Bid Abstract __ W912WJ21B0006.pdf
PDF 939 KB Posted
- Solicitation number
- W912WJ21B0006
About this file
This document is an abstract of offers received in response to Solicitation Number W912WJ21B0006 for electrical upgrades at Buffumville Lake in Charlton, Massachusetts issued by the Department of the Army Corps of Engineers Engineering District New England. Five contractors submitted offers for the project, with total bids ranging from $271,580 to $565,739. The scope of work includes two items - electrical improvements for the lump sum amount of $266,580 to $560,739, and an allowance for electricity utility activities for $5,000. The government estimate was $271,580 to $417,000. All contractors acknowledged amendments and provided bid security in the form of bonds ranging from 5% to 20% of their total bids.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ABSTRACT OF OFFERS - CONSTRUCTION 1. SOLICITATION NUMBER 2. DATE ISSUED 3. DATE OPENED PAGE OF PAGES
4/12/2021 5/12/2021 1 2
4. ISSUING OFFICE NAME AND TITLE OF CERTIFYING OFFICIAL (TYPED)
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation. SIGNATURE DATE SIGNED
9. OFFERS
5. PROJECT TITLE (IFB) 8. GOVERNMENT ESTIMATE NO. 1 NO. 2
(Check A, B, C and complete D, E, and F) A. OFFEROR A. OFFEROR
A. HIRED LABOR
B. REASONABLE CONTRACT B. BID SECURTIY (TYPE AND AMOUNT) B. BID SECURTIY (TYPE AND AMOUNT)
X (Without Profit)
6. NUMBER OF AMENDMENTS ISSUED C. REASONABLE CONTRACT C. AMENDEMENTS ACKNOWLEDGED C. AMENDEMENTS ACKNOWLEDGED
(Including Profit)
7A. ITEM
NUMBER 7B. DESCRIPTION OF OFFERED ITEM
7C. EST.
QUANTITY D. UNIT E. UNIT PRICE F. ESTIMATED AMOUNT D. UNIT PRICE E. ESTIMATED AMOUNT D. UNIT PRICE
E. ESTIMATED
AMOUNT
0001 Electrical Improvements 1 JOB 266,580.00$ 266,580.00$ 336,000.00$ 336,000.00$ 412,000.00$ 412,000.00$ 0002 Allowance for Electricity Utility Activities 1 JOB 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$
TOTAL AMOUNT 271,580.00$ 341,000.00$ 417,000.00$
W912WJ21B0006
Buffumville Lake Electrical Upgrades, Charlton, MA Cole Contracting, Inc.
Erin E. Bradley Bid Opening OfficerUS ARMY ENGINEER DISTRICT, NEW ENGLAND
696 VIRGINIA ROAD
CONCORD, MA 01742
6 3
5% 20%
Midwest Electrical Construction, Inc.
13 May 2021
1. SOLICITATION NUMBER PAGE OF PAGES
2 2
ABSTRACT OF OFFERS - CONSTRUCTION INSTRUCTIONS - Attach this form to OF 1419, Abstract of Offers - Construction, when more than 2 offers are received on CONTINUATION SHEET a construction project. Each Continuation Sheet will accommodate 14 contract items to conform to the number of items which can be entered on the OF 1419. Use additional OF 1419's for contract items in excess of 14 and attach additional Continuation Sheets (OF 1419A) as needed.
2. PROJECT TITLE
NO. 3 NO. 4 NO. 5 NO. 6
A. OFFEROR A. OFFEROR A. OFFEROR A. OFFEROR
B. BID SECURITY (TYPE AND AMT) B. BID SECURITY (TYPE AND AMT) B. BID SECURITY (TYPE AND AMT) B. BID SECURITY (TYPE AND AMT)
3. CONTRACT ITEMS C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED C. AMENDMENTS ACKNOWLEDGED
A. ITEM B. DESCRIPTION OF OFFERED ITEM C. QUANTITY C. UNIT C. UNIT PRICE E. ESTIMATED D. UNIT E. ESTIMATED C. UNIT PRICE E. ESTIMATED D. UNIT E. ESTIMATED
0001 Electrical Improvements 1 JOB 365,500.00$ 365,500.00$ 421,733.00$ 421,733.00$ 560,739.00$ 560,739.00$ 459,459.00$ 459,459.00$ 0002 Allowance for Electricity Utility Activities 1 JOB 5,000.00$ 5,000.00$ -$ -$ 5,000.00$ 5,000.00$ -$ -$
TOTAL AMOUNT 370,500.00$ 421,733.00$ 565,739.00 $459,459.00
3 123
Buffumville Lake Electrical Upgrades, Charlton, MA
20%
KOBO Utility Construction Corp.JE Prenosil & Company Vedant Construction Inc.
W912WJ21B0006
None 20% 20%
LaFleur Electrical Co., Inc.
| FRONT |
| CONTINUATION |
| 2021-05-13T13:53:22-0400 | |
| BRADLEY.ERIN.ELIZABETH.1386908440 |