W912WJ24B0015 Amendment 0001.pdf

PDF 601 KB Posted

Attached to
Maintenance Dredging Narraguagus River, Milbridge, Maine
Solicitation number
W912WJ24B0015
Issued by

About this file

This document is an Amendment to Solicitation W912WJ24B0015 for maintenance dredging of the Narraguagus River Federal Navigation Project in Milbridge, Maine. The amendment provides responses to Requests for Information and revises certain specification sections. The solicitation is for a construction contract to dredge approximately 150,000 cubic yards of material from the navigation channel and anchorages, with dredging to occur between November 1, 2024 and May 15, 2025. Material will be transported via scow to the Douglas Island Disposal Site. The amendment clarifies requirements related to dredging operations, including the allowance of box cutting, the prohibition on dragging, and the process for measuring scow loads. The contracting agency is the U.S. Army Corps of Engineers, New England District, and the NAICS code is 237990 with a $37M size standard. This is an Unrestricted Invitation for Bid with an estimated construction cost of $1 million to $5 million.

View the file

Other files

File Type Posted
Bid Abstract.pdf PDF
Revised Specs.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This Amendment is neccessary to provide responses to Requests for Information and to provide revised specification sections. All other aspects remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 07-Aug-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ24B0015

X 9B. DATED (SEE ITEM 11)

16-Jul-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

07-Aug-2024

CODE

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

W912WJ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912WJ24B0015

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

REQUESTS FOR INFORMATION

1. Section 01 11 00 – Summary of Work states; “The Contractor shall note that the dredging and disposal period for this contract is 1 November 2024 to 31 March 2025.”

o When does USACE anticipate issuing the NTP?

Response: USACE anticipates issuing Notice to Proceed in early October.

2. Section 01 54 50 – Dredging Plant and Equipment states; “All dredge and plant equipment shall be registered with the AUTOMATIC IDENTIFICATION SYSTEM (AIS) in order to ensure that the entire footprint of the Contract's working vessels and scows are available on marine trafficker's electronic chart displays.”

o Does this requirement apply to small vessels (skiffs, survey vessels, etc.)?

Response: USACE has removed the requirement for Automatic Identification System. Please refer to the revised Specs included with this Amendment.

3. Section 01 57 19 – Temporary Environmental Controls, Maine DEP Water Quality Certification, states;

“Clearly mark and designate the dredging area and the transportation route from dredge site to Douglas Island Disposal Site.”

o As the haul route is primarily within the Federal Navigation Channel until it departs the channel at the south end of the project, what are the requirements for marking the haul route and disposal site?

Response: Refer to the attachment at the end of Specification Section 35 20 23 for the haul route. No in-water marking is necessary.

4. Section 01 71 23 – Field Engineering for Dredging states; “The Government will conduct or has conducted a pre-dredge survey within 180 days of the start of dredging operations.”

o As the survey in the bid documents is from September 2023, please confirm that USACE will conduct a new pre-dredge survey.

Response: USACE will conduct a pre-dredge survey prior to the start of dredging operations.

5. Section 01 71 23 – Field Engineering for Dredging states; “Any change to the side slope design (i.e., box cutting) must be approved by the Government prior to the start of any dredging.” Section 35 20 23 – Mechanical Dredging states; “The material may be dredged from the original position or by dredging the space below the pay slope plane at the bottom of the slope for upslope material capable of falling into the cut.”

o Section 35 20 23 indicates that box-cutting is an allowed option. Please confirm that box-cutting of side slopes is allowed.

Response: Box cutting of side slopes is allowed so long as it is included in the Dredging Operation Plan and accepted by the Contracting Officer in accordance with Specification Section 35 20 23, paragraph 3.2.2 Dredging Operation Plan.

6. Section 35 20 23 – Mechanical Dredging states; “No dragging of material will be allowed except as directed by the Contracting Officer.”

o It is important to know pre-bid if dragging will be allowed. Please confirm if dragging will be allowed Response: No dragging will be allowed as per the specifications.

W912WJ24B0015

7. Section 35 20 23 – Mechanical Dredging states; “Do not remove loaded or partially loaded scows from the dredge area until the load has been measured by the Contracting Officer's Representative (COR).”

o What is the intent of this requirement? Scows will depart the dredge at all hours, 7 days per week.

Will the DQM system (Section 35 20 23.13) satisfy this requirement, or will the Contracting Officer's Representative (COR) be available full time to measure each load?

Response: For scows that have a means to display the weight of the load, the COR will be available to confirm/measure the load using this load display feature from 0700 to 1500, Monday through Friday. For scows that do not have this load display feature, and at all times outside of the hours stated for all scows, the COR will use DQM to confirm/measure the scow loads.

8. Section 35 20 23 – Mechanical Dredging states; “All disposal shall be done with the scow at a complete halt. This requirement must be followed except when weather or sea state create unsafe conditions in which case disposal with the scow moving only fast enough to maintain safe control (generally less than one knot) will be permitted.”

o This requirement is very difficult to accomplish, particularly if there is any sort of wind or current.

The scows are free floating pieces of equipment that are being towed on a long cable. Prior NE District solicitations have amended this language to “Disposal at the _______ Disposal Site may be performed with the scow in motion at a speed no greater than 2 knots as long as the release of the material from the scow (as determined by the draft change recorded by the Dredging Quality Management (DQM) System) can be achieved within _______ feet of the specified target.” Please amend this solicitation similarly.

Response: Please refer to the revised Specs included with this Amendment.

(End of Summary of Changes)