This document is an Amendment to Solicitation W912WJ24Q0108 for Access Road Repairs and Gate Replacement at Hodges Village Dam in Oxford, MA. The amendment provides responses to industry questions, clarifying that the contractor is responsible for removing any entirely separated asphalt pieces and that the gates are to be operated manually, not with sensors or mechanical operators. The solicitation closing date remains May 20, 2024 at 5:00 PM Eastern, and all other terms and conditions of the solicitation are unchanged.
The original solicitation is seeking small business vendors to provide labor, materials, equipment, and transportation to repair pavement cracks and replace three security gates at the Hodges Village Dam location. The magnitude of construction is between $25,000 and $100,000. The applicable NAICS code is 238910 with a $19 Million small business size standard, and all vendors must have an active SAM.gov registration to be considered.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachments_Revised.pdf | ||
| Amendment W912WJ24Q0108-0001.pdf | ||
| Attachments.pdf | ||
| Solicitation W912WJ24Q0108.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Amendment is necessary to provide responses to questions from industry. Question #3 is applicable to this amendment.
Solicitation closing remains May 20. 2024 at 5:00 PM Eastern.
All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 17-May-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ24Q0108
X 9B. DATED (SEE ITEM 11)
30-Apr-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
17-May-2024
CODE
U S ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA RD
CONCORD MA 01742-2751
W912WJ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
jennifer.m.samela@usace.army.milEMAIL:978-318-8324TEL:
JENNIFER M SAMELA / ADDED BY UPASS
W912WJ24Q0108
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been modified:
REQUEST FOR INFORMATION
QUESTION 1: We would like to know if this is a brand new contract OR if there is (was) an incumbent performing these services?
RESPONSE 1: This is a construction contract and there is no previous incumbent for this work.
QUESTION 2: There are pieces of asphalt which have been entirely separated from the larger paved structure due to cracks on all sides. In these instances, is the contractor responsible for removing the dislodged piece?
RESPONSE 2: Yes, for large chunks that are entirely separated from the paved structure the contractor must remove the separated piece. The area left behind will be treated as a void and be filled with asphalt millings, then all newly added material shall be compacted. Please refer to Section III.2.b. of the Statement of Work and additional photo in the Revised Attachments for further information.
QUESTION 3: There is a photo in the Attachments with the note as “Example Product” and the photo shows a sensor operating gate. The specifications do not require such. Please confirm that the gates are to be operated manually.
RESPONSE 3: Gates are to be operated manually. The example product’s purpose is to provide the contractor a general idea of gate construction, color, and reflective requirements. A sensor and mechanical operator are not required in this Statement of Work.