Work.

ENG Form 6293 (Accident Prevention Plan)

ENG Form 6206 (Activity Hazard Analysis)

ENG Form 6282 (Site Safety and Health Officer Designation Letter)

First Aid and CPR Certificates

Product specification & SDS sheets

All Certification(s) and License(s) as determined by the Statement of Work.

2. Clean Up:

The Contractor shall practice good housekeeping to maintain a safe job site. The Contractor shall keep the work area, including any storage areas, free from the accumulation of waste materials.

Upon completing work in an area, the Contractor shall remove any tools, equipment, and materials that are not the property of the Government. Upon completion of work, the Contractor shall clean up the job site to the satisfaction of the Government.

3. Government Resources:

The Contractor is responsible for providing all materials to complete the project. Unless specified in the contract, the Government will not provide any equipment, telephone services or other resources.

4. Damage to Government and Private Property:

The Contractor shall be responsible for restoring any Government facilities or structures damaged as a result of the firm's operation. The Contractor shall also be responsible for any damage to private property or injury to any person as a result of the firm's operations. The Contractor shall notify the Technical Point of Contact immediately of damage to Government and private property and injury to any person resulting from the firms' operation.

5. Omissions:

This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state, or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.

6. Quality Assurance:

The Contractor is responsible for the quality control of the contract work. The Government has the right to inspect and test all items called for by the contract, to the extent practicable at all times and at all places during the term of the contract.

7. Other Contracts:

The Government may undertake or award other contracts for additional work not related to this contract, and the Contractor shall fully cooperate with other Contractors and Government employees. The Contractor shall not commit or permit any act, which will interfere with the performance of work by another Contractor, or by Government employees.

8. Sustainability & Environmentally Preferred Products:

Under the Comprehensive Procurement Guidelines (CPG) program, the Environmental Protection Agency (EPA) designates products that are or can be made with recovered materials and recommends practices for buying these products. Any designated product that is being offered or supplied under this contract shall meet the minimum recommended content levels as identified under the CPG program. Visit https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program for a complete list of designated products and the associated recommended contents levels. Offerors must be able to demonstrate that each offered products meets minimum content levels upon request.

Furthermore, the Contractor should also meet the BioPreferred Program requirements. The United States Department of Agriculture (USDA) designates certain bio-based products for federal procurement and specifies minimum bio-based content levels for those products. Any designated product that is being offered or supplied under this contract shall meet USDA BioPreferred's minimum bio-based content level. Visit the BioPreferred web site https://www.biopreferred.gov /BioPreferred/faces/pages/ProductCategories.xhtml for the complete list of designated products and the associated minimum bio based content level requirements.

9. Environmental Protection:

Containers for excess and/or waste materials shall be provided by the Contractor at the site, and the site will be inspected/cleaned on a daily basis. No burning is permissible. Water, air, and land resources shall not be adversely impacted during the course of the work. Contractor will take necessary steps to ensure all federal, state, and local environmental regulatory requirements are met.

10. Receiving and Storing Materials:

The Contractor is responsible for protecting any stored material until it is placed in service. The Contractor is responsible for receiving and unloading of delivered goods. Government employees will not receive material or supplies for the Contractor and will not be responsible for damage to Contractor equipment or material.

11. Existing Conditions:

a. Thomaston Dam Crest Road

The dam crest road measures approximately 2,000' in length and is divided into two sections, separated by a concrete spillway channel bridge. The average width of the road measures 18.5' and includes a small turnaround area measuring approximately 3,400ft2. The majority of the dam crest road has a wire guardrail, except for a steel guardrail section which measures approximately 100' in length in the roundabout on the northwest end. Refer to Informational Photos attachment for layout of the work area. Large cracks and voids have formed on the pavement. Some measure greater than 1" in separation. Approximately 1,000 linear feet of cracks exist on the dam crest road which will require repairs prior to seal coating. The dam crest road was last chip sealed approximately twelve years ago.

Dam crest road can be closed off for use starting at the gate (see Informational Photos), so some means of closure will be necessary between Hill Road and the dam crest road gate.

12. Products:

a. Hot Pour Crack Filler

i. Must conform to ASTM D6690 Type II, ASTM D3405, AASHTO M324 Type II & AASHTO M301 requirements.

ii. Hot applied oil jacketed crack filler

iii. Must be tested to withstand temperatures below 0(d) F after curing.

b. Asphalt Mortar

i. Epoxy-based asphalt overlay mortar

ii. Aggregate size: 1/4" and smaller

c. Asphalt Emulsion Sealer

i. Water-based asphalt emulsion sealant

ii. Color: Flat black

iii. Must be tested to withstand temperatures below 0(d) F after curing.

Note: The Contractor is responsible for ensuring that the sealant permanently bonds to the repair mortar. All products used must be compatible with each other to prevent material failure or delamination.

III. EXECUTION:

Installation of products and execution of work shall occur in accordance with the Statement of Work and all local, state, and federal requirements. The Contractor is responsible for ensuring that all surfaces are prepared according to manufacturer's specifications before all products are applied. No products shall be applied if site conditions including humidity, temperature, or other factors are not within the manufacturer's specified ranges.

1. Dam Crest Road

a. Clear and repair all cracks along Dam Crest Road.

i. The Contractor shall remove all old sealant from cracks and voids by means of mechanical crack routing.

ii. The Contractor shall clear all cracks and voids of all loose particulates, or to a depth of 3" in places where the pavement has entirely split, by means of either high-pressure water or high-pressure air to ensure adhesion of new material.

iii. The Contractor shall fill all cracks and voids measuring more than 1" in separation and/or 1" in depth with asphalt mortar and compact newly added material.

iv. After newly added asphalt mortar has completely cured, the Contractor shall use a hot air lance to remove moisture and melt residual sealant before applying asphalt sealer atop all cracks and voids that were filled with new material.

v. The work area is a common path for pedestrians and vehicles. Although the dam road vehicle access gate can be closed by staff, the Contractor will be required to post signage, traffic cones, or some other visual aid to alert visitors to the application. Signage is required to remain onsite until the sealer has fully cured, at which point the Contractor is required to remove the visual aid.

vi. Hot pour crack filler and asphalt mortar will not be applied if conditions do not meet the manufacturer's specifications including humidity, temperature, or other factors. Project staff may postpone application of hot pour crack filler if weather reports are not within manufacturer's required ranges.

b. Prepare the entire asphalt surface and apply an asphalt emulsion sealer. The sealant must be smooth and of uniform consistency after fully curing.

i. The Contractor is responsible for reclaiming the edge of the paved surface. Years of dirt and debris may have pushed the exposed edges inwards.

ii. During the application of asphalt emulsion sealer, the Contractor is responsible for deploying signage and traffic cones along the perimeter of the work area as a visual indicator to the public, particularly at the intersection of Hill Rd and the dam crest road and at the bottom of the pedestrian staircase from Vista parking area.

iii. All signage and traffic cones must remain in place for the entire cure time as listed in the manufacturer's specifications.

*** END OF NARRATIVE ***

Requirements Pavement Crack Repair and Seal Coating, Thomaston Dam, Thomaston, CT

Section E - Inspection and Acceptance

FAR Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.246-12 Inspection of Construction. 1996-08

Section F - Deliveries or Performance

0001 Delivery Schedule From date of lead time event to completion of performance 210 Calendar Days

Date of Award 1 JobQuantity

Address and POC Place of Performance DoDAAC: 961103 CountryCode: USA

CORPS OF ENGINEERS NEW ENGLAND DIST

NEW ENGLAND DIST PROJ MGR THOMASTON, 331 HILL RD ROUTE 222

THOMASTON, CT 06787-1311 UNITED STATES

MARC A D'AMATO, DELIVER_TO_EMP_ID_NO

Section G - Contract Administration Data

DFARS Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

252.232-7003 Electronic Submission of Payment Requests and Receiving Reports.

2018-12

252.236-7000 Modification Proposals--Price Breakdown.

1991-12

DFARS Clauses Incorporated by Full Text

Number Title Effective Date

Alternate Deviation

Variation Effective Date

252.232-7006 Wide Area WorkFlow Payment Instructions.

2023-01

WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (JAN 2023)

(a) Definitions. As used in this clause-

"Department of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organization.

"Document type" means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

"Local processing office (LPO)" is the office responsible for payment certification when payment certification is done external to the entitlement system.

"Payment request" and "receiving report" are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) Electronic invoicing. The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) WAWF access. To access WAWF, the Contractor shall-

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web- Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the WAWF home page at https://wawf.eb.mil/

(e) WAWF methods of document submission. Document submissions may be via web entry, Electronic Data Interchange, or File Transfer Protocol.

(f) WAWF payment instructions. The Contractor shall use the following information when submitting payment requests and receiving reports in WAWF for this contract or task or delivery order:

(1) Document type. The Contractor shall submit payment requests using the following document type(s):

(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.

(ii) For fixed price line items-

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.

(Contracting Officer: Insert applicable invoice and receiving report document type(s) for fixed price line items that require shipment of a deliverable.)

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.

(Contracting Officer: Insert either "Invoice 2in1" or the applicable invoice and receiving report document type(s) for fixed price line items for services.)

(iii) For customary progress payments based on costs incurred, submit a progress payment request.

(iv) For performance based payments, submit a performance based payment request.

(v) For commercial financing, submit a commercial financing request.

(2) ) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.

[Note: The Contractor may use a WAWF "combo" document type to create some combinations of invoice and receiving report in one step.]

(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF Data to be entered in WAWF Pay Official DoDAAC ____ Issue By DoDAAC ____ Admin DoDAAC ____ Inspect By DoDAAC ____

Ship To Code ____ Ship From Code ____ Mark For Code ____ Service Approver (DoDAAC) ____ Service Acceptor (DoDAAC) ____ Accept at Other DoDAAC ____ LPO DoDAAC ____ DCAA Auditor DoDAAC ____ Other DoDAAC(s) ____ (*Contracting Officer: Insert applicable DoDAAC information. If multiple ship to/acceptance locations apply, insert "See Schedule" or "Not applicable.")

(**Contracting Officer: If the contract provides for progress payments or performance-based payments, insert the DoDAAC for the contract administration office assigned the functions under FAR 42.302(a)(13).)

(4) Payment request. The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

(5) Receiving report. The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F.

(g) WAWF point of contact.

(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.

(Contracting Officer: Insert applicable information or "Not applicable.")

(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.

(End of clause)

Section H - Special Contract Requirements

SECURITY REQUIREMENTS:

General security requirements and guidance: The security requirements described below apply to all contract personnel (including employees of the prime Contractor ("Contractor") and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the designated Government representative (eg., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as "RAMs"), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures -this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clauses of this contract, should FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.

Suspicious Activity Reporting training (e.g. iWATCH, CorpsWatch, or See Something, Say Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.

WAGE DETERMINATIONS:

The Wage Determination for this project can be found at:

https://sam.gov/wage-determination/CT20260001/2

W912WJ26QA111

https://sam.gov/wage-determination/CT20260001/2

Wage Determination No.: CT20260001

Modification No.: 2

Revised Date: 18 May 2026

*** END OF NARRATIVE ***

Section I - Contract Clauses

UAI 5152.249-9000 Basis for Settlement of Proposals

Actual costs will be used to determine equipment costs for a settlement proposal submitted on the total cost basis under Federal Acquisition Regulation (FAR) 49.206-2(b). In evaluating a termination settlement proposal using total cost basis, the following principles will be applied to determine allowable equipment costs.

(a) Actual costs for each piece of equipment, or groups of similar serial or series equipment, need not be available in the contractor's accounting records to determine total actual equipment costs.

(b) If equipment costs have been allocated to a contract using predetermined rates, those charges will be adjusted to actual costs.

(c) Recorded job costs adjusted for unallowable expenses will be used to determine equipment operating expenses.

(d) Ownership costs (depreciation) will be determined using the contractor's depreciation schedule (subject to the provisions of Federal Acquisition Regulation (FAR) 31.205-11).

(e) License, taxes, storage and insurance costs are normally recovered as an indirect expense and unless the contractor charges these costs directly to contracts, they will be recovered through the indirect expense rate.

(End of Clause)

52.211-10 Commencement, Prosecution, and Completion of Work.

The Contractor shall be required to (a) commence work under this contract within calendar 21 days after the date the Contractor receives the notice to proceed (contract award shall be considered notice to proceed if less than the bonding threshold), (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than calendar days from notice to 210 proceed (contract award shall be considered notice to proceed if less than the bonding threshold).* The time stated for completion shall include final cleanup of the premises.

(End of clause)

52.236-27 Site Visit (Construction) .Alternate I

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for-

Tuesday, June 9, 2026 at 10:00 AM Eastern

(c) Participants will meet at-

Thomaston Dam Project Office, 331 Hill Road, Thomaston, CT 06787

(End of provision)

MAGNITUDE OF PROJECT

The estimated cost of the work is between $25,000 and $100,000.

*** END OF NARRATIVE ***

FAR Clauses Incorporated by Reference

Number Title Effective Date

Alternate Deviation

Variation Effective Date

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements.

2017-01

52.204-9 Personal Identity Verification of Contractor Personnel.

2011-01

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (Deviation 2026-O0038)

2026-02

52.204-13 System for Award Management- Maintenance. (Deviation 2026- O0038)

2026-02

52.204-19 Incorporation by Reference of Representations and Certifications.

2014-12

52.209-10 Prohibition on Contracting With Inverted Domestic Corporations.

(Deviation 2026-O0038)

2026-02

52.219-6 Notice of Total Small Business Set-Aside. (Deviation 2026- O0038)

2026-02

52.222-3 Convict Labor. (Deviation 2026- O0038)

2026-02

52.222-6 Construction Wage Rate Requirements. (Deviation 2026- O0038)

2026-02

52.222-7 Withholding of Funds. (Deviation 2026-O0038)

2026-02

52.222-8 Payrolls and Basic Records.

(Deviation 2026-O0038)

2026-02

52.222-9 Apprentices and Trainees.

(Deviation 2026-O0038)

2026-02

52.222-10 Compliance with Copeland Act Requirements. (Deviation 2026- O0038)

2026-02

52.222-11 Subcontracts (Labor Standards).

(Deviation 2026-O0038)

2026-02

52.222-12 Contract Termination-Debarment. 2014-05

52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations.

2014-05

52.222-14 Disputes Concerning Labor Standards. (Deviation 2026- O0038)

2026-02

52.222-15 Certification of Eligibility. 2014-05

52.222-36 Equal Opportunity for Workers with Disabilities. (Deviation 2026- O0038)

2026-02

52.222-50 Combating Trafficking in Persons. (Deviation 2026-O0038)

2026-02

52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026. (Deviation 2026-O0038)

2026-02

52.222-62 Paid Sick Leave Under Executive Order 13706. (Deviation 2026- O0038)

2026-02

52.222-90 Addressing DEI Discrimination by Federal Contractors.

(Deviation 2026-O0040, Revision 1)

2026-04

52.223-2 Reporting of Biobased Products Under Service and Construction Contracts. (Deviation 2026- O0038)

2026-02

52.223-5 Pollution Prevention and Right-to- Know Information.

2024-05

52.223-23 Sustainable Products. (Deviation 2026-O0038)

2026-02

52.226-8 Encouraging Contractor Policies to Ban Text Messaging While

2024-05

Driving.

52.228-2 Additional Bond Security. 1997-10

52.228-11 Pledges of Assets (DEVIATION 2020-O0016)

2021-02 Deviation 2020- O0016

2020-04

52.228-12 Prospective Subcontractor Requests for Bonds.

2022-12

52.228-14 Irrevocable Letter of Credit. 2014-11

52.232-23 Assignment of Claims. 2014-05

52.232-27 Prompt Payment for Construction Contracts.

2017-01

52.232-33 Payment by Electronic Funds Transfer-System for Award Management.

2018-10

52.232-39 Unenforceability of Unauthorized Obligations.

2013-06

52.232-40 Providing Accelerated Payments to Small Business Subcontractors.

2023-03

52.233-1 Disputes. (Deviation 2026- O0038)

2026-02

52.233-3 Protest after Award. (Deviation 2026-O0038)

2026-02

52.233-4 Applicable Law for Breach of Contract Claim. (Deviation 2026- O0038)

2026-02

52.236-2 Differing Site Conditions. 2026-02

(Deviation 2026-O0038)

52.236-3 Site Investigation and Conditions Affecting the Work. (Deviation 2026-O0038)

2026-02

52.236-5 Material and Workmanship.

(Deviation 2026-O0038)

2026-02

52.236-6 Superintendence by the Contractor. (Deviation 2026- O0038)

2026-02

52.236-7 Permits and Responsibilities.

(Deviation 2026-O0038)

2026-02

52.236-8 Other Contracts. (Deviation 2026- O0038)

2026-02

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (Deviation 2026-O0038)

2026-02

52.236-10 Operations and Storage Areas.

(Deviation 2026-O0038)

2026-02

52.236-11 Use and Possession Prior to Completion. (Deviation 2026- O0038)

2026-02

52.236-12 Cleaning Up. (Deviation 2026- O0038)

2026-02

52.236-13 Accident Prevention. (Deviation 2026-O0038)

2026-02

52.236-21 Specifications and Drawings for Construction. (Deviation 2026- O0038)

2026-02

52.240-91 Security Prohibitions and Exclusions. (Deviation 2026- O0038)

2026-02

52.242-14 Suspension of Work. 1984-04

52.243-5 Changes and Changed Conditions. (Deviation 2026- O0038)

2026-02

52.244-6 Subcontracts for Commercial Products and Commercial Services. (Deviation 2026-O0038)

2026-04

52.246-21 Warranty of Construction. 1994-03

52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form).

1984-04

52.249-10 Default (Fixed-Price Construction).

1984-04

DFARS Clauses Incorporated by Reference

Date

Alternate Deviation

Variation Effective Date

252.203-7000 Requirements Relating to Compensation of Former DoD Officials.

2011-09

252.203-7002 Requirement to Inform Employees of Whistleblower Rights.

2022-12

252.204-7003 Control of Government 1992-04

Personnel Work Product.

252.204-7004 Antiterrorism Awareness Training for Contractors.

2023-01

252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting. (DEVIATION 2024-

O0013 REVISION 1)

2024-05 Deviation 2024- O0013

2024-05

252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services.

2023-01

252.204-7020 NIST SP 800-171 DoD Assessment Requirements.

2023-11

252.223-7006 Prohibition on Storage, Treatment, and Disposal of Toxic or Hazardous Materials.

2014-09

252.223-7008 Prohibition of Hexavalent Chromium.

2023-01

252.225-7012 Preference for Certain Domestic Commodities.

2022-04

252.225-7048 Export-Controlled Items. 2013-06

252.225-7056 Prohibition Regarding Business Operations with the Maduro Regime.

2023-01

252.225-7060 Prohibition on Certain Procurements from the Xinjiang Uyghur Autonomous Region.

2023-06

252.232-7004 DoD Progress Payment Rates

(DEVIATION 2020-O0010)

2014-10 Deviation 2020-

2020-03

O0010

252.232-7010 Levies on Contract Payments. 2006-12

252.237-7010 Prohibition on Interrogation of Detainees by Contractor Personnel.

2023-01

252.243-7001 Pricing of Contract Modifications. 1991-12

252.244-7999 Subcontracts for Commercial Products or Commercial Services. (DEVIATION 2026- O0015)

2026-02 Deviation 2026- O0015

2026-01

252.247-7023 Transportation of Supplies by Sea.

2024-10

FAR Clauses Incorporated by Full Text

Date

Alternate Deviation

Variation Effective Date

52.213-4 Terms and Conditions-Simplified Acquisitions (Noncommercial).

(Deviation 2026-O0038)

2026-02

Terms and Conditions-Simplified Acquisitions (Noncommercial) (Feb 2026) (Deviation 2026- O0038)

(a) DELETED

(b) . The Contractor shall be liable for default unless nonperformance is Excusable delays caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence. Examples of occurrences include acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. When an excusable delay occurs, the Contractor shall-

(1) Notify the Contracting Officer in writing as soon as possible;

(2) Remedy the delay as quickly as possible; and

(3) Notify the Contracting Officer when the occurrence is over.

(c) DELETED

(d) DELETED

(e) DELETED

(End of clause)

52.219-28 Postaward Small Business Program Rerepresentation.

(Deviation 2026-O0038)

2026-02

Postaward Small Business Program Rerepresentation (Feb 2026) (Deviation 2026-O0038)

(a) . As used in this clause-Definitions

Long-term contract means a contract of more than five years in duration, including options.

However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern-

(1) Means a concern, including its affiliates, that is independently owned and operated, not dominant in its field of operation, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause.

(2) , as used in this definition, means business concerns, one of whom directly or Affiliates indirectly controls or has the power to control the others, or a third party or parties control or have the power to control the others. In determining whether affiliation exists, consideration is given to all appropriate factors including common ownership, common management, and contractual relationships. SBA determines affiliation based on the factors set forth at 13 CFR 121.103.

(b) If the Contractor represented that it was a small business concern, a small disadvantaged business concern, or a joint venture that was any of the small business concerns identified in 19.000(a)(3) prior to award of this contract, the Contractor shall rerepresent its size and socioeconomic status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts-

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code(s) assigned to this contract. The small business size standard corresponding to this NAICS code(s) can be found at https://www.sba.gov/document /support--table-size-standards.

(d) The small business size standard for a Contractor providing an end item that it does not manufacture, process, or produce itself, for a contract other than a construction or service contract, is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition-

(1) Was set aside for small business and has a value above the simplified acquisition threshold;

(2) Used the HUBZone price evaluation preference regardless of dollar value, unless the Contractor waived the price evaluation preference; or

(3) Was an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.

(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the representation(s) required by paragraph (b) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting officer in writing within the timeframes specified in paragraph (b) of this clause, that the data have been validated or updated, and provide the date of the validation or update.

(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.

(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:

(1) The Contractor represents that it is, is not a small business concern under NAICS 237310 Code assigned to contract number.W912WJ26PAXXX

(2) [Complete only if the Contractor represented itself as a small business concern in paragraph .] The Contractor represents that it is, is not, a small disadvantaged (g)(1) of this clause business concern as defined in .13 CFR 124.1001

(3) . The Women-owned small business (WOSB) joint venture eligible under the WOSB Program Contractor represents that it is, is not a joint venture that complies with the requirements of 13 CFR 127.506(a) through (c). [ The Contractor shall enter the name and unique entity ____ identifier of each party to the joint venture: __.]

(4) . The Economically disadvantaged women-owned small business (EDWOSB) joint venture Contractor represents that it is, is not a joint venture that complies with the requirements of 13 CFR 127.506(a) through (c). [ The Contractor shall enter the name and unique entity ____ identifier of each party to the joint venture: __ .]

(5) Service-disabled veteran-owned small business (SDVOSB) joint venture eligible under the . The Contractor represents that it is, is not an SDVOSB joint venture eligible SDVOSB Program under the SDVOSB Program that complies with the requirements of 13 CFR 128.402. [ The ____ Contractor shall enter the name and unique entity identifier of each party to the joint venture:

(6) [ HUBZone joint venture eligible under the HUBZone Program. Complete only if the offeror is ] The offeror represents, as part of its offer, that It is, is not a HUBZone small business concern.

a HUBZone joint venture that complies with the requirements of 13 CFR 126.616(a) through (c).

[ The Contractor shall enter the name and unique entity identifier of each party to the joint ____ venture: .] Each HUBZone small business concern participating in the HUBZone joint venture must be certified as a HUBZone concern. [ Contractor to sign and date and insert ____ authorized signer's name and title.]

(End of clause)

52.225-9 Buy American-Construction Materials. (Deviation 2026-

2026-02

O0038)

Buy American-Construction Materials (Feb 2026) (Deviation 2026-O0038)

(a) . As used in this clause-Definitions

Commercially available off-the-shelf (COTS) item-

(1) Means any item of supply (including construction material) that is-

(i) A commercial product (as defined in paragraph (1) of the definition of "commercial product" at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies.

However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .