Amendment_W912WJ20Q0146_0001.pdf
PDF 805 KB Posted
- Attached to
- Stamford Hurricane Barrier, Stamford, CT, Lead Abatement and Resurfacing of Concrete Floors
- Solicitation number
- W912WJ20Q0146
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_W912WJ20Q0146_0002.pdf | ||
| Solicitation_W912WJ20Q0146.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W13G86019775250001
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to answ er technical questions and revise the SOW. The closing date remains 18 September, 2020 at 5:00PM, Eastern. All other terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 13
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 16-Sep-2020
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912WJ20Q0146
X 9B. DATED (SEE ITEM 11)
08-Sep-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
16-Sep-2020
CODE
U S ARMY ENGR DISTRICT, NEW ENGLAND
696 VIRGINIA RD
CONCORD MA 01742-2751
W912WJ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
Sheila.M.Winston@usace.army.milEMAIL:978-318-8159TEL:
SHEILA M WINSTONVINCUILLA / CHIEF, CONTRACTING DIVISION
W912WJ20Q0146
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
QUESTIONS AND ANSWERS
1. QUESTION: Page 11, Existing Conditions: West Abutment, Main Floor, approximately 700 SF concrete floor, Second Floor, approximately 550 SF concrete floor and East Abutment, approximately 400 SF concrete floor.
Based on this description, removing existing coatings from the walking surfaces of the floors. We are not painting the “Cove” the vertical and horizontal portion of the machine pads or raised structure supporting the structural steel in the Trolley Corridors. Is this the intent of this work?
1. ANSWER: The intent is for the painting of all horizontal concrete surfaces, no vertical surfaces. This does include the platform that the equipment motors/hydraulic tank is on but doesn’t include raised structure supporting the structural steel in the Trolley Corridors.
2. QUESTION: Section 6. Specific Safety Section-Lead Based Paint Abatement: d. Final Clearance Sampling: This sections calls for 3rd party independent clearance testing per ASTM E 1728. This standard is the sampling process, no clearance level is provided. Lead levels likely exist on all surfaces from erosion of existing lead paint. What is the proposed clearance level?
2. ANSWER: Clearance sampling shall be completed in accordance with ASTM E1728 and ASTM E3074. Samples must be analyzed by a laboratory recognized by the EPA’s National Lead Laboratory Accreditation Program (NLLAP). The SOW has been updated to reflect this information.
3. QUESTION: There is no mention in the scope of work of the steel walkway connecting the two areas of the second floor. Is the intent not to paint this area?
3. ANSWER: The metal steel walkway isn’t included in this contract.
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
STATEMENT OF WORK
LEAD ABATEMENT AND RESURFACE CONCRETE FLOORS
U.S. ARMY CORPS OF ENGINEERS
STAMFORD HURRICANE BARRIER
STAMFORD, CONNECTICUT
Statement of Work
I. General:
1. Scope – Furnish all labor, materials and equipment necessary to lead abate, prepare, and epoxy coat all concrete floors at the West and East Abutments of the Stamford Hurricane Barrier in Stamford Connecticut including, the West and East Main floors, generator room, west side second floor equipment area, West and East trolley corridors, concrete equipment platforms, bathroom, and furnace room. The Contractor must be qualified to handle and dispose of lead paint in accordance with all federal and state laws and regulations. The work includes the following:
a. Lead abatement of existing painted coating.
b. Mechanical preparation of the concrete substrate in accordance with manufacturer’s preparation recommendations.
c. Application of the epoxy floor coating system in accordance with manufacturer’s application recommendations.
2. Location – The Stamford Hurricane Barrier (West Branch) is located at 230 Elmcroft Road Stamford CT. The East Branch is located at 140 Harbor Drive Stamford CT.
3. Site Visit – Contact the Technical Point of Contact to arrange a site visit. The Technical Point of Contact for the project is Project Manager, Diana J. Errico-Topolski (978-318-8370 or Diana J. Errico-Topolski@usace.army.mil) Diana.J.Errico-Topolski@usace.army.mil.
4. Schedule – The work shall be completed no later than 120 days from Notice to Proceed (NTP). Contractor shall commence work within 14 calendar days after NTP. Work shall be performed Monday through Friday 8:30 AM to 4:00 PM unless otherwise approved by the Technical Point of Contact. No work shall be done on weekends or Government holidays.
5. Safety Requirements – All work shall be conducted in accordance with the U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1, most recent edition), and all applicable OSHA, federal, state, and local safety and health requirements. A copy of EM 385-1-1 can be accessed at the project office or electronically at Headquarters USACE website under publications using the following link:
http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385- 1-1.pdf
Project staff reserve the right to cease work at any time should the safety of employees, Contractors, and/or the public become jeopardized.
a. Accident Prevention Plan:
The Contractor shall prepare an Accident Prevention Plan (APP) specific to the activities being performed. It shall include Activity Hazard Analyses (AHAs) as described below.
A non-mandatory, fillable APP template is available upon request. However, the contractor is permitted to submit their own plan, at a minimum it must meet the requirements of EM 385-1-1, Appendix A, Section K.
A preparatory meeting shall be conducted by the prime contractor to discuss the APP contents with all effected onsite employees. The Prime Contractor is responsible for informing their subcontractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.
Weekly safety meetings shall be held and documented. Records shall be available to the TPOC upon request.
COVID 19: Procedures shall be documented in the Abbreviated Accident Prevention Plan and in the appropriate AHA’s to address site specific COVID-19 monitoring procedure which address at the minimum, the following items:
Contractor shall provide employees with and require them to use all required COVID-
19 related PPE in accordance with CDC and state guidelines.
Procedures shall be in place for periodic sanitation inspections and disinfecting of project sites and work areas in accordance with CDC guidelines.
Site specific procedures shall be in place to practice and promote appropriate social distancing while on site, when such procedure are practical.
Employees shall be trained in signs, symptoms and protection measures in accordance with CDC guidelines.
b. Activity Hazard Analysis (AHA):
An AHA shall be submitted for each major phase of work. A major phase of work is defined as an operation involving a type of work presenting hazards not experienced in previous operations or where a new subcontractor or work crew is to perform the work.
The analysis shall define all activities to be performed, identify the sequence of work, the specific hazards anticipated, and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level. The AHA shall be continuously reviewed and revised to address changing site conditions as appropriate.
c. Emergency Response:
Emergency procedures shall be documented in the Accident Prevention Plan and will include a map with directions to the nearest hospital, emergency contact numbers, and onsite First Aid/CPR responders.
d. Required Personnel:
The Contractor shall employ a minimum of one Competent Person (CP) at each project site to function as the Site Safety and Health Officer (SSHO). The SSHO shall be present at the project site and report to the contractor’s upper management. The SSHO is required to have related construction experience and have at a minimum completed a 10 Hour OSHA training.
In addition, when emergency medical services are not accessible within five (5) minutes of the work location and there are two (2) or more workers onsite, at least two (2) employees shall have (in-person) training in First Aid and CPR. Minimum qualifications are listed in EM 385-1-1, Section 03.A.02.c.
*Note: Other Competent or Qualified Persons may be required per EM 385-1-1 and/or other sections of this Statement of Work, based on the characteristics of the project*
e. Accident Reporting:
All accidents and near misses shall be investigated by the Contractor. All work-related recordable injuries, illnesses and property damage accidents (excluding on-the-road vehicle accidents), in which the property damage exceeds $5,000.00, shall be verbally reported to the TPOC within four (4) hours of the incident. Serious accidents as described in EM 385-1-1 Section 01.D shall be immediately reported to the TPOC. ENG Form 3394 shall be completed and submitted to the TPOC within five (5) working days of the incident.
The Contractor shall compile employee work hours (including subcontractors) and forward the total hours to the TPOC no later than close of business on the 10th calendar day of the following month. The method of transmission by the prime contractor to the TPOC shall be electronically.
6. Specific Safety Section-Lead Based Paint Abatement
a. General: The requirements of this section are applicable to contracts involving activities that disturb Lead-based paint (LBP). All LBP activities, training, and submittals shall comply with EM 385-1-1, Section 06.C; 29 CFR 1910.1025; 29 CFR 1926.62; as well as State, and local requirements.
b. Submittals: A site-specific Lead Compliance Plan is required to be submitted and accepted by the Technical Point of Contact (TPOC) prior to initiating lead abatement tasks. This plan shall be developed as an appendix to the APP and describe procedures to be followed to protect contractor and government employees, the environment, and general public from lead hazards while performing lead hazard control activities.
Specifically, the Lead Compliance Plan shall address the following:
i. A description of each work activity in which lead is emitted, to include equipment and materials used, controls in place, crew size, job responsibilities, operating procedures, and maintenance practices, work activity locations and lead-containing components keyed to the project drawings;
ii. Description of means to be used to achieve exposure compliance, including any engineering controls;
iii. Employee exposure assessment procedures to monitor and document employee lead exposure. Exposure monitoring shall include two types:
1) Initial determination (may be omitted if there is sufficient objective/historical data showing action level compliance according to the requirements); and
2) Continued exposure monitoring required as a result of initial exposure determinations.
iv. Protective clothing, housekeeping procedures to prevent spread of lead contamination both in and beyond the lead hazard control area, and hygiene facilities and practices to prevent employees from inadvertent ingestion of lead;
v. Administrative controls to limit employee exposure to lead, including employee rotation schedule to be employed, if engineering controls or PPE fail to eliminate exposures exceeding the PEL;
vi. Medical surveillance procedures to monitor employee exposures and ensure fitness for wearing respiratory protection;
vii. Competent person (CP) and employee training required;
viii. Detailed sketches identifying lead hazard control areas, including decontamination areas and facilities, critical barriers, and physical and air distribution boundaries;
ix. Perimeter or other area air monitoring outside or adjacent to the regulated area;
x. Security required for each lead hazard control area; and
xi. Waste generation, characterization, transportation, and disposal (including recordkeeping).
c. Required Certifications and Licenses:
i. The contractor must be licensed in lead abatement by the EPA or applicable state where the work will be completed.
ii. At least one onsite employee will be designated as the lead abatement competent person and be certified as a Lead Abatement Supervisor by the EPA or applicable state where the work will be completed.
iii. At a minimum, site workers involved with lead abatement activities must be certified as Lead Abatement Workers by the EPA or applicable state where the work will be completed.
iv. Copies of certificates and licenses shall be kept on site and available for review if requested by the TPOC.
d. Final Clearance Sampling: For interior lead abatement projects, a 3rd party, independent clearance examiner must assess the areas impacted by the abatement activities. The examiner must be a Certified Industrial Hygienist (CIH), Certified Risk Assessor, or a Certified Lead-Based Paint Inspector.
i. Clearance sampling shall be completed in accordance with ASTM E1728 and ASTM
E3074. Samples must be analyzed by a laboratory recognized by the EPA’s National Lead Laboratory Accreditation Program (NLLAP).
ii. Dust samples shall be collected in accordance with ASTM Standard E 1728 and analyzed by a laboratory recognized by the EPA’s National Lead Laboratory Accreditation Program (NLLAP).
7. Pre-Construction Conference – Prior to the start of any work, the Technical Point of
Contact will schedule and conduct a “Pre-Construction Conference”. The Contractor’s Project Manager and Quality Control Personnel will attend this meeting. This conference will be held at the time and location agreeable to the government and contractor. No work may be performed under this contract prior to this conference. The purpose of the conference is to enable the Technical Point of Contact to outline the procedures that will be followed by the
Government in its administration of the contract, and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government’s administration and inspection of contract work or obtain other pertinent information that might be required. At the Pre-Construction conference the contractor shall provide the name of the project superintendent with a telephone number for project coordination.
The following is a general list of items for discussion during this Pre-Construction Conference:
i. Authority of the Technical Point of Contact and Quality Assurance Inspectors.
ii. Contractor’s Safety Program (including sub-contractors).
iii. Accident Prevention Plan and Activity Hazard Analysis (Submitted & accepted prior to start of work on site)
iv. Accident Reporting (ENG Form 3394)
v. Fall Protection Plan IAW EM 385-1-1, Section 21
vi. Safety Data Sheet (SDS) requirements
vii. Contractor’s Equipment
viii. Correspondence, Communication, Security and Administrative Procedures.
ix. Invoice and payment.
8. Permits – The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable Federal, State, County, and Municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.
9. Security – The contractor will comply with all established security policies at the Stamford Hurricane Barrier. Due to periods of heightened security that may affect the access to the areas covered under this contract, the Government reserves the right to close any property or portion of property and reschedule and/or cancel any subsequent service. The Contractor shall be given at least 24 hour notice of any such closure.
10. Contractor Conduct – Alcohol and firearms are prohibited on project grounds. Contractor and employees must comply with CFR 36 Rules and Regulations.
11. Payment – After final inspection and acceptance by the Government, the Contractor must submit an invoice to the Technical Point of Contact. The invoice shall include the invoice date, contract number, dates of service, description of work, quantities, process, and total amount due per line item. The invoice must also include the company letterhead and this must match the data that is registered in the System for Award Management (SAM) registry.
For jobs greater than 30 days the contractor may request progress payment.
All invoices may be mailed to U.S. Army Corps of Engineers Hop Brook Lake
4 Straits Turnpike
Middlebury, Connecticut 06762
Or Emailed to Diana J. Errico-Topolski@usace.army.mil Diana.J.Errico- Topolski@usace.army.mil.
II. Technical Requirements:
Part 1 General:
1. Summary – Furnish all labor, materials, and equipment to lead abate, mechanically prepare, level and repair damaged substrate if necessary, and apply an epoxy floor coating system to one (1) West Side Main floor including generator room, one (1) West side second floor including trolley corridor, tool room, equipment platform, bathroom and furnace room, and one (1) East side main level including trolley corridor and equipment platform at the Stamford Hurricane Barrier.
2. Submittals – Although the Government technically reviews submissions required by this
Statement of Work, it is emphasized that the Contractor’s work must be completed using proper internal controls and review procedures. The documents identified below must be prepared in accordance with the applicable standards, submitted to the Technical Point of Contact for review and accepted by the Government prior to the commencement of any field activities.
Accident Prevention Plan (APP) including Fall Protection Plan) to include mechanical floor preparation plan (barriers, ventilation, dust collection, protection of equipment or materials not being treated etc.) – Prior to the start of field work
Activity Hazard Analysis – Prior to the start of field work Lead Based Paint Disposal Plan (LBPDP) Copy of contractor’s Connecticut license or certification to handle and dispose of lead paint.
Documentation of legal disposal of lead paint at an authorized facility(documentation required after disposal and prior to final payment) Epoxy flooring product and color sample – Prior to ordering Manufacturer’s product data sheets – Prior to ordering Manufacturer’s cut sheets for all new and replaced materials Warranty information
3. References – All work shall be in conformance with:
a. U.S. Army Corps of Engineers (USACE)
i. EM-385-1-1 2014 Safety and Health Requirements Manual, U.S. Army
Engineering Manual
b. Other appropriate Federal, State, and Local codes for such an installation
4. Existing Conditions:
a. West Abutment Main Floor:
i. Approximately 700 square feet of concrete flooring surface includes the West abutment main floor and generator room. See exhibits A-B. At least 1 or more of the existing paint layers is believed to contain lead paint. There could be sections of pitting, flaking paint, and unevenness that may need to be addressed in the preparatory phase of the floor resurfacing.
b. West Abutment Second Floor:
i. Approximately 550 square feet of concrete flooring surface includes the second floor tool room, equipment platform, trolley area, bathroom, and furnace room.
See exhibits C-E. At least 1 or more of the existing paint layers is believed to contain lead paint. There could be sections of pitting, flaking paint, and unevenness that may need to be addressed in the preparatory phase of the floor resurfacing.
c. East Abutment Main Floor:
i. Approximately 400 square feet of concrete flooring includes the main floor, equipment platform and trolley area. See exhibits F-G. At least 1 or more of the existing paint layers is believed to contain lead paint. There could be sections of pitting, flaking paint, and unevenness that may need to be addressed in the preparatory phase of the floor resurfacing.
NOTE: The Government will move any non-fixed items off of the floor surface prior to the start of work.
5. Clean Up and Waste Disposal – The contractor shall practice good housekeeping to maintain a safe job site. The contractor shall keep the work area, including any designated storage areas free from accumulation of waste materials. Upon completing work in an area the contractor shall remove any tools, equipment, and materials that are not the property of the Government. Any and all disturbed areas resulting from contractor activities shall be restored by the contractor to the satisfaction of the Technical Point of Contact. All waste material will be disposed of offsite in accordance with all Federal, State, and Local regulations.
6. Environmental Protection – Containers for excess and/ or waste materials, rubbish, etc.
shall be provided by the contractor at the site, and the site will be inspected/ cleaned on a daily basis when working onsite. Water, air and land resources shall not be adversely impacted during the course of the work. The contractor will take necessary steps to ensure all Federal, State, and Local environmental regulatory requirements are met at no additional cost to the Government. Assurance of compliance with this section by subcontractors shall be the responsibility of the contractor.
7. Sustainability & Environmentally Preferred Products – All products provided by the contractor must meet the recycled content requirements set forth by the Environmental Protection Agency. Under the Comprehensive Procurement Guidelines (CPG) program, the Environmental Protection Agency (EPA) designates products that are or can be made with recovered materials, and recommends practices for buying these products. Any designated product that is being offered or supplied under this contract shall meet the minimum recommended content levels as identified under the CPG program. Visit https://www.epa.gov/smm/comprehensive-procurement-guideline-cpgprogram for a complete list of designated products and the associated recommended contents levels.
Offerors must be able to demonstrate that each offered products meets minimum content levels upon request.
Furthermore, the contractor shall provide Safer Choice labeled products under this contract, as applicable. The contractor is encouraged to visit https://www.epa.gov/saferchoice/products for updated lists of qualifying products. Products that are identified as “environmentally preferable” have a lesser or reduced effect on human health and the environment when compared with competing products that serve the same purpose, and bio-based will be selected over those which do not carry such designations. The United States Department of Agriculture (USDA) designates certain bio-based products for federal procurement and specifies minimum bio based content levels for those products. Any designated product that is being offered or supplied under this contract shall meet USDA BioPreferred's minimum bio based content level. Visit the BioPreferred web site https://www.biopreferred.gov/BioPreferred/faces/pages/ProductCategories.xhtml for the complete list of designated products and the associated minimum bio based content level requirements.
8. Building Protection – Any involved building or structure, and all of its contents shall be protected from the elements during the duration of this contract. The contractor shall keep on site the means to quickly cover and protect all areas open to the elements during an unforeseen weather related event that could cause damage to the building and or any of its contents during all phases of this contract.
9. Personal Protective Equipment - It is the contractor’s responsibility to furnish and supply personnel with the proper personal protective equipment necessary for performing the work.
10. Government Resources – The government will supply any electricity necessary for the project work from points of existing outlets when available. The contractor shall carefully conserve the use of electricity provided. The contractor shall supply his own means of communication (telephone). There is not a restroom available at the contract site, and there is no access to potable water at the contract site. The contractor would have to provide these resources or have an acceptable alternative plan for these resources.
11. Damage to Government and Private Property – The contractor shall be responsible for restoring all Government facilities or structures damaged as a result of the contractor’s operation. The contractor shall also be responsible for any damage to private property or injury to any person as a result of the contractor’s operation. The contractor shall notify the Project Manager immediately of damage to Government and private property and injury to any person resulting from the contractor’s operation. Also, the Contractor shall notify the Technical Point of Contact of damage to Government facilities due to vandalism or other causes on the day such damage is first noticed. Trucks and/or trailers will be driven on existing roads only and not across or through park areas to facilities. The Contractor shall also restore landscape features (shrubs, flowers, grasses, etc.), which are damaged or destroyed by the contractor’s operation. Damaged or destroyed grass areas shall be re-planted as directed by the Technical Point of Contact, and shrubs and flowers which are damaged or destroyed shall be replaced from nursery stock of like size and kind.
12. Omissions – This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state, or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.
13. Quality Assurance – The contractor is responsible for the quality control of the contract work. The contractor shall establish and maintain a quality control system to assure compliance with the contract requirements. The government has the right to inspect and test all items called for by the contract, to the extent practicable at all times and at all places during the term of the contract.
14. Other Contracts – The Government may undertake or award other contracts for additional work not related to this contract, and the contractor shall fully cooperate with other contractors and Government employees. The contractor shall not commit or permit any act which will interfere with the performance of work by another contractor or by Government employees.
15. Receiving and Storing Materials – The contractor is responsible for protecting any stored material until it is placed in service. The contractor is responsible for receiving and unloading of delivered goods. Government employees will not receive materials or supplies for the contractor and will not be responsible for damage to the contractor’s equipment or materials.
16. Requests for information – Requests concerning the work of this project should be directed to the Technical Point of Contact, Part 2 Products:
All products shall be new, unused and to the satisfaction of the Technical Point of Contact.
Products shall be approved by the Technical Point of Contact prior to installation.
1. Concrete floor epoxy coating system shall meet the following requirements:
a. Will not chip, crack, or peel.
b. Waterproof product intended to protect concrete from heavy traffic, oil, chemicals.
c. Meets or exceeds OSHA standards for traction.
d. One primer coat of epoxy floor primer.
e. Two coats of a 100% solids epoxy flooring system.
f. One or two topcoats per the manufacturer’s application recommendations.
g. Final floor thickness shall be at minimum total thickness of 1/8”.
2. Color shall be medium to dark grey, and approved by the Technical Point of Contact. (Color samples shall be submitted for approval.)
3. Flooring texture shall be an orange peel texture, and sample provided shall be approved by the Technical Point of Contact.
Part 3 Execution:
1. Safety Equipment: It is the Contractor’s responsibility to furnish and supply personnel with the proper personal protective equipment (Hardhats, Hand Protection, Eye Protection, Ventilation, etc.) when and where necessary.
2. Preparation:
The Contactor shall supply all materials, equipment and labor to prepare the floor surface for the epoxy coating. Surface preparation shall include lead abatement of existing painted surfaces, and mechanically preparing the floor surface by grinding, shot blasting or other means as specified by the approved product. Floor must be clean and sound prior to application. Floor must be leveled to manufacture standards to ensure an even application of the epoxy product. This shall be done according to the best practice standards for this type of epoxy.
a. Appropriate Personal Protective Equipment (PPE) shall be utilized for each step of this job including protection from potentially hazardous airborne particulates that could be inhaled.
b. Industry standard containment barriers, dust collection mechanisms, and ventilation systems with dust collection capabilities shall be properly utilized and functioning during mechanical preparation of floor surfaces.
c. Appropriate protection shall be incorporated around any wood surfaces, plumbing and electrical components, and any other surface that could be damages due to the mechanical preparation of the floor surface.
d. All floor openings shall be properly blocked and taped during the mechanical preparation of floor surfaces.
e. If blasting, the recommended blasting media is glass beads or similar non-toxic blasting media to obtain an appropriate Concrete Surface Profile (CSP) recommended for the epoxy floor coating system.
f. NOTE: SILICA SAND MAY NOT BE USED ON FEDERAL INSTALLATIONS
AS A BLAST MEDIA
g. The Contractor shall dispose of any paint, dust, and other waste materials according to Federal, State, and Local requirements regarding this type of material.
3. Application of Epoxy Coating:
The Contractor shall supply all materials, equipment, and labor necessary to properly epoxy coat the Stamford Hurricane Barrier floors.
a. The Contractor shall prepare the floor surface to receive epoxy coating.
b. The Contractor shall furnish and apply one (1) primer coat of epoxy flooring primer.
c. The Contractor shall apply two (2) coats of a 100% solids epoxy flooring system.
d. The Contractor shall apply one (1) or two (2) coats of a topcoat, per the manufacturer’s application recommendation.
e. The epoxy floor coating shall be applied evenly to assure seamless coverage of the concrete floor surface. The final floor thickness shall be at minimum total thickness of 1/8”.
f. The Contractor shall follow all cure times and manufacturer recommendations regarding surface preparation, humidity, and temperature.
4. Disposal:
The Contractor shall dispose of all materials in the appropriate waste streams. Any new and unused epoxy product shall be mixed and cured before being disposed in required waste streams.
(End of Summary of Changes)