Performance Work Statement
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_W912WJ19Q0125-0002.pdf | ||
| Map_2.pdf | ||
| Map_1.pdf | ||
| HDD_Construction_Photos.pdf | ||
| Amendment_W912WJ19Q0125-0001.pdf | ||
| Solicitation_W912WJ19Q0125.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 1
PERFORMANCE WORK STATEMENT
FOR
GEOPHYSICAL UTILITY TRACING
ACCESS CONTROL POINT AREA
US ARMY SOLDIER SYSTEMS CENTER, NATICK, MA
9 August 2019
Utility Geophysics Survey US Army Soldier Systems Center, Natick, MA
I Sep-19
TABLE OF CONTENTS
TABLE OF CONTENTS ................................................................................................................ I
LIST OF FIGURES ...................................................................................................................... III
LIST OF TABLES ........................................................................................................................ III
LIST OF ACRONYMS ................................................................................................................ IV
1. PROJECT SCOPE AND SCHEDULE
1.1 Scope
1.2 Schedule
1.3 Payment
2. SECURITY REQUIREMENTS
2.1 Directorate of Emergency Service and Physical Security
2.2 Contractor Personnel Conduct
2.3 Contractors that do not require CAC:
3. PROJECT BACKGROUND
3.1 Site History
3.2 Site Conditions
3.3 Geology and Hydrogeology
3.4 Existing Positional Control and Utility Tracing
4. GENERAL REQUIREMENTS
4.1 Summary
4.2 Site Clearing and Survey Obstacles
4.3 Requests for Information
4.4 Submittals
4.5 Clean Up
4.6 Government Resources
4.7 Omissions
4.8 Environmental Protection
4.9 Quality Assurance
4.10 Damage to Government or Private Property
4.11 Other Contracts
4.12 Receiving and Storing Materials and Equipment
5. HEALTH AND SAFETY REQUIREMENTS
5.1 Accident Prevention Plan
5.2 Activity Hazard Analysis
5.3 Accident Reporting
5.4 Site Safety and Health Officer
6. UTILITY GEOPHYSICS REQUIREMENTS AND OBJECTIVES
6.1 General Requirements
6.2 Goal and Objectives
II Sep-19
6.3 Site Features
6.4 Data Quality Objectives
7. ASSUMPTIONS
8. OPERATIONS, FUNCTIONS CHECKS, AND REPEAT PROFILES
8.1 Operation, Functions Checks, Quality Control
8.2 Repeat Profiles
9. DELIVERABLES
9.1 General
9.2 Work Plan
9.3 Report
10. ELECTRONIC DATA DELIVERABLES
10.1 General
10.2 AutoCAD Deliverable
10.3 Report Figures
10.4 GPR Data
10.5 Terrain Conductivity Data
10.6 Magnetometer Data
10.7 GPS Data
10.8 Geologic Boundary Elevation Pick and Grid Files
11. REFERENCES
APPENDIX A – 27 JAN 2019 SITE PHOTOS .......................................................................... A-1
APPENDIX B - AS-BUILT BUILDING DRAWINGS ................................................................. B-1
APPENDIX C –BORING LOGS AND NSSC CROSS SECTION ............................................. C-1
APPENDIX D - SURVEYED UTILITY MAPS ........................................................................... D-1
APPENDIX E - NSSC CONTRACTOR ACCESS REQUEST FORM ....................................... E-1
APPENDIX F – HEALTH AND SAFETY FORMS .................................................................... F-1
APPENDIX G – ANTITERRORISM / OPERATIONS SECURITY REQUIREMENTS .............. G-2
III Sep-19
LIST OF FIGURES
Figure 1. Access control point area of investigation, US Army Soldier Systems Center, Natick MA showing positional control and wells (Table 3 and Table 4) (imagery is 13 April 2016). See also Appendix A through D
Figure 2. Graphical depiction of accuracy and precision, showing effects of internally consistent surveys (2c), and incorporating known features (2d)
LIST OF TABLES
Table 1. NSSC ACP geophysics utility tracing project schedule
Table 2. ACP area building utility summary. Building gutters discharge to stormwater system under parking lot and driveways. Appendix B and D available upon request
Table 3. ACP area monitor wells. All data referenced to MA State Plane North American Datum of 1983 (NAD83), North American Vertical Datum (NAVD88) (feet) (see Figure 1)
Table 4. USACE positional control within and near the ACP. All data referenced to MA State Plane NAD83, NAVD88 (feet) (see Figure 1and AutoCAD Utility Map). Additional control points with data will be available
Table 5. QC Check Summary for EM-61 Mark II, EM-31, various frequency domain instruments (e.g., GEM-2), and geologic boundary interpretations (ASTM, 2011, 2008, 2007, Dawson Technical, 2010, ECC, 2006, USACE, 2011, 1995)
IV Sep-19
LIST OF ACRONYMS
ACP Access Control Point AHA Activity Hazard Analysis ARL Army Research Laboratory APP Abbreviated Accident Prevention Plan ASTM American Society for Testing and Materials Bldg Building CFR Code of Federal Regulations CMP common mid-point DoD Department of Defense DQO Data Quality Objectives EDDs Electronic Data Deliverables EM Engineer Manual FPCON Force Protection Conditions ft Feet ft bgs feet below ground surface GDA Government Designated Authority GIS Geographic Information System GPR Ground Penetrating Radar GPS Global Positioning System HQDA Headquarters, Department of the Army in inch KO Contracting Officer MA Massachusetts NAD North American Datum NAVD North American Vertical Datum NCIC‐III National Crime Information Center Interstate Identification Index
NSSC Natick Soldier Systems Center OPSEC Operation Security OSHA Occupational Safety and Health Administration PWS Performance Work Statement RTK-DGPS Real-Time Kinematic and Differential Global Positioning Systems SOP Standard Operating Procedure SSHO Site Safety and Health Officer SSHP Site Safety and Health Plan TARP Threat Awareness and Reporting Program TSDB Terrorist Screening Database USACE United States Army Corps of Engineers USEPA United States Environmental Protection Agency USGS United States Geological Survey
US Army Soldier System Center, Natick, MA
1 Sep-19
1. PROJECT SCOPE AND SCHEDULE
1.1 Scope
Execute a subsurface utility verification and tracing exploration using multiple complimentary measurement methods (e.g., Electrical Resistivity/Electrical Magnetic (ER/EM), utility line locator, video inspection/sonde where utility depths require, ground penetrating radar (GPR), as well as direct visual inspection to locate known and suspected exterior utilities, and assess the presence of exterior utilities in an approximately 5.5 acre portion of the Natick U.S. Army’s Soldier Systems Center’s (NSSC) access control point (ACP), Natick Massachusetts (MA) (Figure 1). Features observed in the data that may impact subsurface construction shall also be identified (debris, buried foundations, bedrock surface, and unknowns), and the boundaries of major lithologic or fill units.
The primary intent is to complete the subsurface utility verification and tracing exploration, identify potential buried debris and foundations, and secondarily to assess shallow geologic conditions before NSSC begins ACP final design. The USACE and the NSSC facilities team have developed an AutoCAD utility location map for the area of interest based on land survey results to date of vault, manhole, and valve cover locations. This map is the base map for this PWS and its deliverables (see Section 9 and 10). Connections between buildings and the mapped utilities must be assessed. While the building interior utilities are not a part of this exploration, all building and facility mechanical and utility rooms must be a component of the exploration effort for exterior underground utility mapping explorations as part of this PWS. In addition to the ACP area, the water and electric lines in front of Building 15 are also to be located using methods indicated above, specified herein and field located. The Contractor should assume 250’ section of these utilities should be located. This line was installed using horizontal directional drilling methods. The approximate location of this line is shown on the plan included in Appendix B. A separate utility plan shall be provided by the Contractor immediately following the field effort.
The depth of the gravity sewer sloping from the west to the east across the site (see Figure 1) should be considered when determining which utility locating methods to employ.
Horizontal precision and accuracy for all utility-tracing data points shall be less than or equal to 1 foot. Vertical accuracy (estimated depth to top of utility or feature) for all utility-tracing data points shall be 1 foot; greater where limited by the measurement method and clearly identified as such.
1.2 Schedule
The performance work statement’s (PWS) intent is to complete all work within 120 days of award (Table 1). The Contractor shall include a schedule with their work plan, with at least one alternative schedule window to allow for bad weather and site schedule constraints.
An optional site visit walk will occur on September 17, 2019 at 9:30 am EDT, and is a good opportunity to understand site logistics including topography, traffic, and security constraints on this project. Those attending the site visit must coordinate access with the USACE project manager and FAX their information to NSSC by September 13, 2019 (see Section 2.1.1).
2 Sep-19
Figure 1. Access control point area of investigation, US Army Soldier Systems Center, Natick MA showing positional control and wells (Table 3 and Table 4) (imagery is 13 April 2016). See also Appendix A through D.
Approx. Location of Sewer Line with approx. depths of 20’ to the west sloping to 4’ to the east
3 Sep-19
Approx.
Days after
Award Task
FAX Field Team Information to NSSC for badge processing (including one field team alternate). Do not email.
Submit to USACE PM Draft Work Plan and Standard Operating Procedures (SOPs), including anticipated geophysical and GPS equipment frequencies and illustration of each.
Submit to USACE PM a Google Earth Map identifying which work areas need to be cleared of stockpiled materials/shipping containers, parked cars, security barriers (where feasible), trailers, snow, aggregate, or vegetation.
Submit to USACE PM and Safety Office an Accident Prevention Plan and Activity Hazard Analysis
Receive USACE Comments on Draft Work Plan, Accident Prevention Plan, and Activity Hazard Analysis
29 Submit to USACE PM Final Work Plan and Standard Operating Procedures (SOPs)
34 Mobilize to the ACP
42 Demobilize from the ACP
Submit work related illness/injury and exposure hours to USACE PM and Safety Office. Submit start and end points for elevation profiles to USACE PM. Submit location plan of the Building 15 utilities
Submit draft report with maps, profiles, and AutoCAD EDDs for USACE and NSSC review
80 Receive USACE and NSSC comments
94 Submit revised AutoCAD EDD for USACE and NSSC review
108 Receive USACE and NSSC comments
115 Submit final report with EDDs
1.3 Payment
After final inspection and acceptance by the Government, the Contractor must submit an invoice via email and hard copy to the Project Manager Robert Leitch (978-318-8033). The invoice shall include the invoice date, contract number, dates of service, description of work, and total amount due per line item. Transmit all invoices to:
Robert.A.Leitch@usace.army.mil
Robert A. Leitch
CENAE-PPM
696 Virginia Road Concord MA 01742
Table 1. NSSC ACP geophysics utility tracing project schedule.
Utility Geophysics Mapping
4 Sep-19
2. SECURITY REQUIREMENTS
2.1 Directorate of Emergency Service and Physical Security
2.1.1 NSSC Contractor Access
Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204‐9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in Contractor security matters or processes.
The Contractor shall FAX to Protection Division, Directorate of Operations employee’s names and information on NSSC Contractor Access Request Form (Appendix E) for background investigation for all personnel that will be entering Army-controlled installations or facilities, a minimum of seven (7) business days prior to arrival. An accompanying letter with the following information must accompany the FAX:
Project name
Contract number
Full name, address, and social security number of all employees
Contractor's full address and telephone number
USACE PM names and phone numbers
Pipe locator, geophysics, and GPS base station broadcast frequencies or frequency ranges and one picture of each equipment type
FAX number is (508) 233-6293. After faxing information to NSSC Protection Division, an e-mail shall also be sent to Project Manager Robert Leitch at Robert.A.Leitch@usace.army.mil indicating intent to attend the site visit (Contractor Access Request Form shall not be e-mailed to PM).
Badges shall be worn at all times while working at NSSC. All Contractor personnel that have Permanent Resident Cards (USCIS Form I-551) (green cards) shall possess them when entering the installation. Proof of the Form l-551 being up to date (valid with expiration date visible) must be in possession when entering the Installation. All Contractor personnel shall immediately report instances of lost or stolen badges to the Project Manager and Protection Division, Directorate of Operations. Badges shall be worn and be visible at all times while on the Installation. The Contractor shall be responsible for returning all Identification Badges to the Project Manager after completion of the project. Final payment will not be made until all badges are returned and have been accounted for.
2.1.2 Force Protection Conditions
During Force Protection Conditions (FPCONs) CHARLIE and DELTA, contracted services may be limited or discontinued. Contracted services will resume when the FPCON level is reduced to level BRAVO or lower. The Contractor is responsible for adjusting the work sequence (field to office) and/or revising the field effort schedule in anticipation of the reduced FPCON level.
No additional compensation will be provided for this inconvenience.
mailto:Robert.A.Leitch@usace.army.mil
5 Sep-19
2.1.3 Job Site Security
The Contractor shall be responsible for maintaining a secure job site and ensure NSSC installation perimeter confined to the area of the scope of this contract is secure at all times during work hours and leaving secure upon departure from the Installation for security after work hours. Areas of staging, material storage, and equipment shall be reviewed with the USACE PM for approval at pre-work meeting.
2.1.4 Facility Security
At the close of each work period (night work, weekend day), government facilities, equipment, and materials shall be secured.
2.1.5 Materials, Supplies, and Equipment
The Contractor shall be responsible for all arrangements for the receipt of materials and supplies at the job site. Government personnel are not permitted to receive or sign for items delivered to the site.
2.1.6 Damages
Work shall proceed in a manner minimizing disturbance or risk of damage to surrounding structures, interior finishes, room furnishings, personal belongings, equipment, or infrastructure.
The Contractor shall be responsible for protecting and avoiding damage to the project site and surrounding areas, shall carry appropriate comprehensive/liability insurance coverage to account for possible damage, and lost items. Any damage to the Project work area, exterior, interior or surroundings resulting from the Contractor’s actions or equipment shall be the responsibility of the Contractor to repair or replace as determined by the USACE PM. If any other existing building, road conditions, sprinkler system, lawn, landscape etc. are damaged, it shall be the responsibility of the Contractor to restore by matching the existing conditions in materials, dimensions, appearance and integrity as accurately as possible at no cost to the Government. This work shall take place as soon as possible. Any damage to lawn areas shall be replaced with sod and maintained by Contractor until lawn/sod has been reestablished. A satisfactory match will be determined by the USACE PM. If repairs cannot be made by the Contractor, the cost of the repairs will be determined by the Contracting Officer or USACE PM and appropriate compensation shall be made by the Contractor, payable to the U.S. Treasury.
2.1.7 Cameras
The Contractor shall coordinate permission to use cameras with the USACE PM.
2.2 Contractor Personnel Conduct
2.2.1 Conduct
The Contractor’s conduct shall not reflect discredit upon the Government. Contractor shall ensure that personnel present a professional appearance. Contractor’s employees shall observe and comply with all local policies and procedures concerning fire, safety, environmental protection, sanitation, security, and possession of firearms or other lethal or illegal weapons or substance. Contractor is responsible for ensuring that any Contractor employees providing
6 Sep-19 services under this contract conduct themselves and perform services in a professional, safe, and responsible manner. Contractor shall remove from the job site any employee for reasons of misconduct or security. Contractor shall ensure no Contractor employees conduct political related activities or events on NSSC facilities.
2.2.2 Smoking
Smoking is prohibited within and outside of all NSSC facilities except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
2.3 Contractors that do not require CAC:
The Contractor shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC‐III) and Terrorist Screening Database (TSDB) (Army Directive 2014‐05/AR 190‐13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The applicable installation/facility Antiterrorism/Operations Security Requirements including AT level 1 training (general) as well as iWATCH training is described in more detail in Appendix G – Antiterrorism/Operations Security Requirements. The Contractor shall comply with all required training and coordination requirements described in Appendix G and its attachments.
3. PROJECT BACKGROUND
3.1 Site History
In the mid-1950s, the Army purchased the property that essentially encompasses this entire peninsula (ICF, 2008). Prior to the 1950s, area north of Kansas Street (Figure 1) was a gravel pit operated by the Town of Natick. During that time, there were various operations consistent with sand and gravel, including cutting of vegetation, filling and potentially the creation of construction debris. In 1954, the Army purchased the land and began to develop it. Private homes within the ACP area were removed, and the foundations are reported to have been left in place. The Army built the ACP with commercial and military entrances, which have changed configurations over time.
3.2 Site Conditions
The ACP contains a mix of modern and Cold War-era office buildings and infrastructure, some of which pre-dates 1950. The ACP is being replaced by a modern system and facilities designed by USACE (Figure 1, Table 2). A chain link fence separates the installation from the commercial road north of the ACP. The investigation area is bounded to the east by the Lake Cochituate shoreline and to the north by General Greene Avenue. The ACP area is NSSC’s primary vehicle access point for several hundred employees and supporting contractors each day.
7 Sep-19
Building Number Primary Function
Known and Potential Utilities
Notes
DeFranzo Gate Commercial Truck Entrance
E All known utilities are above grade.
Knowlton Gate ID Check C, E As Built plans available.
1 Administration C, E, S, W, G, F As Built plans available.
DeFranzo Gate Security Office
C, E, S, W No information on historic utilities.
Knowlton Gate Security Office
C, E, S, W As Built plans available.
92 .Administration C, E, W, S No information on historic utilities.
96 Utility Control C, E, W No information on historic utilities.
97 Utility Control C, E, W No information on historic utilities.
C-Communication (LAN, Fire Detection, Phone, Fiber +/- metal tracing line) E-Electrical F-Fire Suppression G-Gas, Natural
R-Refrigerant S-Sanitary T-Treated and Raw Groundwater W-Water WW-Wastewater, Oil Water Separators
Most of the utilities in the study area are thought to be underneath existing roadways, and to a lesser degree in the grass and tree areas between the roads. Trees between Bldg 39 and 92 have laterally extensive root systems, potentially reducing GPR data quality (Figure 1 and Appendix A). The land surface between Lot C and the Knowlton Gate slopes to the south, with a change in elevation of approximately 30 feet. One or more areas may be more challenging to establishing a grid due to narrow workspace or vehicle traffic hazards (e.g., land between the security fence and General Greene Avenue).
Potential utility materials include, but are not limited to, cast iron, plain or corrugated steel, bituminized fiber, plain/corrugated/wrought iron, asbestos-cement, concrete, vitrified clay, polyvinyl chloride plastic (PVC), acrylonitrile-butadiene-styrene (ABS), and reinforced plastic mortar (USACE, 2006). Some utilities, such as fiber-optic communication lines, may not have metal tracing tape. Buried foundations suspected to be present near General Greene Avenue may contain varying amounts of fill debris including, but not limited to, boulders, metal, and/or masonry debris.
The utility lines to the east of Building 15 (approx. depth is indicated in Appendix B) are to be located both horizontally and vertically to the precision of other utilities as described herein.
3.3 Geology and Hydrogeology
Glacial outwash sand and gravel deposits thicken southward from 5 to over 30 ft, and are underlain by fine to medium sand (ICF, 2008). Fine sands are common under the site, with discontinuous layers of peat, cobbles, coarse sand, and clay. Fill material is likely present over
Table 2. ACP area building utility summary. Building gutters discharge to stormwater system under parking lot and driveways. Appendix B and D available upon request by successful Contractor.
8 Sep-19 former foundations and near current buildings. Road-base fill underlies parking areas and roadways. Regional depth to bedrock is 155-199 feet below grade (Appendix C).
Groundwater is expected to be 13-20 feet below grade where not affected by leaking water utilities or near Lake Cochituate (USGS, 2017, MacTec, 2011). Two monitoring wells with locations and boring logs are on site (Figure 1, Table 3, and Appendix C). Additional wells and boreholes are present (see map and logs in Appendix C), and will by surveyed by USACE for consistency, and positional data provided to the contractor (see Section 4.6 and Appendix C).
Name Easting (feet) Northing (feet) Ground Elevation (feet)
MW-4 694024.02 2930929.91 142.3000031
MW-74B-HP2 693459.51 2930965.8 171.1000061
3.4 Existing Positional Control and Utility Tracing
USACE established a positional control the MA NAD83 horizontal and NAVD88 vertical datum (Figure 1, Table 3). The survey team also located some visible manways, vaults, and exterior pipes, and were used to update the Northern Industrial Campus utility maps. Current as-built and record drawings show where utilities enter or exit a building, but their location below grade ranges from confident to unknown. These maps (Appendix B, D) are FOR OFFICIAL USE ONLY (FOUO), and available upon request (see Section 7). The FOUO AutoCAD-compatible file used to as the basemap for this project containing all of the utility information to date shall be transmitted at contract award.
Name Description Easting
(feet) Northing
(feet) Ground Elevation
(feet)
1095K CONCRETE BOUND W/ MONEL RIVET 693326.45 2930895.95 169.06
CAL2 PK Nail 692728.53 2931000 166.18
4. GENERAL REQUIREMENTS
4.1 Summary
Furnish all materials, equipment, and labor to:
Locate known and suspected utilities using a minimum of two (three as soil depth requires) complimentary methods, including visual inspection at the buildings
Identify locations and elevations of utilities in manways & vaults, line-locator results, pavement patches, building corners within and abutting the survey area.
Identify potential utility locations
Identify features observed in the data that may impact subsurface construction (foundations, debris, bedrock surface, and unknowns)
Table 3. ACP area monitor wells. All data referenced to MA State Plane North American Datum of 1983 (NAD83), North American Vertical Datum (NAVD88) (feet) (see Figure 1).
Table 4. USACE positional control within and near the ACP. All data referenced to MA State Plane NAD83, NAVD88 (feet) (see Figure 1and AutoCAD Utility Map). Additional control points with data will be available.
9 Sep-19
Assess significant changes in geology/subsurface conditions within 15 feet of ground surface
Submit draft and final report
Submit draft and final AutoCAD map deliverables
Submit draft and final pick files and grid maps of interpreted subsurface stratigraphy within 15 feet of ground surface.
Submit geophysics, positional, and geologic electronic data deliverables
Where a geophysical method does not achieve the desired penetration depth (e.g., thick root zones around mature trees), an alternate method shall be employed (e.g., cart-mounted magnetometer). Areas where data quality suffers due to site conditions/logistical constraints and features that cannot be overcome by reasonable field coordination will be clearly identified as soon as possible while in the field and will be clearly identified on all deliverables.
4.2 Site Clearing and Survey Obstacles
The majority of the site is paved, mowed grass, or equipment and material staging areas (Figure 1), so no clearing and grubbing is required for instrument access.
Some temporary vehicle barriers may be moved in advance of the utility tracing, but must be identified during the Pre-Work Meeting. Areas where parked cars or trucks will interfere with utility tracing that cannot be mitigated with weekend or of-hour/evening work must also be identified during the Pre-Work Meeting to coordinate alternatives for NSSC personnel. If off-hour/evening work is anticipated then this must be clearly identified during the Pre-Work Meeting as well as Work Plans and Safety Documents.
4.3 Requests for Information
Direct all requests, to include copies of FOR OFFICIAL USE ONLY information and other than regular workday access, to the Project Manager, Robert Leitch, at 978-318-8033 or Robert.A.Leitch@usace.army.mil.
4.4 Submittals
See Section 5, 9 and 10.
4.5 Clean Up
The Contractor shall practice good housekeeping to maintain a safe job site in accordance with the approved site safety and health plan, corporate safety policies, and USACE requirements (USACE, 2014). The Contractor shall keep the work area, including any storage areas, free from the accumulation of waste materials. Upon completing work, the Contractor shall remove any tools, equipment, and materials that are not the property of the government. Upon completion of work, the Contractor shall clean up the job site to the satisfaction of the Government. The work site shall be left in the same condition as prior to the start of work to the satisfaction of the USACE project manager.
4.6 Government Resources
10 Sep-19
The Contractor is responsible for providing all materials to complete the project unless otherwise specified in this PWS and contract. USACE is dedicated to working with the Contractor to achieve project success. This includes providing supporting data, coordinating site activities and permissions, limited field oversight, and in depth submittal reviews. The Government offers the following additional resources/suggestions to optimize the contractor’s efforts and schedule, and improve data quality.
Access. Weekend, after hours, and workday access to government buildings is available and may be required (to be discussed during the pre-work meeting), but must be coordinated with the USACE PM at least 5 workdays in advance of fieldwork.
AutoCAD Utilities Plan file. Serves as the basemap for all work done under this PWS including electronic data deliverables, and shall be provided at contract award via ARL FTP site by the USACE PM.
Bathroom Facilities. Available at Building 20.
Borehole Data. Drilling logs are available upon request.
Building As-Built and Utility Maps. See Section 7.
Fillable Health and Safety Forms. Fillable versions of the Appendix F forms are provided to the successful bidder.
FOUO Data for Preparing Quotes. Appendix B and D pdfs will be provided via ARL FTP site upon Contractor request to the USACE PM.
Site Plan. A detailed, spring 2019 site plan with topography and additional control points will be provided to the successful Contractor in PDF and AutoCAD formats.
Topographic Data. USACE shall supply elevation data in the project vertical datum for all profiles collected by the Contractor. Contractor shall request the data through the USACE Project Manager using a GIS shape file or in tabular format (profile name, start and stop coordinates in the project horizontal datum).
Water Levels. Where water levels are needed, USACE will collect and provide them to the Contractor.
4.7 Omissions
This contract and PWS may not cover all specified activities, steps, and procedures required to supply the contract product. In case of omission, the normal industry, state, or federal standards, software requirements, practices, specifications, and/or guides shall prevail. In no instance shall an omission be reason to produce less than an acceptable product.
4.8 Environmental Protection
The Contractor shall prevent pollution or damage to the environment resulting from activities during this contract. The Contractor will receive no additional payment for environmental protection work. Prevention of pollution and environmental damage is a Contractor obligation under current State and federal Laws and regulations. Assurance of compliance with this section by subcontractors shall be the responsibility of the Contractor.
4.9 Quality Assurance
The Contractor is responsible for the quality control of the contract work as discussed in the following sections. The Government has the right to inspect and test all items called for by the contract, to the extent practicable at all times and at all places during the term of the contract.
11 Sep-19
4.10 Damage to Government or Private Property
The Contractor shall be responsible for restoring any Government facilities or structures damaged as a result of the firm’s operation. The Contractor shall also be responsible for any damage to private property or injury to any person resulting from the firm’s operations. The Contractor shall notify the Technical Point of Contact immediately of damage to Government and private property and injury to any person (including employees) resulting from the firms’ operation.
4.11 Other Contracts
The Government may undertake or award other contracts for additional work not related to this contract, and the Contractor shall fully cooperate with other Contractors and Government employees. The Contractor shall not knowingly commit or permit any act, which will interfere with the performance of work by another Contractor, or by Government employees.
4.12 Receiving and Storing Materials and Equipment
The Contractor is responsible for protecting any stored materials and equipment used for this PWS. The Contractor is responsible for receiving and unloading of delivered goods.
Government employees will not receive material or supplies for the Contractor and will not be responsible for damage to Contractor equipment or material.
5. HEALTH AND SAFETY REQUIREMENTS
5.1 Accident Prevention Plan
The Contractor shall prepare an Accident Prevention Plan (APP) specific to the activities being performed. It shall include an Activity Hazard Analysis (AHA) as described in Section 5.2 below (see appendix F). All work shall be conducted in accordance with the APP, the U.S. Army Corps of Engineers Safety and Health requirements Manual (EM 385-1-1, most recent edition at http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1- 1.pdf), and all applicable federal, state, and local, and installation safety and health requirements.
The APP shall detail how safety and health will be managed during the project. The APP shall address the requirements of applicable Federal, State and local safety and health laws, rules, and regulations. The Contractor shall comply with Federal Acquisition Regulation Clause No.
52.236-13 for Accident Prevention, which is added by reference. Special attention shall focus on the requirements of EM 385-1-1, specifically Section 01.A.12 through 01.A.17, Figure 1-2 AHA, and Appendix A, (Minimum Basic Outline for Accident Prevention Plan). A qualified person shall develop the APP. The contractor shall be responsible for documenting the qualified person’s credentials. Work shall not proceed until the Government Designated Authority (GDA), Ms. Sheila Harvey (978-318-8504), has reviewed the APP. Transmit all draft safety documents to Ms. Harvey at Sheila.Harvey@usace.army.mil, and CC Robert Leitch
(USACE PM).
As part of the APP the contractor must prepare a Site Safety and Health Plan (SSHP) that that covers the 14 elements identified in EM 385-1-1, Section 33.B.02. The SSHP shall be attached http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf mailto:Sheila.Harvey@usace.army.mil
12 Sep-19 to the APP as an appendix. SSHP elements adequately covered elsewhere in the APP need not be duplicated again in the SSHP.
The APP shall interface with the Contractor's overall safety and health program. Any portions of the Contractor's overall safety and health program referenced in the APP shall be included in the applicable APP element and made site-specific. The Government considers the Prime Contractor to be the "controlling authority" for safety and health of the subcontractors.
Contractors are responsible for informing their subcontractors of the safety provisions under the terms of the contract, the penalties for noncompliance, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out.
The Contractor shall conduct a safety meeting at the project site on the first day of work, whenever a new activity or phase of work begins, or at least weekly during the progress of work.
All safety meetings shall be documented (use form in Appendix F or similar). Records of the safety briefings shall be submitted to the GDA weekly, and CC Robert Leitch (USACE PM).
5.2 Activity Hazard Analysis
An AHA shall be submitted for each major phase of work (see Appendix F). A major phase of work is defined as an operation involving a type of work presenting hazards not experienced in previous operations or where a new subcontractor or work crew is to perform the work (e.g., mob/demob, utility tracing method 1, utility tracing method 2, work between the security fence and General Greene Avenue). The analysis shall define all activities to be performed, identify the sequence of work, the specific hazards anticipated, and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level. Work shall not proceed on a phase of work until the AHA has been accepted by the GDA. A preparatory meeting shall be conducted by the contractor to discuss the AHA contents with all engaged in the activity.
The preparatory meeting shall be conducted by the prime contractor and shall include all subcontractors and Government on-site representatives. The AHA shall be continuously reviewed and revised to address changing site conditions or operations as appropriate.
5.3 Accident Reporting
All accidents and near misses shall be investigated by the Contractor. All work-related recordable injuries, illnesses and property damage accidents (excluding on-the-road vehicle accidents), in which the property damage exceeds $5,000.00, shall be verbally reported to the GDA and USACE PM within 4 hours of the incident. Serious accidents as described in EM 385- 1-1 Section 01.D shall be immediately reported to the GDA and USACE PM. ENG Form 3394 shall be completed and submitted to the GDA within five working days of the incident, and CC Robert Leitch (USACE PM) (see Appendix F).
The Contractor shall complete the attached “USACE Contractor Monthly Summary Record of Injuries/Illness and Work Hour Exposure” (for prime and its subcontractors) and forward the completed form to the GDA no later than close of business on the 5th calendar day of the following month. The method of transmission by the prime contractor to the GDA shall be electronically, and CC Robert Leitch (USACE PM).
5.4 Site Safety and Health Officer
13 Sep-19
The Contractor shall designate one individual as the Site Safety and Health Officer (SSHO) who shall have the qualifications detailed below. Documentation of SSHO qualifications shall be submitted for approval prior to initiating work. The SSHO may have other duties in addition to site safety and health, but may not be the Contractor’s Site Superintendent.
a. Minimum [two – five] years of experience in implementing safety and health programs at similar projects;
b. Working knowledge of construction safety procedures as well as Federal and state occupational safety and health regulations;
c. 10-hour OSHA Construction Safety certification or as an equivalent, 10 hours of formal construction safety and health training covering the subjects of the OSHA 10-hour course.
6. UTILITY GEOPHYSICS REQUIREMENTS AND OBJECTIVES
6.1 General Requirements
Design and execute a geophysics and underground utility mapping based utility exploration using a minimum of three complimentary methods and a workflow accounting for the given and existing site conditions (see Sterling and others, 2009). All geophysics and utility mapping data shall be geo-tagged as it is collected. Follow-up QC positional data collection is encouraged, it shall not be used as a substitute for geo-tagging the geophysics data.
The Contractor shall use the latest versions of all data acquisition, processing, and presentation software used to execute this PWS to maximize software interoperability. This includes, but is not limited to, AutoCAD, report preparation software (Adobe Professional, Microsoft Office), and supporting data collection, processing, and interpretation software.
6.2 Goal and Objectives
The intent of this Performance Work Statement is to verify the existing subsurface utility information as well as fill in underground utility data gaps in advance of upcoming construction in an approximately 5.5 acre portion of the Soldier System Center’s ACP. The objectives are to:
Locate, estimate the depth to utility top and diameter, of known and suspected utilities.
Identify potential buried foundations, debris, bedrock, boulders, or other unidentified features potentially affecting new utility or foundation construction, and estimate extent and depth to top of feature.
Interpret the stratigraphy up to 15 feet below grade (correlated to available boring data).
6.3 Site Features
Site features shall be used to create known points supporting geophysics data interpretation and underground utility mapping. The following minimum features shall be measured by employing industry accepted methods for tying in the positional and elevation data to the established benchmark(s). The team assigned to determining the positional data shall have past experience performing this type of work. The resulting data shall have a maximum horizontal error equal to or less than half the precision standard required for the geophysics data:
Invert elevation and location. Estimate the utility diameter and direction where accessible.
14 Sep-19
Building corner location and elevation within and bounding the study area
Pavement patches or other linear cracking which may correspond with utilities within the study area
Monitor wells and soil borings where found
6.4 Data Quality Objectives
The Contractor shall follow and meet the data quality objectives discussed below (United States Environmental Protection Agency, 2006). In some cases, the data quality objective will need modification based on field results. In many cases, measurement device specifications and use define these objectives. Where data quality objectives are modified based on field results, the data and evaluation leading to the change shall be fully documented in the report. The Contractor is encouraged to generate and meet additional data quality objectives where they support the project goals and objectives.
Quantifying the exploration’s horizontal and depth precision and accuracy are two primary data quality objectives governing survey design, execution, data processing & interpretation, and reporting. Consistently following manufacturer’s guidelines SOPs yields consistent or more accurate data and interpretations (Figure 2c). Incorporating known positional features (monitor wells, already mapped utilities) and their response increases survey precision (Figure 2d).
A. State the Problem/Identify the Decision
What is the Data’s Horizontal Precision and Accuracy?
What is the Data’s Depth Precision and Accuracy?
Data Processing Anomaly Resolution. What process or workflow will be used to verify an anomaly is a utility instead of buried building debris?
Figure 2. Graphical depiction of accuracy and precision, showing effects of internally consistent data (2c), and incorporating known features (2d).
15 Sep-19
Geophysics Profile Intersection Mismatch. Is it the result of a modeling assumption, positional data error, or other factor?
B. Identify Decision Inputs
Horizontal Precision and Accuracy. Measured accuracy and drift of the GPS data collection system, satellite availability, system capability.
Depth Precision and Accuracy. Measurement method, GPR velocity profile at boring with a detailed geologic log, water table depth at the time of survey.
Data Processing Anomaly Resolution. Location of utilities entering a building, nearby manways.
Geophysics Profile Intersection Mismatch. What is the vertical difference between the two interpreted surfaces or range of velocities? What were the model input values for each profile? Other factors driving mismatch (e.g., steep topography, software limitations)?
C. Identify the Study Boundaries.
Horizontal Precision and Accuracy. Positional control extent and area of interest.
Depth Precision and Accuracy. No deeper than the water table.
Data Processing Anomaly Resolution. Location of known utilities, pavement patches, cultural features.
Geophysics Profile Intersection Mismatch. Lateral and lowermost data model boundaries.
Internal boundaries may occur within overburden units (where resolvable).
D. Develop Decision Rule/Limits of Decision Errors
Horizontal Precision and Accuracy. 1.0 feet for utility tracing.
Depth Precision and Accuracy. 1.0 feet and the measurement method limits.
Data Processing Anomaly Resolution. Anomalies potentially representing utilities must be consistent across two location methods, match pavement patches or manways, and/or match exterior utility (e.g., gas meter).
Geophysics Profile Intersection Mismatch. Where topographic changes make models diverge at profile intersections, differences greater than 1 ft in the upper 10 ft necessitate re-running the models to improve internal consistency across all of the data sets.
E. Optimize the Design
Horizontal Precision and Accuracy. Alter operating procedures to accommodate site conditions.
Depth Precision and Accuracy. Use an alternate monitor well or soil boring location to obtain velocity profile data, or alternate measurement method.
Data Processing Anomaly Resolution. Evaluate supplied utility plans, building as-built drawings.
Geophysics Profile Intersection Mismatch. Evaluate site conditions and artifacts introduced by the modeling process.
7. ASSUMPTIONS
AutoCAD Utility Deliverable. Contractor adds interpreted utilities locations to the supplied AutoCAD Site Plan File and submits with draft and final report.
Building Access for Utility/Cable Locator Connections. Available, but must be coordinated in advance through USACE.
16 Sep-19
Geologic Boundary Picks. Minimum number of points includes profile intersections, and sufficient number of data points between profile intersections to characterize the change in boundary elevation.
Geophysics Data. All are simultaneously collected with GPS data.
GPS Satellite Coverage. Varies from excellent to problematic. Topography may reduce RTK base station reception.
Grid Spacing. Five foot centers unless site conditions dictate a smaller spacing.
Interior Data. While building interior utility mapping is not a component of this PWS, all building utility connections are a mandatory mapping point and connection to the exterior mapping effort needed for this utility verification and trace PWS.
Positional Data. Contractor establishes GPS base station where feasible, and uses differential GPS where a base station is not feasible. All data is collected and processed in accordance with EM 1110-1-1003 (USACE, 2011) using USACE surveyed benchmarks, control points, and features.
Power. None is available on site.
Site Visit. If attending, the Contractor’s field team leader shall be present.
Project Horizontal and Vertical Datums. MA State Plane NAD83 and NAVD88, respectively, in feet.
Residual Hazardous Waste Conditions. None known at ground surface.
Snow. Parking lots, roads, and sidewalks will be plowed. Snow pile remnants may be present.
Subcontractors. USACE encourages use of specialty subcontractors where it optimizes the technical products and minimizes price and schedule problems (e.g., video inspection/pipe locator services).
Unexploded Ordnance. None found or anticipated.
Work Hours. Regular work hours are Monday through Friday, 0700-1800. Holiday and weekend work is encouraged to minimize traffic hazards, lost time, and holiday areas. Other than weekday, work must be coordinated at least two weeks in advance of mobilization through the USACE project manager.
8. OPERATIONS, FUNCTIONS CHECKS, AND REPEAT PROFILES
8.1 Operation, Functions Checks, Quality Control
This PWS section is not a substitute for the geophysics team’s internal and equipment-unique checks and field standardization, and vendor specifications. All equipment shall undergo quality control checks, with the results summarized and included with the final report, along with a discussion on how the results affect data quality, measurement uncertainty, and limitations.
8.1.1 Pipe and Cable/Sonde and/or video/sonde Locators
Verify the unit’s signal does not conflict with site operations. Using existing located utilities, verify the signal at the selected frequency passes into the conductor, successfully propagates along the conductor, and is detected by the receiving antenna. Signal frequencies shall be included in the Work Plan and will be approved by the Installation before mobilization.
17 Sep-19
8.1.2 GPR
GPR data will be collected consistent with ASTM standard 6432 (2005) and the Contractor’s SOP using a common offset mode. Assuming suitable reflectors are present in the common-offset data, GPR energy propagation velocities will be determined using the common mid-point (CMP) method. The CMP data shall be processed to determine GPR energy propagation velocities using X2-T2 or semblance methods. GPR energy propagation velocities shall be used to estimate the depth of reflectors present on the GPR profiles and for other processing and QA/QC purposes. Spatial and waveform sampling frequencies shall be selected to ensure proper waveform recording and subsurface structural imaging.
System operating performance will be tested by conducting airwave walk-away tests at the beginning and end of each field day. This test will be used to confirm system operation stability and to ensure the sampling frequency used to record the GPR data is known and remains stable during data acquisition.
The following procedures shall be used at a minimum, augmented by the geophysics Contractor’s internal SOPs (after Kirsch, 2006, Milsom, 2003, USACE, 1995):
Travel Time and Ground Truth Data. Measure at least one transect through 1-2 existing borings or piezometers for depth and travel time quality control. Where existing piezometers or wells are present, USACE will collect water levels just before or after completing the data collection as required.
Noise and Filtering-1. Minimize filtering during data acquisition, and eliminate noise from portable electronics (radios, smart phones).
Time Zero. Calculate and apply time zero correction
Noise and Filtering-2. Filter receiver electronic noise and system ringing before applying bandpass filters
Gain. Apply amplitude equalization using gain controls best matching site conditions (do not assume automatic gain control will suffice)
Corrections. Apply static and dynamic corrections as warranted by the data and site conditions
Travel Time to Depth. Convert two way travel time to depth using site data such as water table elevations and results from nearby borings or piezometers provided to the Contractor by USACE.
8.1.3 Time and Frequency Domain Instruments
Execute using ASTM guides (ASTM 2011, 2008, 2007), and Table 5, adjusted for site conditions and utility/utility conduit depths and materials.
8.1.4 Magnetometer
Verify the unit can detect a known buried culvert or large diameter utility and a surface object (trailer hitch ball, well cover), and its geo-tagged location is within project requirements).
Assess proximity limits to metal structures and impacts from solar flares and diurnal magnetic field fluctuations.
18 Sep-19
8.1.5 GPS
See Table 5.
8.2 Repeat Profiles
A minimum 50-foot long path shall be established at the site to daily test all positional and geophysical equipment, and demonstrate repeatability (see Table 5).