Amendment W912WJ24Q0161-0001.pdf

PDF 436 KB Posted

Attached to
Road Gates Replacements, Knightville Dam & Littleville Dam, Huntington, MA
Solicitation number
W912WJ24Q0161
Issued by

About this file

This document is an Amendment to Solicitation W912WJ24Q0161 for Road Gates Replacements at the Knightville Dam and Littleville Dam projects in Huntington, Massachusetts. The amendment provides responses to industry questions, including:

  • The road gates vary in length from approximately 12 to 22 feet, and the contractor is responsible for field measurements and sizing the new gates.
  • The Contractor's Point of Contact can serve as the Site Safety and Health Officer (SSHO) and Quality Control Manager, provided the individual meets the required qualifications.
  • Cutting off old gate posts below ground level is not permitted, and all existing posts and concrete footings must be fully removed.
  • Round tubing is not allowed for the gate arms, which must be fabricated from 3-inch square steel tube.

The solicitation closing date remains August 28, 2024 at 5:00 PM Eastern, and all other terms and conditions of the original solicitation remain unchanged. This is a small business set-aside procurement with a NAICS code of 237310 and size standard of $45 million.

View the file

Other files

File Type Posted
Solicitation W912WJ24Q0161.pdf PDF
Attachments.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment is necessary to provide responses to questions from industry.

Solicitation closing remains August 28, 2024 at 5:00 PM Eastern.

All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 26-Aug-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ24Q0161

X 9B. DATED (SEE ITEM 11)

12-Aug-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

26-Aug-2024

CODE

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

W912WJ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

jennifer.m.samela@usace.army.milEMAIL:978-318-8324TEL:

JENNIFER M SAMELA / ADDED BY UPASS

W912WJ24Q0161

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

REQUEST FOR INFORMATION

QUESTION 1: Can you please provide the desired length of the gates?

RESPONSE 1: The road gates vary in length from approximately 12’ to 22’. Refer to Part 1.3.b.

Road Gates to be Replaced of the Statement of Work. The Contractor is responsible for all field measurements and sizing the new gates to span the road and meet set back requirements. Refer to Part 2.1.a.iii. Road Gates of the Statement of Work.

QUESTION 2: Since this is a relatively small scope of work, can the Contractor’s Point of Contact also be the Quality Control Person and Level 3 Safety Officer?

RESPONSE 2: The SSHO and Quality Control Manager must meet the requirements of EM 385- 1-1, Chapter 2-3.b and 2-4.b, as stated in Section I.6.d. of the Statement of Work. There are no restrictions on the Contractor’s Point of Contact serving as the SSHO and QCM provided that the individual has all training/certifications/experience to meet the requirements per the Statement of Work and EM 385-1-1.

QUESTION 3: For the gates that have a significant portion of their post foundations underneath the asphalt, would it be acceptable to cut off the old posts below ground level and then install new posts a few feet away from the old foundations?

RESPONSE 3: No, cutting off the old posts below ground level is not permissible. All old post and their associated concrete footing shall be removed as stated in Part.3.3. Demolition of the Statement of Work.

QUESTION 4: Would it be acceptable to use round tubing for the gate arm as opposed to square tubing?

RESPONSE 4: No, round tubing is not permissible. All horizontal and diagonal crossbeams of new gates shall be fabricated from 3” square tube steel as stated in Part 2.1.a. Road Gates of the Statement of Work.

(End of Summary of Changes)