Amendment 0001- RFIs

View the file

Other files

File Type Posted
W912WJ19R0018_-_Amendment_0003.pdf PDF
W912WJ19R0018_-_Amendment_0002.pdf PDF
Past_Performance_Questionnaire.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Information Amendment 0001 to W912WJ19R0018

SB General AE IDIQ

1. Can a firm provide one person to cover multiple disciplines requested? (i.e. Can the Mechanical HVAC & the Mechanical Plumbing be the same individual?)

GOVERNMENT RESPONSE: No.

2. Do the PPQs for the first 3 projects in Section F count toward the 60 page limitation in Part I?

If not, can we provide PPQs for other projects in Section F or only the first 3 projects?

GOVERNMENT RESPONSE: PPQs do not count against the page limit. Only PPQs for the first 3 projects are to be provided.

3. Do the projects have to be 100% complete or can they be “substantially” complete? We’ve seen both on solicitations but it is not explicitly identified in this solicitation other than limit to age of project. We have a project at Hanscom AFB with one of our proposed sub consultants and hope to use that project in Section F.

GOVERNMENT RESPONSE: Projects can be submitted for which the A-E firm has not yet fully completed their assigned tasks although such projects will be given less consideration.