This document is a standardized Pump Station Inspection Checklist for the Devens Consolidated Landfill, created by SERES and ARCADIS. The checklist provides a comprehensive template for systematically documenting the status and condition of various site components and equipment, including site appearance, air supply pumps, leachate pumps, ventilating fan, pump enclosure heater, discharge plug valve, flow meter readings, auto dialer, and site maintenance. The inspection form allows for detailed tracking of pump statuses, circuit breaker conditions, selector switch positions, elapsed time, air flow readings, water levels, and whether maintenance was performed or is needed, with options to select "Yes" or "No" for most inspection items and space for additional comments.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Devens Consolidated Landfill Pump Station Inspection Checklist

Date:____________ Time:___________ Inspector:___________ Weather:_______________________________

Inspection Category Inspection Item Select/Complete Comments

Fence Inspected? Yes No

Gate Inspected? Yes No

Pump Enclosure Inspected? Yes No

Panels Inspected? Yes No

Leachate Well Inspected? Yes No

Meter Pit Inspected? Yes No

Pump #1 Status On Off

Pump #2 Status On Off

Bubbles in Leachate Well? Yes No

Air Flow Reading (scfm)

Pump #1 Circuit Breaker Status On Trip Off

Pump #2 Circuit Breakers Status On Trip Off

Pump #1 Selector Switch Status Hand Off Auto

Pump #2 Selector Switch Status Hand Off Auto

Lead/Lag Switch Status #1 Auto #2

Pump #1 Elapsed Time (hours)

Pump #2 Elapsed Time (hours)

Checked? Yes No

Vent Status Open Closed

Checked? Yes No

Status On Off

Exercised w/ Pumps Off? Yes No

Position Open Closed

Total (Gallons)

Resettable Totalizer (Gallons)

Flow Rate (gpm)

Water Level (ft bgs)

Auto Dialer Status Normal Disarmed

Maintenance Performed? Yes No

Maintenance Needed? Yes No

Site Maintenance

Flow Meter Readings

Site Appearance

Air Supply Pumps

Leachate Pumps

Ventilating Fan

Pump Enclosure Heater

Discharge Plug Valve