This is Amendment 0004 to solicitation W912WJ25B0003 for Concrete Repairs at Blackwater Dam in Webster, NH, issued by the US Army Corps of Engineers New England District. The amendment provides responses to contractor questions about railing removal/reinstallation during concrete repairs, water access and usage requirements, and extends the bid due date.

Key details include: horizontal fence supports can be temporarily removed but vertical posts must remain in place; contractors can draw water from the Blackwater River upstream but must maintain minimum Aquatic Base Flow requirements; water trucks can access the upstream side of the dam through an unlocked gate; running water hoses through the equipment building is not feasible; discharged water must be controlled to prevent contamination; and contractors must submit their water usage plan for government approval. The bid due date has been extended from December 12, 2024 at 1:00 PM to December 16, 2024 at 1:00 PM.

View the file

Other files

File Type Posted
Bid Abstract.pdf PDF
Amendment 0005.pdf PDF
Amendment 0003.pdf PDF
Amendment 0002.pdf PDF
Amendment 0001.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment 0004 is necessary to provide responses to RFIs and extend the bid due date. All other aspects remain the same.

1. CONTRACT ID CODE PAGE OF PAGES

1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ25B0003

X 9B. DATED (SEE ITEM 11)

12-Nov-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

U0003

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

10-Dec-2024

CODE

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

W912WJ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912WJ25B0003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0004

1. Please confirm if existing railings at top of non-overflow Spillway downstream elevation is getting removed and reinstalled as necessary to perform concrete repairs? Or should contractor assume that existing railing is not getting removed during concrete repairs?

Government Response: The horizontal supports of the fencing on top of the spillway are connected to the vertical posts using a bolted hub type system and thus can be removed and reinstalled. The contractor can temporarily remove the fence fabric and horizontals for construction. The vertical posts are not to be removed. Any damages incurred on the fences resulting from the construction activities shall be repaired to the satisfaction of and at no additional cost to the Government.

2. Amendment#002 – response to question#5 states – no water is available at site. Can you provide us following details:

a. Is there a fire-hydrant near dam structure? How far it is from equipment building?

Government Response: There is no hydrant in the vicinity.

b. If contractor gets water trucks for project – can it be driven to the upstream side of dam from parking lot side?

Government Response: Yes, the gate can be unlocked to allow the contractor access to the upstream side of the dam.

c. If contractor has to run hoses to get water to the upstream side of dam, can contractor assume that hoses can run through equipment building and pass through non overflow section of spillway and reach the upstream side?

Government Response: This is not feasible. There is no access through the equipment room unless the contractor intends to run hoses up a multi-turn staircase to the top of the structure then back down over the dam.

3. Can bid date be extended by one week?

Government Response: See Amendment 0004.

4. For building a water diversion system on upstream side of dam to perform work – contractor requires substantial quantity of water. Can contractor utilize/draw water from the upstream of Blackwater River?

Government Response: The Contractor can draw water from the Blackwater River upstream of Blackwater Dam. The amount of water a contractor can draw is dependent on the flow in the river at the time of draw. The Contractor is required to keep a minimum Aquatic Base Flow (ABF) flowing downstream depending on the time of year which is shown below:

If the inflow is greater than ABF, they can have inflow minus ABF in cfs. If the river inflow to the dam is less than the ABF, they can have 30% of the inflow in cfs.

a. If no, can authority provide us with another source of water in nearby area of work?

Government Response: There are no known source nearby.

5. To perform work at Bullnose repair location on upstream in phases – contractor will be required to relocate water filled cofferdam system on upstream side, resulting in discharge of water filled in cofferdam – can contractor assume that water can be discharged in Blackwater River System?

Government Response: Yes, the water can be discharged back into the river. Discharge of any kind into the waters of the U.S. will need to be controlled (i.e. no contaminate). Note: for example, if what is released from the inflated coffer dam develops a sheen on the water, it would be the contractor that is responsible for the containment and cleanup.

Prior to drawing any water from the stream for use in construction, the contractor shall submit, in writing to the Government for review and approval, the contractor’s proposed compliance with the requirements stipulated above. The submittal shall include, but not limited to, methods of drawing water from the stream, discharging water back to the stream, and for testing of water prior to and after discharging back into the stream. No water shall be drawn nor discharged until approval is received from the Government.

Note: Flow rate information is public and can be accessed from the following:

- www.reservoircontrol.com and click Merrimack River Basin > BWD and it lists the flow rates.

- Call 603-648-2474 and there is a recording

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time has changed from 12-Dec-2024 01:00 PM to 16-Dec-2024 01:00 PM.