Stamford Hurricane Barrier, Stamford, CT, Lead Abatement and Resurfacing of Concrete Floors
Solicitation number
W912WJ20Q0146
Issued by

View the file

Other files

File Type Posted
Amendment_W912WJ20Q0146_0002.pdf PDF
Amendment_W912WJ20Q0146_0001.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STAMFORD HURRICANE BARRIER

DIANA ERRICO-TOPOLSKI

PO BOX 396 DYKE LANE

STAMFORD CT 06904-0394

TEL: 203-729-8840 FAX: 203723-9166

W13G86019775250001

REQUEST FOR QUOTATIONS

(THIS IS NOT AN ORDER) 1

PAGE OF PAGES

1. REQUEST NO. 2. DATE ISSUED RATING

W912WJ20Q0146 08-Sep-2020 5a. ISSUED BY

8. TO: NAME AND ADDRESS, INCLUDING ZIP CODE

IMPORTANT: This is a request for information, and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or services. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this

Request for Quotations must be completed by the quoter.

11. SCHEDULE (Include applicable Federal, State, and local taxes)

ITEM NO.

(a)

SUPPLIES/ SERVICES

(b)

QUANTITY

(c)

UNIT

(d)

UNIT PRICE

(e) (f)

SEE SCHEDULE

AMOUNT

% No. %

NOTE: Additional provisions and representations [ ] are [ ] are not attached.

13. NAME AND ADDRESS OF QUOTER (Street, City, County, State, and ZIP Code)

14. SIGNATURE OF PERSON AUTHORIZED TO

SIGN QUOTATION

15. DATE OF

QUOTATION

16. NAME AND TITLE OF SIGNER (Type or print) (Include area code)

TELEPHONE NO.

AUTHORIZED FOR LOCAL REPRODUCTION STANDARD FORM 18 (REV. 6-95)

PREVIOUS EDITION NOT USABLE Prescribed by GSA FAR (48 CFR) 53.215-1(a)

THIS RFQ X[ ] IS [ ] IS NOT A SMALL BUSINESS SET-ASIDE

6. DELIVER BY (Date)

SEE SCHEDULE

AND/OR DMS REG. 1

UNDER BDSA REG. 2

4. CERT. FOR NAT. DEF.3. REQUISITION/PURCHASE

REQUEST NO.

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

9. DESTINATION (Consignee and address, including ZIP Code)

7. DELIVERY

[ ]X FOB

DESTINATION

[ ] OTHER

(See Schedule)

18-Sep-2020(Date)

PLEASE FURNISH QUOTATIONS TO THE ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS:10.

AMANDA N LANE

(Name and Telephone no.) (No collect calls)5b. FOR INFORMATION CALL:

d. CALENDAR DAYSc. 30 CALENDAR DAYSb. 20 CALENDAR DAYS12. DISCOUNT FOR PROMPT PAYMENT a. 10 CALENDAR DAYS

W912WJ20Q0146

Section B - Supplies or Services and Prices

INSTRUCTIONS TO OFFERORS

*SITE VISITS ARE HIGHLY RECOMMENDED PRIOR TO PROVIDING A QUOTE. SEE CLAUSE 52.236-27

FOR ADDITIONAL INFORMATION.

*PLEASE DIRECT QUESTIONS TO AMANDA LANE AT (978) 318-8814 or

AMANDA.N.LANE@USACE.ARMY.MIL. ANY INFORMATION RECEIVED AT THE SITE VISIT WHICH

CONFLICTS WITH THIS SOLICITAION SHOULD BE BROUGHT TO THE ATTENTION OF AMANDA

LANE. THE SOLICITATION AND RESULTING CONTRACT SHALL BE THE GOVERNING DOCUMENT

IN ALL CASES.

**QUOTES CAN BE E-MAILED TO AMANDA LANE AT AMANDA.N.LANE@USACE.ARMY.MIL.

NOTE 1: In accordance with FAR Part 28.102-1(b), the Contractor will be required to provide the following payment protections for all construction contracts greater than $150,000.00.

(i) Payment Bond or

(ii) Irrevocable Letter of Credit and

(iii) Performance Bond

A Payment Bond or Irrevocable Letter of Credit is the SELECTED payment protection for the Government. The penal amount of bond shall be 100% of the original contract price. If the contract price increases, the Government will require an increase in the penal sum of the existing bond. This bond shall be submitted to the Contracting Officer within 10 days after receipt of award.

A Performance Bond shall be required if the total price of the quote is greater than $150,000.00. The penal amount of the Performance Bond shall be 100% of the original contract price. If the contract price increases, the Government will require an increase in the penal sum of the existing bond. This bond shall also be submitted to the Contracting Officer within 10 days after receipt of award.

NOTE 2: In accordance with FAR Part 28.102-1(c), the Contractor will be required to provide one of the following payment protections for all construction contracts greater than $35,000.00 but not greater than $150,000.00.

(i) Payment bond or

(ii) Irrevocable letter of credit

A Payment Bond or Irrevocable Letter of Credit is the SELECTED payment protection for the Government. The penal amount of bond shall be 100% of the original contract price. If the contract price increases, the Government will require an increase in the penal sum of the existing bond. This bond shall be submitted to the Contracting Officer within 10 days after receipt of award.

**No Payment Protections Required for construction contracts less than $35,000**

NOTE 3:

QUOTATION INSTRUCTIONS:

1. If subcontractor will be used for this work, please provide company names:

2. In accordance with FAR Part 52.204-7(b)(1) Contractors must be registered in the System for Award Management (SAM) database (www.SAM.gov) to submit an offer. (Formerly the Central Contractor Registration (CCR) database and the On-Line Representations and Certifications (ORCA).) Any reference to CCR or ORCA in any clause or provision is referring to the www.sam.gov website. Please note that Google and Google Chrome are not supported browsers for SAM registration. Mozilla FireFox, Safari, and Internet Explorer are supported browsers.

NOTE: SAM.gov registration takes approximately 3 weeks (DUNS registration 1-2 business days; CAGE code validation up to 10 business days; IRS validation and overall submission 7-10 business days). It is the contractor’s responsibility to track SAM.gov registration and follow-up with required tasks.

In addition, if you are registering a new entity in SAM.gov, you must provide an original, signed notarized letter stating that you are the authorized Entity Administrator. The Entity Administrator must establish a LOGIN.GOV account using the e-mail address that will be associated with the SAM registration. See https://www.gsa.gov/about-us/organization/federal-acquisition-service/office-of-systems-management/integrated-award-environment-iae/sam-update for additional information.

3. Provide business DUNS number: _______________________________ (phone 800-333-0505 for DUNS).

4. Provide business CAGE code: __________________________________

5. Tax Identification Number: ___________________________________

6. Contractors shall provide completed FAR clause 52.204-8 (Annual Representations and Certifications) found in Section K of this solicitation with their quote, if the Contractors have not completed their annual representations and certifications electronically via the SAM website at www.sam.gov. (See Paragraph 2 above).

7. Contractors are not required to submit an Accident Prevention Plan (APP) with their quote. The successful offeror will be required to submit this document at the direction of the Technical Point of Contact. The APP must be accepted by the Government Designated Authority prior to the commencement of work.

POTENTIAL QUOTERS ARE NOTIFIED THAT THE BASIS ON WHICH AWARD WILL BE MADE IS PRICE

ALONE.

ALL RESPONSIBLE SOURCES MAY SUBMIT A RESPONSE WHICH, IF TIMELY RECEIVED, MUST BE

CONSIDERED BY THE AGENCY.

INVOICES SHALL BE SENT TO TECHNICAL POINT OF CONTACT.

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job SHB Lead Abatement & Resurface

FFP

Contractor shall furnish all labor, materials and equipment necessary to lead abate, prepare, and epoxy coat all concrete floors at the Stamford Hurricane Barrier, Stamford, CT in accordance with the Statement of Work.

FOB: Destination

MILSTRIP: W13G8601977525

PURCHASE REQUEST NUMBER: W13G86019775250001

PSC CD: Y1QA

NET AMT

Section C - Descriptions and Specifications

STATEMENT OF WORK

LEAD ABATEMENT AND RESURFACE CONCRETE FLOORS

U.S. ARMY CORPS OF ENGINEERS

STAMFORD HURRICANE BARRIER

STAMFORD, CONNECTICUT

Statement of Work

I. General:

1. Scope – Furnish all labor, materials and equipment necessary to lead abate, prepare, and epoxy coat all concrete floors at the West and East Abutments of the Stamford Hurricane Barrier in Stamford Connecticut including, the West and East Main floors, generator room, west side second floor equipment area, West and East trolley corridors, concrete equipment platforms, bathroom, and furnace room. The Contractor must be qualified to handle and dispose of lead paint in accordance with all federal and state laws and regulations. The work includes the following:

a. Lead abatement of existing painted coating.

b. Mechanical preparation of the concrete substrate in accordance with manufacturer’s preparation recommendations.

c. Application of the epoxy floor coating system in accordance with manufacturer’s application recommendations.

2. Location – The Stamford Hurricane Barrier (West Branch) is located at 230 Elmcroft Road Stamford CT. The East Branch is located at 140 Harbor Drive Stamford CT.

3. Site Visit – Contact the Technical Point of Contact to arrange a site visit. The Technical Point of Contact for the project is Project Manager, Diana J. Errico-Topolski (978-318-8370 or Diana J. Errico-Topolski@usace.army.mil).

4. Schedule – The work shall be completed no later than 120 days from Notice to Proceed (NTP). Contractor shall commence work within 14 calendar days after NTP. Work shall be performed Monday through Friday 8:30 AM to 4:00 PM unless otherwise approved by the Technical Point of Contact. No work shall be done on weekends or Government holidays.

5. Safety Requirements – All work shall be conducted in accordance with the U.S. Army Corps of Engineers Safety and Health Requirements Manual (EM 385-1-1, most recent edition), and all applicable OSHA, federal, state, and local safety and health requirements. A copy of EM 385-1-1 can be accessed at the project office or electronically at Headquarters USACE website under publications using the following link:

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385- 1-1.pdf

Project staff reserve the right to cease work at any time should the safety of employees, Contractors, and/or the public become jeopardized.

a. Accident Prevention Plan:

The Contractor shall prepare an Accident Prevention Plan (APP) specific to the activities being performed. It shall include Activity Hazard Analyses (AHAs) as described below.

A non-mandatory, fillable APP template is available upon request. However, the contractor is permitted to submit their own plan, at a minimum it must meet the requirements of EM 385-1-1, Appendix A, Section K.

A preparatory meeting shall be conducted by the prime contractor to discuss the APP contents with all effected onsite employees. The Prime Contractor is responsible for informing their subcontractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.

Weekly safety meetings shall be held and documented. Records shall be available to the TPOC upon request.

COVID 19: Procedures shall be documented in the Abbreviated Accident Prevention Plan and in the appropriate AHA’s to address site specific COVID-19 monitoring procedure which address at the minimum, the following items:

Contractor shall provide employees with and require them to use all required COVID-

19 related PPE in accordance with CDC and state guidelines.

Procedures shall be in place for periodic sanitation inspections and disinfecting of project sites and work areas in accordance with CDC guidelines.

Site specific procedures shall be in place to practice and promote appropriate social distancing while on site, when such procedure are practical.

Employees shall be trained in signs, symptoms and protection measures in accordance with CDC guidelines.

b. Activity Hazard Analysis (AHA):

An AHA shall be submitted for each major phase of work. A major phase of work is defined as an operation involving a type of work presenting hazards not experienced in previous operations or where a new subcontractor or work crew is to perform the work.

The analysis shall define all activities to be performed, identify the sequence of work, the specific hazards anticipated, and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level. The AHA shall be continuously reviewed and revised to address changing site conditions as appropriate.

c. Emergency Response:

Emergency procedures shall be documented in the Accident Prevention Plan and will include a map with directions to the nearest hospital, emergency contact numbers, and onsite First Aid/CPR responders.

d. Required Personnel:

The Contractor shall employ a minimum of one Competent Person (CP) at each project site to function as the Site Safety and Health Officer (SSHO). The SSHO shall be present at the project site and report to the contractor’s upper management. The SSHO is required to have related construction experience and have at a minimum completed a 10 Hour OSHA training.

In addition, when emergency medical services are not accessible within five (5) minutes of the work location and there are two (2) or more workers onsite, at least two (2) employees shall have (in-person) training in First Aid and CPR. Minimum qualifications are listed in EM 385-1-1, Section 03.A.02.c.

*Note: Other Competent or Qualified Persons may be required per EM 385-1-1 and/or other sections of this Statement of Work, based on the characteristics of the project*

e. Accident Reporting:

All accidents and near misses shall be investigated by the Contractor. All work-related recordable injuries, illnesses and property damage accidents (excluding on-the-road vehicle accidents), in which the property damage exceeds $5,000.00, shall be verbally reported to the TPOC within four (4) hours of the incident. Serious accidents as described in EM 385-1-1 Section 01.D shall be immediately reported to the TPOC. ENG Form 3394 shall be completed and submitted to the TPOC within five (5) working days of the incident.

The Contractor shall compile employee work hours (including subcontractors) and forward the total hours to the TPOC no later than close of business on the 10th calendar day of the following month. The method of transmission by the prime contractor to the TPOC shall be electronically.

6. Specific Safety Section-Lead Based Paint Abatement

a. General: The requirements of this section are applicable to contracts involving activities that disturb Lead-based paint (LBP). All LBP activities, training, and submittals shall comply with EM 385-1-1, Section 06.C; 29 CFR 1910.1025; 29 CFR 1926.62; as well as State, and local requirements.

b. Submittals: A site-specific Lead Compliance Plan is required to be submitted and accepted by the Technical Point of Contact (TPOC) prior to initiating lead abatement tasks. This plan shall be developed as an appendix to the APP and describe procedures to be followed to protect contractor and government employees, the environment, and general public from lead hazards while performing lead hazard control activities.

Specifically, the Lead Compliance Plan shall address the following:

i. A description of each work activity in which lead is emitted, to include equipment and materials used, controls in place, crew size, job responsibilities, operating procedures, and maintenance practices, work activity locations and lead-containing components keyed to the project drawings;

ii. Description of means to be used to achieve exposure compliance, including any engineering controls;

iii. Employee exposure assessment procedures to monitor and document employee lead exposure. Exposure monitoring shall include two types:

1) Initial determination (may be omitted if there is sufficient objective/historical data showing action level compliance according to the requirements); and

2) Continued exposure monitoring required as a result of initial exposure determinations.

iv. Protective clothing, housekeeping procedures to prevent spread of lead contamination both in and beyond the lead hazard control area, and hygiene facilities and practices to prevent employees from inadvertent ingestion of lead;

v. Administrative controls to limit employee exposure to lead, including employee rotation schedule to be employed, if engineering controls or PPE fail to eliminate exposures exceeding the PEL;

vi. Medical surveillance procedures to monitor employee exposures and ensure fitness for wearing respiratory protection;

vii. Competent person (CP) and employee training required;

viii. Detailed sketches identifying lead hazard control areas, including decontamination areas and facilities, critical barriers, and physical and air distribution boundaries;

ix. Perimeter or other area air monitoring outside or adjacent to the regulated area;

x. Security required for each lead hazard control area; and

xi. Waste generation, characterization, transportation, and disposal (including recordkeeping).

c. Required Certifications and Licenses:

i. The contractor must be licensed in lead abatement by the EPA or applicable state where the work will be completed.

ii. At least one onsite employee will be designated as the lead abatement competent person and be certified as a Lead Abatement Supervisor by the EPA or applicable state where the work will be completed.

iii. At a minimum, site workers involved with lead abatement activities must be certified as Lead Abatement Workers by the EPA or applicable state where the work will be completed.

iv. Copies of certificates and licenses shall be kept on site and available for review if requested by the TPOC.

d. Final Clearance Sampling: For interior lead abatement projects, a 3rd party, independent clearance examiner must assess the areas impacted by the abatement activities. The examiner must be a Certified Industrial Hygienist (CIH), Certified Risk Assessor, or a Certified Lead-Based Paint Inspector.

i. Dust samples shall be collected in accordance with ASTM Standard E 1728 and analyzed by a laboratory recognized by the EPA’s National Lead Laboratory Accreditation Program (NLLAP).

7. Pre-Construction Conference – Prior to the start of any work, the Technical Point of Contact will schedule and conduct a “Pre-Construction Conference”. The Contractor’s Project Manager and Quality Control Personnel will attend this meeting. This conference will be held at the time and location agreeable to the government and contractor. No work may be performed under this contract prior to this conference. The purpose of the conference is to enable the Technical Point of Contact to outline the procedures that will be followed by the Government in its administration of the contract, and to discuss the performance that will be expected from the Contractor. This conference will allow the Contractor an opportunity to ask questions about the Government’s administration and inspection of contract work or obtain other pertinent information that might be required. At the Pre-Construction conference the contractor shall provide the name of the project superintendent with a telephone number for project coordination.

The following is a general list of items for discussion during this Pre-Construction Conference:

i. Authority of the Technical Point of Contact and Quality Assurance Inspectors.

ii. Contractor’s Safety Program (including sub-contractors).

iii. Accident Prevention Plan and Activity Hazard Analysis (Submitted & accepted prior to start of work on site)

iv. Accident Reporting (ENG Form 3394)

v. Fall Protection Plan IAW EM 385-1-1, Section 21

vi. Safety Data Sheet (SDS) requirements

vii. Contractor’s Equipment

viii. Correspondence, Communication, Security and Administrative Procedures.

ix. Invoice and payment.

8. Permits – The Contractor shall, without additional expense to the Government, be responsible for obtaining any necessary licenses, permits, and letters of certification. The Contractor shall comply with any applicable Federal, State, County, and Municipal laws, codes, and regulations in connection with the performance of the work specified under this contract.

9. Security – The contractor will comply with all established security policies at the Stamford Hurricane Barrier. Due to periods of heightened security that may affect the access to the areas covered under this contract, the Government reserves the right to close any property or portion of property and reschedule and/or cancel any subsequent service. The Contractor shall be given at least 24 hour notice of any such closure.

10. Contractor Conduct – Alcohol and firearms are prohibited on project grounds. Contractor and employees must comply with CFR 36 Rules and Regulations.

11. Payment – After final inspection and acceptance by the Government, the Contractor must submit an invoice to the Technical Point of Contact. The invoice shall include the invoice date, contract number, dates of service, description of work, quantities, process, and total amount due per line item. The invoice must also include the company letterhead and this must match the data that is registered in the System for Award Management (SAM) registry.

For jobs greater than 30 days the contractor may request progress payment.

All invoices may be mailed to U.S. Army Corps of Engineers Hop Brook Lake

4 Straits Turnpike Middlebury, Connecticut 06762

Or Emailed to Diana J. Errico-Topolski@usace.army.mil

II. Technical Requirements:

Part 1 General:

1. Summary – Furnish all labor, materials, and equipment to lead abate, mechanically prepare, level and repair damaged substrate if necessary, and apply an epoxy floor coating system to one (1) West Side Main floor including generator room, one (1) West side second floor including trolley corridor, tool room, equipment platform, bathroom and furnace room, and one (1) East side main level including trolley corridor and equipment platform at the Stamford Hurricane Barrier.

2. Submittals – Although the Government technically reviews submissions required by this

Statement of Work, it is emphasized that the Contractor’s work must be completed using proper internal controls and review procedures. The documents identified below must be prepared in accordance with the applicable standards, submitted to the Technical Point of Contact for review and accepted by the Government prior to the commencement of any field activities.

Accident Prevention Plan (APP) including Fall Protection Plan) to include mechanical floor preparation plan (barriers, ventilation, dust collection, protection of equipment or materials not being treated etc.) – Prior to the start of field work

Activity Hazard Analysis – Prior to the start of field work Lead Based Paint Disposal Plan (LBPDP) Copy of contractor’s Connecticut license or certification to handle and dispose of lead paint.

Documentation of legal disposal of lead paint at an authorized facility(documentation required after disposal and prior to final payment) Epoxy flooring product and color sample – Prior to ordering Manufacturer’s product data sheets – Prior to ordering Manufacturer’s cut sheets for all new and replaced materials Warranty information

3. References – All work shall be in conformance with:

a. U.S. Army Corps of Engineers (USACE)

i. EM-385-1-1 2014 Safety and Health Requirements Manual, U.S. Army

Engineering Manual

b. Other appropriate Federal, State, and Local codes for such an installation

4. Existing Conditions:

a. West Abutment Main Floor:

i. Approximately 700 square feet of concrete flooring surface includes the West abutment main floor and generator room. See exhibits A-B. At least 1 or more of the existing paint layers is believed to contain lead paint. There could be sections of pitting, flaking paint, and unevenness that may need to be addressed in the preparatory phase of the floor resurfacing.

b. West Abutment Second Floor:

i. Approximately 550 square feet of concrete flooring surface includes the second floor tool room, equipment platform, trolley area, bathroom, and furnace room.

See exhibits C-E. At least 1 or more of the existing paint layers is believed to contain lead paint. There could be sections of pitting, flaking paint, and unevenness that may need to be addressed in the preparatory phase of the floor resurfacing.

c. East Abutment Main Floor:

i. Approximately 400 square feet of concrete flooring includes the main floor, equipment platform and trolley area. See exhibits F-G. At least 1 or more of the existing paint layers is believed to contain lead paint. There could be sections of pitting, flaking paint, and unevenness that may need to be addressed in the preparatory phase of the floor resurfacing.

NOTE: The Government will move any non-fixed items off of the floor surface prior to the start of work.

5. Clean Up and Waste Disposal – The contractor shall practice good housekeeping to maintain a safe job site. The contractor shall keep the work area, including any designated storage areas free from accumulation of waste materials. Upon completing work in an area the contractor shall remove any tools, equipment, and materials that are not the property of the Government. Any and all disturbed areas resulting from contractor activities shall be restored by the contractor to the satisfaction of the Technical Point of Contact. All waste material will be disposed of offsite in accordance with all Federal, State, and Local regulations.

6. Environmental Protection – Containers for excess and/ or waste materials, rubbish, etc.

shall be provided by the contractor at the site, and the site will be inspected/ cleaned on a daily basis when working onsite. Water, air and land resources shall not be adversely impacted during the course of the work. The contractor will take necessary steps to ensure all Federal, State, and Local environmental regulatory requirements are met at no additional cost to the Government. Assurance of compliance with this section by subcontractors shall be the responsibility of the contractor.

7. Sustainability & Environmentally Preferred Products – All products provided by the contractor must meet the recycled content requirements set forth by the Environmental Protection Agency. Under the Comprehensive Procurement Guidelines (CPG) program, the Environmental Protection Agency (EPA) designates products that are or can be made with recovered materials, and recommends practices for buying these products. Any designated product that is being offered or supplied under this contract shall meet the minimum recommended content levels as identified under the CPG program. Visit https://www.epa.gov/smm/comprehensive-procurement-guideline-cpgprogram for a complete list of designated products and the associated recommended contents levels.

Offerors must be able to demonstrate that each offered products meets minimum content levels upon request.

Furthermore, the contractor shall provide Safer Choice labeled products under this contract, as applicable. The contractor is encouraged to visit https://www.epa.gov/saferchoice/products for updated lists of qualifying products. Products that are identified as “environmentally preferable” have a lesser or reduced effect on human health and the environment when compared with competing products that serve the same purpose, and bio-based will be selected over those which do not carry such designations. The United States Department of Agriculture (USDA) designates certain bio-based products for federal procurement and specifies minimum bio based content levels for those products. Any designated product that is being offered or supplied under this contract shall meet USDA BioPreferred's minimum bio based content level. Visit the BioPreferred web site https://www.biopreferred.gov/BioPreferred/faces/pages/ProductCategories.xhtml for the complete list of designated products and the associated minimum bio based content level requirements.

8. Building Protection – Any involved building or structure, and all of its contents shall be protected from the elements during the duration of this contract. The contractor shall keep on site the means to quickly cover and protect all areas open to the elements during an unforeseen weather related event that could cause damage to the building and or any of its contents during all phases of this contract.

9. Personal Protective Equipment - It is the contractor’s responsibility to furnish and supply personnel with the proper personal protective equipment necessary for performing the work.

10. Government Resources – The government will supply any electricity necessary for the project work from points of existing outlets when available. The contractor shall carefully conserve the use of electricity provided. The contractor shall supply his own means of communication (telephone). There is not a restroom available at the contract site, and there is no access to potable water at the contract site. The contractor would have to provide these resources or have an acceptable alternative plan for these resources.

11. Damage to Government and Private Property – The contractor shall be responsible for restoring all Government facilities or structures damaged as a result of the contractor’s operation. The contractor shall also be responsible for any damage to private property or injury to any person as a result of the contractor’s operation. The contractor shall notify the

Project Manager immediately of damage to Government and private property and injury to any person resulting from the contractor’s operation. Also, the Contractor shall notify the Technical Point of Contact of damage to Government facilities due to vandalism or other causes on the day such damage is first noticed. Trucks and/or trailers will be driven on existing roads only and not across or through park areas to facilities. The Contractor shall also restore landscape features (shrubs, flowers, grasses, etc.), which are damaged or destroyed by the contractor’s operation. Damaged or destroyed grass areas shall be re-planted as directed by the Technical Point of Contact, and shrubs and flowers which are damaged or destroyed shall be replaced from nursery stock of like size and kind.

12. Omissions – This contract may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state, or federal standards, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.

13. Quality Assurance – The contractor is responsible for the quality control of the contract work. The contractor shall establish and maintain a quality control system to assure compliance with the contract requirements. The government has the right to inspect and test all items called for by the contract, to the extent practicable at all times and at all places during the term of the contract.

14. Other Contracts – The Government may undertake or award other contracts for additional work not related to this contract, and the contractor shall fully cooperate with other contractors and Government employees. The contractor shall not commit or permit any act which will interfere with the performance of work by another contractor or by Government employees.

15. Receiving and Storing Materials – The contractor is responsible for protecting any stored material until it is placed in service. The contractor is responsible for receiving and unloading of delivered goods. Government employees will not receive materials or supplies for the contractor and will not be responsible for damage to the contractor’s equipment or materials.

16. Requests for information – Requests concerning the work of this project should be directed to the Technical Point of Contact, Part 2 Products:

All products shall be new, unused and to the satisfaction of the Technical Point of Contact.

Products shall be approved by the Technical Point of Contact prior to installation.

1. Concrete floor epoxy coating system shall meet the following requirements:

a. Will not chip, crack, or peel.

b. Waterproof product intended to protect concrete from heavy traffic, oil, chemicals.

c. Meets or exceeds OSHA standards for traction.

d. One primer coat of epoxy floor primer.

e. Two coats of a 100% solids epoxy flooring system.

f. One or two topcoats per the manufacturer’s application recommendations.

g. Final floor thickness shall be at minimum total thickness of 1/8”.

2. Color shall be medium to dark grey, and approved by the Technical Point of Contact. (Color samples shall be submitted for approval.)

3. Flooring texture shall be an orange peel texture, and sample provided shall be approved by the Technical Point of Contact.

Part 3 Execution:

1. Safety Equipment: It is the Contractor’s responsibility to furnish and supply personnel with the proper personal protective equipment (Hardhats, Hand Protection, Eye Protection, Ventilation, etc.) when and where necessary.

2. Preparation:

The Contactor shall supply all materials, equipment and labor to prepare the floor surface for the epoxy coating. Surface preparation shall include lead abatement of existing painted surfaces, and mechanically preparing the floor surface by grinding, shot blasting or other means as specified by the approved product. Floor must be clean and sound prior to application. Floor must be leveled to manufacture standards to ensure an even application of the epoxy product. This shall be done according to the best practice standards for this type of epoxy.

a. Appropriate Personal Protective Equipment (PPE) shall be utilized for each step of this job including protection from potentially hazardous airborne particulates that could be inhaled.

b. Industry standard containment barriers, dust collection mechanisms, and ventilation systems with dust collection capabilities shall be properly utilized and functioning during mechanical preparation of floor surfaces.

c. Appropriate protection shall be incorporated around any wood surfaces, plumbing and electrical components, and any other surface that could be damages due to the mechanical preparation of the floor surface.

d. All floor openings shall be properly blocked and taped during the mechanical preparation of floor surfaces.

e. If blasting, the recommended blasting media is glass beads or similar non-toxic blasting media to obtain an appropriate Concrete Surface Profile (CSP) recommended for the epoxy floor coating system.

f. NOTE: SILICA SAND MAY NOT BE USED ON FEDERAL INSTALLATIONS

AS A BLAST MEDIA

g. The Contractor shall dispose of any paint, dust, and other waste materials according to Federal, State, and Local requirements regarding this type of material.

3. Application of Epoxy Coating:

The Contractor shall supply all materials, equipment, and labor necessary to properly epoxy coat the Stamford Hurricane Barrier floors.

a. The Contractor shall prepare the floor surface to receive epoxy coating.

b. The Contractor shall furnish and apply one (1) primer coat of epoxy flooring primer.

c. The Contractor shall apply two (2) coats of a 100% solids epoxy flooring system.

d. The Contractor shall apply one (1) or two (2) coats of a topcoat, per the manufacturer’s application recommendation.

e. The epoxy floor coating shall be applied evenly to assure seamless coverage of the concrete floor surface. The final floor thickness shall be at minimum total thickness of 1/8”.

f. The Contractor shall follow all cure times and manufacturer recommendations regarding surface preparation, humidity, and temperature.

4. Disposal:

The Contractor shall dispose of all materials in the appropriate waste streams. Any new and unused epoxy product shall be mixed and cured before being disposed in required waste streams.

ATTACHMENTS

PLEASE REFER TO THE ATTACHMENTS INCLUDED AT THE END OF THIS SOLICITATION FOR

ADDITIONAL INFORMATION.

Section F - Deliveries or Performance

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 120 dys. ANP 1 STAMFORD HURRICANE BARRIER

DIANA ERRICO-TOPOLSKI

PO BOX 396 DYKE LANE

STAMFORD CT 06904-0394

203-729-8840 FOB: Destination

961106

Section H - Special Contract Requirements

SECURITY REQUIREMENTS

The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the Technical Point of Contact NLT 5 calendar days after the completion of the training.

WAGE DETERMINATION

"General Decision Number: CT20200020 07/10/2020

Superseded General Decision Number: CT20190020

State: Connecticut

Construction Type: Building

County: Fairfield County in Connecticut.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.80 for calendar year 2020 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.80 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2020. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/03/2020 1 01/17/2020 2 01/24/2020 3 02/21/2020 4 04/24/2020 5 05/08/2020 6 05/15/2020 7 05/22/2020 8 06/05/2020 9 07/03/2020 10 07/10/2020

ASBE0033-002 06/01/2019

Rates Fringes

HEAT & FROST INSULATOR

(Includes Duct, Pipe and Mechanical Systems)..............$ 40.21 30.99

BRCT0001-006 01/06/2020

Rates Fringes

BRICKLAYER.......................$ 35.71 34.34

BRCT0001-007 01/06/2020

Rates Fringes

CEMENT MASON/CONCRETE FINISHER...$ 35.71 34.34

CARP0326-024 05/04/2020

Rates Fringes

FLOOR LAYER: Carpet Only.........$ 34.53 25.64

CARP0326-025 05/04/2020

Rates Fringes

FLOOR LAYER: Hardwood Floors Only.............................$ 34.53 25.64

CARP0326-026 05/04/2020

Rates Fringes

METAL BUILDING ERECTOR (Metal Siding / Wall Panels)............$ 34.53 25.64

CARP0326-027 05/04/2020

Rates Fringes

CARPENTER (Scaffold Builder).....$ 34.53 25.64

CARP0326-028 05/04/2020

Rates Fringes

CARPENTER (Includes Acoustical Ceiling Installation, Drywall Hanging, Form Work, and Metal Stud Installation)...............$ 34.53 25.64

CARP0326-029 05/04/2020

Rates Fringes

SOFT FLOOR LAYER.................$ 34.53 25.64

CARP0326-030 05/04/2020

Rates Fringes

FLOOR LAYER: Vinyl Flooring Only.............................$ 34.53 25.64

CARP1121-006 01/06/2020

Rates Fringes

MILLWRIGHT.......................$ 34.94 26.19

ELEC0003-006 04/28/2016

Rates Fringes

ELECTRICIAN (Includes Low Voltage and Installation of Alarms and Sound and Communication Systems)...........$ 50.75 43.704

ELEC0488-003 06/01/2020

Rates Fringes

ELECTRICIAN (HVAC/Temperature Controls Installation)...........$ 39.92 3%+28.75

ELEV0091-002 01/01/2020

Rates Fringes

ELEVATOR MECHANIC................$ 55.12 34.765

ENGI0478-004 04/05/2020

POWER EQUIPMENT OPERATOR

(Backhoe/Excavator/Trackhoe).....$ 42.11 25.30

PAID HOLIDAYS: New Year's Day, Good Friday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day, provided the employee works 3 days during the week in which the holiday falls, if scheduled, and if scheduled, the working day before and the working day after the holiday.

ENGI0478-005 04/05/2020

Rates Fringes

POWER EQUIPMENT OPERATOR

(Bulldozer) Finegrade (Slopes, Shaping, laser or GPS, etc.).......................$ 41.32 25.30 Rough Grade Dozer...........$ 39.95 25.30

PAID HOLIDAYS: New Year's Day, Good Friday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day, provided the employee works 3 days during the week in which the holiday falls, if scheduled, and if scheduled, the working day before and the working day after the holiday.

ENGI0478-012 04/05/2020

Rates Fringes

POWER EQUIPMENT OPERATOR

(Crane under 100 ton rated capacity)).......................$ 41.32 25.30

When crane operator is operating equipment that requires a fully licensed crane operator to operate he receives an extra $4.00 premium in addition to the hourly wage rate and benefit contributions:

PAID HOLIDAYS: New Year's Day, Good Friday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day, provided the employee works 3 days during the week in which the holiday falls, if scheduled, and if scheduled, the working day before and the working day after the holiday.

ENGI0478-016 04/05/2020

POWER EQUIPMENT OPERATOR

(Loader - 7 cubic yards or over)............................$ 42.45 25.30

PAID HOLIDAYS: New Year's Day, Good Friday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day, provided the employee works 3 days during the week in which the holiday falls, if scheduled, and if scheduled, the working day before and the working day after the holiday.

IRON0424-001 06/01/2020

Rates Fringes

IRONWORKER (Reinforcing, Structural, Ornamental)..........$ 36.67 37.62

LABO0230-002 04/05/2020

Rates Fringes

LABORER (Mason Tender-Cement/Concrete)..........$ 31.50 22.15

PAIN0011-014 06/01/2020

Rates Fringes

GLAZIER..........................$ 39.18 22.55

PAIN0011-021 06/01/2020

Rates Fringes

PAINTER (Brush and Roller).......$ 35.62 22.55

PAIN0011-023 06/01/2020

Rates Fringes

DRYWALL FINISHER/TAPER...........$ 36.37 22.55

PLUM0777-001 06/01/2020

Rates Fringes

PLUMBER..........................$ 44.63 32.95

PLUM0777-003 06/01/2020

PIPEFITTER.......................$ 44.63 32.95

PLUM0777-009 06/01/2020

Rates Fringes

PIPEFITTER (HVAC Pipe Installation Only)...............$ 44.63 32.95

* ROOF0009-001 06/01/2020

Rates Fringes

ROOFER

Composition.................$ 38.40 21.89 Slate and Tile..............$ 38.90 21.89

SHEE0038-006 07/01/2020

Rates Fringes

SHEET METAL WORKER (Metal Flashing and HVAC Duct Installation Only)...............$ 46.67 42.80

SHEE0040-001 07/01/2020

Rates Fringes

SHEET METAL WORKER (Including HVAC Unit Installation)..........$ 38.90 39.46

SHEE0040-008 07/01/2020

Rates Fringes

SHEET METAL WORKER (Metal Roofs Installation)..............$ 38.90 39.46

TEAM0677-001 04/05/2020

Rates Fringes

TRUCK DRIVER (Dump Truck)........$ 30.08 25.79

* UAVG-CT-0001 01/01/2019

Rates Fringes

LABORER: Common or General......$ 31.00 22.15

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION"

Section I - Contract Clauses

CLAUSES INCORPORATED BY REFERENCE

52.204-13 System for Award Management Maintenance OCT 2018 52.204-18 Commercial and Government Entity Code Maintenance AUG 2020 52.204-19 Incorporation by Reference of Representations and

Certifications.

DEC 2014

52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment.

AUG 2020

52.209-10 Prohibition on Contracting With Inverted Domestic Corporations

NOV 2015