This modification amends a solicitation for concrete repairs, drainage improvements, and sealant coating work on the northeast spillway at Barre Falls Dam in Barre, Massachusetts. The U.S. Army Corps of Engineers is seeking these services. The modification answers questions from industry, including confirming that the repair area is only within the concrete panels shown in photograph C1 and not the wider area of deterioration. It also provides details on the depth of weep holes to be cleaned, whether excavation will be required for new weep holes, how many existing and new weep holes will be addressed, and indicates a site visit was held with representatives from Allegiance Masonry Contracting, Trident Waterproofing, and the Corps in attendance. The quote due date remains August 17, 2023.

View the file

Other files

File Type Posted
Specifications June 2023.pdf PDF
Drawings.pdf PDF
Solicitation W912WJ23Q0098.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment 0001 is to answ er questions from industry and post the site visit attendee sheet.

The quote due date remains August 17, 2023 at 5:00 pm.

All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 14-Aug-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ23Q0098

X 9B. DATED (SEE ITEM 11)

18-Jul-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

14-Aug-2023

CODE

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

W912WJ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

jennifer.m.samela@usace.army.milEMAIL:978-318-8324TEL:

JENNIFER M SAMELA / ADDED BY UPASS

W912WJ23Q0098

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

QUESTIONS AND ANSWERS

QUESTION 1: Confirm that the repair area is within the concrete panels as indicated on photo C1 only, and does not include the area of deterioration outside that area towards the bridge.

ANSWER 1: Confirmed. The whole area of repair is shown in C1.

QUESTION 2: Is the depth of the weep holes that need to be cleaned out 3 feet? If not, what is the depth?

ANSWER 2: Approximately 2-feet.

QUESTION 3: Is it the intent to excavate and put gravel on the back side of the North

Spillway wall for the installation of the new weep holes? Or is the gravel to be packed from the front?

ANSWER 3: The gravel will be packed from the front; there will be no excavation behind the North Spillway Wall.

QUESTION 4: Please identify the specific weep holes to be cleaned out.

ANSWER 4: Existing weep holes to be cleaned out are shown on S-201. There are

FIVE (5) shown.

QUESTION 5: Indicate the anticipated number of new weep holes to be installed.

ANSWER 5: New weep holes are shown on S-201. There are THIRTEEN (13) shown.

QUESTION 6: Who is the Technical Point of Contact (TPOC) for the awarded contract?

ANSWER 6: There will be a Contracting Officer’s Representative assigned to the project after award.

W912WJ23Q0098

SITE VISIT ATTENDEES

Barre Falls Dam Conrete Repairs August 10, 2023

9:00 am

Site Visit Sign-In

Name (First and Last) Company Name

Brian Adams

Allegiance Masonry Contracting

Jim Dove

Allegiance Masonry Contracting

Brady Noel

Trident Waterproofing, Inc.

Ann Adley US Army Corps of Engineers

Brianna Green US Army Corps of Engineers

(End of Summary of Changes)