Amendment 0001

View the file

Other files

File Type Posted
BidSummary.pdf PDF
Amendment_0001_attachment.pdf PDF
Solicitation_W912WJ-16-B-0006.pdf PDF
Specifications.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

This amendment is being issued to answ er a request for information, add a specification to the solicitation, and include the pre-bid site visit sign in sheet. The bid opening date is changed to Thursday, March 17 at 2:00PM.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 11-Mar-2016

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912WJ-16-B-0006

X 9B. DATED (SEE ITEM 11)

10-Feb-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

11-Mar-2016

CODE

U S ARMY ENGR DISTRICT, NEW ENGLAND

696 VIRGINIA RD

CONCORD MA 01742-2751

W912WJ 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912WJ-16-B-0006

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT SPEC

1.1 CHANGES TO SPECIFICATIONS

1.1.1 Narrative Changes

1. Section 01 11 00 SUMMARY OF WORK, Subpart 1.1 WORK COVERED BY CONTRACT DOCUMENTS, fifth paragraph; add the following to the end of this paragraph:

"In addition, the Contractor shall furnish and install new high density urethane weatherstripping for the exterior doors that lead into the Intake Tower."

2. Section 01 33 00 SUBMITTAL PROCEDURES, Submittal Register; delete the Submittal Register attached at the end of this section and insert a new Submittal Register, copy attached to this amendment, in its place.

1.1.2 New Specification Section

Specification Section 08 71 10 DOOR WEATHERSTRIPPING is added to the specification document. A copy of the new section accompanies this amendment.

END OF CHANGES

RFI

Question: Does the yellow paint on the junction cover need to be removed as part of this contract?

Response: Yes, as per Spec Section 01 11 00 SUMMARY OF WORK, paragraph 1.1, fourth paragraph, "All steel members of the bridge shall be prepared and painted including girders, diaphragms, entire bearing assemblies, expansion joint cover plate, utility conduits and related items.”

SECTION 08 71 10

SECTION 08 71 10

DOOR WEATHERSTRIPPING

PART 1 GENERAL

1.1 SUMMARY

This section covers the furnishment and installation of new high density urethane weatherstripping for the exterior doors that lead into the Intake Tower.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D3574 (2011) Standard Test Methods for Flexible

Cellular Materials — Slab, Bonded, and Molded Urethane Foams

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Weatherstripping; G, RO

Submit manufacturer's descriptive literature for weatherstripping.

1.4 DELIVERY

Deliver weatherstripping in original containers.

PART 2 PRODUCTS

2.1 WEATHERSTRIPPING

Weatherstripping shall be a high density urethane open cell foam that exhibits closed cell characteristics when compressed. It shall have a very low compression set, good shock absorption, and low out-gassing. Attachment to the door frame shall be by permanent acrylic adhesive. Weatherstripping shall be 1/2-inch wide by 1/4-inch thick. Color shall be black. Product characteristics shall be as follows:

Adhesive: Permanent acrylic based pressure sensitive adhesive. Shall include s a film carrier for non-stretch characteristics.

Test Method: In accordance with ASTM D3574.

Density: 15 lb/ft3.

Compression Deflection: 4 to 8 psi.

Compression Set: (50%) 10 max.

Service Temperature: Acrylic based, -20°F to 190°F.

Flammability: FMVSS 302; UL94 HBF = 3/16.

Application Temperature Range: 65 - 100 °F.

2.1.1 Acceptable Product

An aceptable product for weatherstripping shall be "Weather Stripping and Gasket Tape, Item Code 472079", as available from Essentra Components, 7400 West Industrial Drive, Forest Park, IL 60130; Telephone 800-847-0486;

(essentracomponents.com), or approved equal.

PART 3 EXECUTION

3.1 DEMOLITION

Existing weatherstripping and related items of the door leading into the intake tower shall be removed in their entirety and the underlying surfaces shall be prepared and painted prior to the installation of new weatherstripping. After painting is completed, installation of new weatherstripping shall be performed.

3.2 INSTALLATION

Install weatherstripping in accordance with manufacturers' printed installation instructions. Provide full contact, weathertight seals that allow operation of doors without binding the weatherstripping and that are complete around all door edges including sill.

-- End of Section --

SITE VISIT SIGN IN SHEET

Chad Lamper The Aulson Co.

Leroy Page UWS Construction Services

Andrew Elliott UWS Construction Services

Donnie Dursin Atlas Painting

(End of Summary of Changes)