Amendment_0001_attachment.pdf

PDF 35 KB Posted

Attached to
East Brimfield Delead and Repaint Service Bridge
Solicitation number
W912WJ16B0006
Issued by

About this file

Amendment attachment

View the file

Other files

File Type Posted
BidSummary.pdf PDF
Amendment_0001.pdf PDF
Solicitation_W912WJ-16-B-0006.pdf PDF
Specifications.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Paint Service Bridge, East Brimfield Dam, Sturbridge, MA Amendment 0001

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

AMENDMENT 0001 OF SOLICITATION

1.1 CHANGES TO SPECIFICATIONS

1.1.1 Narrative Changes

1.1.2 New Specification Section

-- End of Section Table of Contents --

DOCUMENT 00 00 01 Page 1

AMENDMENT 0001 OF SOLICITATION

1.1 CHANGES TO SPECIFICATIONS

1.1.1 Narrative Changes

1. Section 01 11 00 SUMMARY OF WORK, Subpart 1.1 WORK COVERED BY CONTRACT DOCUMENTS, fifth paragraph; add the following to the end of this paragraph:

"In addition, the Contractor shall furnish and install new high density urethane weatherstripping for the exterior doors that lead into the Intake Tower."

2. Section 01 33 00 SUBMITTAL PROCEDURES, Submittal Register; delete the Submittal Register attached at the end of this section and insert a new Submittal Register, copy attached to this amendment, in its place.

1.1.2 New Specification Section

Specification Section 08 71 10 DOOR WEATHERSTRIPPING is added to the specification document. A copy of the new section accompanies this amendment.

END OF AMENDMENT 0001

DOCUMENT 00 00 01 Page 2

SECTION TABLE OF CONTENTS

DIVISION 08 - OPENINGS

SECTION 08 71 10

DOOR WEATHERSTRIPPING

PART 1 GENERAL

1.1 SUMMARY

1.2 REFERENCES

1.3 SUBMITTALS

1.4 DELIVERY

PART 2 PRODUCTS

2.1 WEATHERSTRIPPING

2.1.1 Acceptable Product

PART 3 EXECUTION

3.1 DEMOLITION

3.2 INSTALLATION

-- End of Section Table of Contents --

SECTION 08 71 10 Page 1

SECTION 08 71 10

DOOR WEATHERSTRIPPING

PART 1 GENERAL

1.1 SUMMARY

This section covers the furnishment and installation of new high density urethane weatherstripping for the exterior doors that lead into the Intake Tower.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D3574 (2011) Standard Test Methods for Flexible Cellular Materials — Slab, Bonded, and Molded Urethane Foams

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Weatherstripping; G, RO

Submit manufacturer's descriptive literature for weatherstripping.

1.4 DELIVERY

Deliver weatherstripping in original containers.

PART 2 PRODUCTS

2.1 WEATHERSTRIPPING

Weatherstripping shall be a high density urethane open cell foam that exhibits closed cell characteristics when compressed. It shall have a very low compression set, good shock absorption, and low out-gassing.

Attachment to the door frame shall be by permanent acrylic adhesive.

Weatherstripping shall be 1/2-inch wide by 1/4-inch thick. Color shall be black. Product characteristics shall be as follows:

Adhesive: Permanent acrylic based pressure sensitive adhesive. Shall include s a film carrier for non-stretch characteristics.

SECTION 08 71 10 Page 2

Test Method: In accordance with ASTM D3574.

Density: 15 lb/ft3.

Compression Deflection: 4 to 8 psi.

Compression Set: (50%) 10 max.

Service Temperature: Acrylic based, -20°F to 190°F.

Flammability: FMVSS 302; UL94 HBF = 3/16.

Application Temperature Range: 65 - 100 °F.

2.1.1 Acceptable Product

An aceptable product for weatherstripping shall be "Weather Stripping and Gasket Tape, Item Code 472079", as available from Essentra Components, 7400 West Industrial Drive, Forest Park, IL 60130; Telephone 800-847-0486;

(essentracomponents.com), or approved equal.

PART 3 EXECUTION

3.1 DEMOLITION

Existing weatherstripping and related items of the door leading into the intake tower shall be removed in their entirety and the underlying surfaces shall be prepared and painted prior to the installation of new weatherstripping. After painting is completed, installation of new weatherstripping shall be performed.

3.2 INSTALLATION

Install weatherstripping in accordance with manufacturers' printed installation instructions. Provide full contact, weathertight seals that allow operation of doors without binding the weatherstripping and that are complete around all door edges including sill.

-- End of Section --

SECTION 08 71 10 Page 3

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 3 PAGES

01 11 00 SD-01 Preconstruction Submittals

1.7.2.2 G ROInitial Project Schedule

SD-07 Certificates

1.7.2.3 G ROPeriodic Schedule Updates

1.7.1 G RORequest Application

01 33 00 SD-01 Preconstruction Submittals

1.9 G ROSubmittal Register

01 33 29 SD-01 Preconstruction Submittals

1.4 G RODocumentation Requirements

01 35 26 SD-01 Preconstruction Submittals

1.7 G ROAccident Prevention Plan (APP)

SD-06 Test Reports 1.4Monthly Exposure Reports 1.12Notifications and Reports

1.12.2 G ROAccident Reports

1.12.3LHE Inspection Reports

SD-07 Certificates 1.6.1.5Crane Operators/Riggers

1.7.2.1 G ROStandard Lift Plan

1.7.2.2 G ROCritical Lift Plan

1.8Activity Hazard Analysis (AHA) 1.9.1Hot Work Permit 1.12.4Certificate of Compliance

License Certificates 01 45 00 SD-01 Preconstruction Submittals

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P H

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 3 PAGES

01 45 00 3.2 G ROContractor Quality Control (CQC) Plan

01 50 00 SD-01 Preconstruction Submittals

1.4 G ROConstruction Site Plan

3.8.9 G ROTemporary Electrical System

SD-03 Product Data 2.2Barricades 2.2Safety Fence 2.2Chain-Link Fence

01 57 20 SD-01 Preconstruction Submittals

1.7 G ROEnvironmental Protection Plan

01 74 19 SD-01 Preconstruction Submittals

1.5 G ROWaste Management Plan

08 71 10 SD-03 Product Data

2.1 G ROWeatherstripping

09 97 02 SD-01 Preconstruction Submittals

1.3 G ROSafety, Health, and

Environmental Requirements

1.3.1.5 G RORespiratory Protection Plan

1.3.1 G ROVentilation Assessment Plan

1.3.2.1 G ROAirborne Sampling Plan

1.3.2 G ROMedical Surveillance Plan

1.3.2.2 G ROWorker Protection Plan

1.3.3.1Waste Manifest

1.3.3.1 G ROWaste Disposal Plan

1.3.3.2 G ROContainment Plan

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 3 OF 3 PAGES

09 97 02 1.3.3.3 G ROVisible Emissions Monitoring Plan

1.3.3.4 G ROTSP Monitoring Plan

1.3.3.5 G ROWater Quality Plan

SD-03 Product Data Part 2 G ROManufacturer's Product Data

Sheet SD-06 Test Reports

1.3.3.4TSP Test Report 3.4Inspection Reports 1.3.2.2Medical Status Report 1.3.2.3Change in Medical Status Report

1.3.2.1 G ROAir Monitoring Test Plan

1.3.2.1Air Monitoring Test Report

SD-07 Certificates 1.5.1Certified EHS Professional 1.5.2Certified Lead Laboratory 1.5.3SSPC QP 1 Certificate 1.5.4SSPC QP 2 Certificate 1.5.5Coating Thickness Gage

Qualification

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P

A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 00 01 - AMENDMENT 0001 OF SOLICITATION
00 00 01 - AMENDMENT 0001 OF SOLICITATION
1.1 CHANGES TO SPECIFICATIONS
1.1.1 Narrative Changes
1.1.2 New Specification Section
DIVISION 08 - OPENINGS
08 71 10 - DOOR WEATHERSTRIPPING
08 71 10 - DOOR WEATHERSTRIPPING
PART 1 GENERAL
1.1 SUMMARY
1.2 REFERENCES
1.3 SUBMITTALS
1.4 DELIVERY
PART 2 PRODUCTS
2.1 WEATHERSTRIPPING
2.1.1 Acceptable Product
PART 3 EXECUTION
3.1 DEMOLITION
3.2 INSTALLATION

Revised Submittal Register