W912WJ19R0018_-_Amendment_0001.pdf
PDF 49 KB Posted
- Attached to
- Small Business General Design A-E IDIQ
- Solicitation number
- W912WJ19R0018
About this file
Amendment 0001- RFIs
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912WJ19R0018_-_Amendment_0003.pdf | ||
| W912WJ19R0018_-_Amendment_0002.pdf | ||
| Past_Performance_Questionnaire.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Information Amendment 0001 to W912WJ19R0018
SB General AE IDIQ
1. Can a firm provide one person to cover multiple disciplines requested? (i.e. Can the Mechanical HVAC & the Mechanical Plumbing be the same individual?)
GOVERNMENT RESPONSE: No.
2. Do the PPQs for the first 3 projects in Section F count toward the 60 page limitation in Part I?
If not, can we provide PPQs for other projects in Section F or only the first 3 projects?
GOVERNMENT RESPONSE: PPQs do not count against the page limit. Only PPQs for the first 3 projects are to be provided.
3. Do the projects have to be 100% complete or can they be “substantially” complete? We’ve seen both on solicitations but it is not explicitly identified in this solicitation other than limit to age of project. We have a project at Hanscom AFB with one of our proposed sub consultants and hope to use that project in Section F.
GOVERNMENT RESPONSE: Projects can be submitted for which the A-E firm has not yet fully completed their assigned tasks although such projects will be given less consideration.