Effective: 03/01/17 Canceling: 03/01/16

M A

R C

H2017 Gas and electric underground service installation requirements

CALL PSE’S CUSTOMER CONSTRUCTION SERVICES AT 1-888-321-7779 OR VISIT PSE.COM/CUSTOMERCONSTRUCTION FOR MORE INFORMATION.

Builder/owner/developer responsibilities

PSE requires the following conditions to make the worksite construction ready ahead of scheduled service installation:

Permits

• Fuel line must be in place with an approved permit and plumbed to an approved gas meter location.

A valid permit must be indicated by either:

» A permit visible from outside the structure, or » A green Gas Service Approval sticker affixed to the fuel line.

• Electrical permit must be approved and the Department of Labor & Industries (L&I) sticker must be affixed on the electric meter base.

Meter location

• An acceptable meter location that allows for required access and clearance shall be provided.

» See Gas Meter Clearances and Service Installation Requirements (form 3885) for gas meter locations.

» See Electric Underground Service Installation Requirements (form 6080) for electric meter locations.

Trench work

• The worksite must be prepared to PSE specifications.

» The site must be at final grade or have final grade marked in the area of construction and trench line route.

» For unique site preparation requirements, contact your Project Manager.

» Installation of trench, work pits, sand for bedding and shading, and conduit must meet PSE specifications.

» Sand must be provided by the builder or developer and placed within hand-shoveling distance to the work pit or trench for bedding and shading. (See Sand Requirements for Direct-Buried Installations on page 2.)

» If either gas or electric service will not be provided by PSE, please consult with the other utility for any additional clearance requirements. Use the greater of any conflicting distances.

» Conduit for electric service lines shall be used under all paved surfaces, decks, rockeries, bulkheads, or obstacles to access the service line.

Additional information

• For additional electric service installation information, see Electric Underground Service Installation Requirements

(form 6080).

• For additional gas service installation information and meter set assembly locations and clearances, see Gas Meter Clearances and Service Installation Requirements (form 3885).

• View a video for the proper installation of natural gas piping at this site: pse.com/servicerequirementvideos

Become familiar with what can delay your project and cause it to be red-tagged:

• Construction debris or water in the trench or work pits.

• Trenches excavated to the incorrect depth.

• Failure to maintain minimum separations between utilities and drainage pipes.

• Sand and backfill material are not available, inaccessible, or inadequate.

• Requested meter location is not acceptable or fails to meet minimum clearances.

• Permits are not approved or visible.

• Conduit color and size are incorrect, or conduit is installed improperly.

Gas and electric underground service installation requirements

Canceling: 03/01/16

JOINT SERVICE LINE TRENCH DIRECT-BURIED INSTALLATIONJOINT SERVICE LINE TRENCH CONDUIT INSTALLATION

Service lines in conduit and direct-buried installations

Separation requirements to other utilities for conduit and direct-buried installations

Backfill requirements for conduit and direct-buried installations

*Check with local permitting agency for depth of cover requirements for any PSE facility installed in public right-of-way.

36" cover may be required over PSE facilities.

*Contact your TV/TEL provider about their separation requirements from power.

FINAL GRADE FINAL GRADE

24" MIN

TO

36" MAX

COVER*

24" MIN

TO

36" MAX

COVER*

BACKFILL FOR

CONDUIT FREE OF

ROCKS LARGER

THAN 8" IN

DIAMETER

FINAL BACKFILL FOR

DIRECT-BURIED FREE

OF ROCKS LARGER

THAN 8" IN DIAMETER

12" MIN

SEPARATION

12" MIN

SEPARATION

12" MIN

SEPARATION

6" MIN

SEPARATION

12" MIN

SEPARATION

12" MIN

SEPARATION

GAS SERVICE LINE

IN CONDUIT

TV & TEL ELECTRIC SERVICE

CABLE IN CONDUIT

GAS SERVICE LINE

DIRECT-BURIED

TV & TEL ELECTRIC SERVICE

CABLE DIRECT-BURIED

6" SAND SHADING

4" SAND BEDDING

32" TYPICAL

(POWER, GAS, PHONE & CABLE)

32" TYPICAL

(POWER, GAS, PHONE & CABLE)

24" MIN

(TO EXCAVATED DIRT PILE)

24" MIN

(TO EXCAVATED DIRT PILE)

INSTALLATION

HORIZONTAL SEPARATION VERTICAL SEPARATION WHEN CROSSING

GAS TO ELECTRIC GAS TO TV/TEL ELECTRIC TO TV/TEL GAS TO ELECTRIC GAS TO TV/TEL ELECTRIC TO TV/TEL

CONDUIT 12" MINIMUM 6" MINIMUM 12" MINIMUM* 6" MINIMUM 6" MINIMUM 12" MINIMUM*

DIRECT-BURIED 12" MINIMUM 12" MINIMUM 12" MINIMUM* 12" MINIMUM 6" MINIMUM 12" MINIMUM*

NOTE: STACKING UTILITIES NOT PERMITTED

INSTALLATION BEDDING SHADING BACKFILL

CONDUIT NOT REQUIRED NOT REQUIRED SOIL THAT IS FREE FROM CONSTRUCTION DEBRIS, GLASS, SHARP

ROCKS, FROZEN CLODS, AND ROCKS LARGER THAN 8"

DIRECT-BURIED 4" MINIMUM 6" MINIMUM

Sand requirements for direct-buried installations

• The customer shall provide additional clean sand meeting PSE standards in piles that are readily accessible within hand-shoveling distance of each work pit for shading and bedding.

» Sand meeting PSE specification can be found at supplier locations within the PSE service territory and is commonly referred to as “builder’s sand” (ASTM C33). Call PSE’s Customer Construction Services at 1-888-321-7779 for additional sand information.

» Bedding sand will be provided and installed by the customer to a minimum depth of 4 inches prior to the electric and gas direct-buried installations.

» Shading sand is to be installed by the PSE crew after direct-buried electric, gas, or joint service line installation.

Enough sand shall be provided so that the installation can be covered to a minimum depth of 6 inches.

(See diagrams above.)

Canceling: 03/01/16

Property line work pit and service connections

Work Pit Legend

1. 3/8" Pull Rope − For runs over 60' for electric and 100' for gas.

2. Electric Service Conduit − Customer Provided. See Conduit Requirements in Electric Underground Service Installation Requirements (form 6080).

3. 3/4 Yard Bedding and Shading Sand − Sand shall be provided on-site by the customer and placed within hand-shoveling distance to the work pit for bedding and shading of direct-buried facilities. A larger work pit may require more sand (see sand and backfill requirements on Page 2).

4. Gas Service Conduit − Customer Provided. See Conduit Requirements in Gas Meter Clearances and Service Installation Requirements (form 3885).

5. Electric Stub Marker − Utility Provided. Power stub shall be exposed on day of service connection

6. Gas Stub Marker − Utility Provided. Dig to 12" from gas stub marker. Customer shall not expose the stub. If accidentally exposed, cover with 12" of sand.

7. CATV/TEL Marker

SECTION A-A

WORK PIT DIMENSIONS

ELECTRIC AND JOINT UTILITY

ELECTRIC AND JOINT UTILITY

28" TO 32" MIN DEEP

(24" MIN COVER)

48"

(APPROX)

PIPES AND

WIRES

UTILITY INSTALLED

GAS

TEL

TV

POWER

48"

(APPROX)

FINAL GRADE

A

A

AA

ELECTRIC

SERVICE

TV &

TEL

GAS

SERVICE

TRENCH TO

BUILDING

POWER

TV & TEL

GAS

PSE TRANSFORMER

(OR PEDESTAL, HANDHOLE, OR STUBOUT)

PSE POLE

EXCAVATED DIRT

PILE AND SAND

BEDDING/SHADING

EXCAVATED DIRT

PILE AND SAND

BEDDING/SHADING

24"

MIN

24"

MIN

48" MIN

24"

MIN

48" MIN

12" MIN

12" MIN

12" MIN 12" MIN

12" MIN

WORK PIT PROFILE AT PADMOUNTED TRANSFORMERS,

PEDESTALS OR HANDHOLES

WORK PIT PROFILE AT PSE POLES

© 2017 Puget Sound Energy | 3061 03/17

Effective: 03/01/17 Canceling: 03/01/16

Meter and service connections work pit

Work Pit Legend

1. Electric Meter Base - Customer Provided, and secured to stud or structural member.

2. 3/8" Pull Rope - For runs over 60' for electric and 100' for gas.

3. Conduit Service Riser - Customer Provided.

4. Conduit Straps (2 Minimum) - Customer Provided.

5. Conduit Elbows - Customer Provided, 24 " min bend radius. See conduit requirements in Electric Underground Service Installation Requirements (form 6080).

6. Electric Service Conduit - Customer Provided. See Conduit Requirements in Electric Underground Service Installation Requirements (form 6080).

7. Gas Meter Assembly - Utility Provided.

8. Fuel Line Stub Typically Protrudes 4" to 5" - Customer Provided

9. Finish Grade - Finish grade shall be clearly marked at fuel line stubout.

10. Work Pit - Leave work pit open between gas service line conduit and proposed gas meter service riser location for gas line extension (Customer Provided).

11. 3/4 Yard Bedding and Shading Sand - Sand shall be provided on-site by the customer and placed within hand-shoveling distance to the work pit for bedding and shading of direct-buried facilities. A larger work pit may require more sand (see sand and backfill requirements on Page 2).

12. Drainage Pipe - 6 " minimum clearance should be maintained from gas service line.

13. Electric Meter - Utility Provided.

14. Gas Service Conduit - Customer Provided. See Conduit Requirements in Gas Meter Clearances and Service Installation Requirements (form 3885).

Discontinuous and Continuous-Conduit Options

METER BASE WORK PIT DIMENSIONS

ELECTRIC AND JOINT UTILITY

48" TO 60"

(APPROX)

32" TO 38"

TYPICAL

4'

MIN

2 11

WORK PIT 48" TO 60"

FROM FUEL LINE STUB

28" TO 32" DEEP

(24" MIN COVER)

FUEL LINE STUB

FINISHED WALL

DISCONTINUOUS-CONDUIT CONTINUOUS-CONDUIT

12"

MIN

32"

TYPICAL

POWER

TV & TEL

GAS

48" TO 60"

(APPROX)

ELECTRIC

METER

GAS

METER

For spacing between utilities, see Separation Requirements to Other Utilities for Conduit and Direct-Buried Installations

(Page 2).

Canceling: 03/01/16

M A

R C

H2017 Gas meter clearances and service installation requirements

CALL PSE’S CUSTOMER CONSTRUCTION SERVICES AT 1-888-321-7779 OR VISIT PSE.COM/CUSTOMERCONSTRUCTION FOR MORE INFORMATION.

• The clearances in this handout also apply to features on buildings adjacent to the building where the gas meter is located.

• Final grade of the service line route must be in place before the service line can be installed.

• If you are unable to meet the meter location requirements in this handout, contact PSE for further assistance.

• Puget Sound Energy reserves the right to designate gas meter locations so that they comply with PSE standards.

• For gas meter installations in Cle Elum and west of Cle Elum within Upper Kittitas County, see the Gas Meter Protection from Snow and Ice in Snow Country handout (form 3736).

Builder/owner/developer requirements

Gas meter locations

Measuring around a building corner

Locate gas meter on the front wall, or within the front 1/3 of the side wall, observing the corner clearance requirements detailed below.

The area 3 feet in front of and 2 feet to either side of the meter set assembly must be free of any landscaping (bushes, fences, etc.) and other structures that restrict access to the meter set assembly.

Outside corners

• The regulator relief vent (see diagram above) should be at least 12" from any outside corner.

» If the regulator relief vent is at least 12" from any outside corner, then there are no minimum clearances to features around the corner.

» If the regulator relief vent is less than 12" from any outside corner, then the minimum clearances specified in this handout must be maintained.

Measure as if using a string

Inside corners

• Clearance distances from the regulator relief vent or meter set assembly to the feature must be maintained in accordance with this handout. Measure as if using a string.

METER TYPE

A

METER WIDTH

(TYPICAL)

B

FUEL LINE

HEIGHT (TYPICAL)

METER

OUTLET

DIAMETER

250 16" 32" TO 36" 1"

425 24" 42" TO 46" 1-1/4"

630 30" 42" TO 46" 1-1/4"

1000 32" 46" 1-1/4"

GAS METER CLEARANCE TO FINISH GRADE

(250 METER SHOWN)

HOUSE/BUILDINGHOUSE/BUILDING

PLAN VIEWPLAN VIEW ELEVATION VIEWELEVATION VIEW

FUEL LINE LOCATION

(TYPICAL)

REGULATOR

TYPICAL

REGULATOR

RELIEF VENT

8" MIN

FINISH GRADE

TYPICAL PUBLIC ACCESS

DRIVEWAY

FR

ON

T 1/

OF

SI

DE

W

AL

L

FR

ON

T 1/

OF

SI

DE

W

AL

L

WALKWAY

FRONT WALL

BUILDING

FEATURE

METER

<12"

METER

PROPERTY

FEATURE

PROPERTY

FEATURE

BUILDING

FEATURE

6" MIN

B

A

Gas meter clearances and service installation requirements

Canceling: 03/01/16

Property line work pit for customer-provided trench and backfill

Service line in conduit installations

Service line direct-buried installations

1/2 YARD BEDDING AND SHADING SAND

SAND SHALL BE PROVIDED ON-SITE BY THE CUSTOMER AND PLACED WITHIN HAND-

SHOVELING DISTANCE TO THE WORK PIT FOR BEDDING AND SHADING OF DIRECT-BURIED

FACILITIES. A LARGER WORK PIT MAY REQUIRE MORE SAND (SEE BACKFILL REQUIREMENTS IN

THIS HANDOUT). SAND SHALL BE WASHED, CLEAN, AND FREE OF DEBRIS OR ROCKS LARGER

THAN 1/4 INCH.

GAS SERVICE LINE CONDUIT

CUSTOMER PROVIDES AND PLUGS

CONDUIT END.

GAS STUB MARKER

UTILITY PROVIDED

48"

(APPROX)

GAS STUB

MARKER WHEN

DIGGING WORK

PIT LEAVE 12"

OF SAND IF

ACCIDENTLY

EXPOSED

GAS STUBOUT

GAS STUB

MARKER

20" TO 24"

DEEP

24"

FINAL GRADE

GAS STUBOUT

WHEN DIGGING WORK PIT,

LEAVE 12" OF SAND

OVER GAS STUB END IF

ACCIDENTALLY EXPOSED

24" MIN

(TO EXCAVATED DIRT PILE)

24" MIN

(TO EXCAVATED DIRT PILE)

12" TYPICAL

(4" MIN*)

12" TYPICAL

FINAL

GRADE

FINAL

GRADE

GAS SERVICE

LINE

IN CONDUIT

FOR MINIMUM

GAS SERVICE

LINE DEPTH

SEE TABLE AT

RIGHT

36" MAX

COVER

BACKFILL FOR

CONDUIT

SEE

REQUIREMENTS

FOR MINIMUM

GAS SERVICE LINE

DEPTH

SEE TABLE AT RIGHT

36" MAX

COVER

FINAL BACKFILL

FOR DIRECT BURY

SEE

REQUIREMENTS

6" SAND SHADING

GAS SERVICE LINE

DIRECT-BURIED

4" SAND BEDDING

48"24"

GAS STUBOUT

DIG TO WITHIN 12" FROM GAS STUB MARKER

CUSTOMER SHALL NOT EXPOSE THE STUB. IF

ACCIDENTALLY EXPOSED, COVER GAS STUB WITH

12" OF SAND

WORK PIT DIMENSIONS

WORK PIT CROSS-SECTION

Backfill requirements for conduit installations

• Backfill for conduit: Soil that is free from construction debris, glass, sharp rocks, frozen clods, and rocks larger than 10" in diameter.

• Shading: None required above conduit.

• Bedding: None required below conduit.

GAS SERVICE LINE IN CONDUIT

INSTALLATION

GAS SERVICE LINE DEPTH TABLE FOR CONDUIT AND

DIRECT-BURIED INSTALLATIONS

*TRENCH WIDTH EXCEPTION

GAS SERVICE TYPE

GAS SERVICE

PIPE SIZE

MINIMUM DEPTH OF

COVER OVER GAS

RESIDENTIAL ANY SIZE 18"

COMMERCIAL/INDUSTRIAL 1-1/4"+ 24"

ANY SERVICE IN SNOW

COUNTRY (SEE FORM 3736)

ANY SIZE 24"

Backfill requirements for direct-buried installations

• Final backfill for direct bury: The backfill layer above the sand shading shall be soil that is free from construction debris, glass, sharp rocks, frozen clods, and rocks larger than 8" in diameter.

» If the final layer contains rocks larger than 8" in diameter, then 12" of shading shall be placed over the gas service.

» Rocks larger than 10" in diameter are not permitted in the final backfill.

• Sand bedding: The customer shall provide and install clean sand to a depth of 4" inches prior to gas service pipe installation. See diagram at left.

• Sand shading: The customer shall provide additional clean sand in piles that are readily accessible near the trench. This shading sand is to be installed by the PSE crew after direct-buried gas line installation. Enough sand shall be provided so that the installation can be covered to a depth of 6 inches. See diagram at left.

• If customer-owned facilities will be included in the trench, please contact PSE or local power company directly for clearance requirements.

GAS SERVICE LINE

DIRECT-BURIED INSTALLATION

For separation requirements to other utilities see page 2 of the Gas and Electric Underground Service Installation Requirements handout (form 3061)

For separation requirements to other utilities see page 2 of the Gas and Electric Underground Service Installation Requirements handout (form 3061)

TR

EN

CH

T

O

BU

IL

DI

N G

24"

(APPROX)

20" TO 24" DEEP

WHEN CONVERTING EXISTING CONSTRUCTION

THE MINIMUM TRENCH WIDTH ACCEPTABLE IS 4"

Canceling: 03/01/16

SERVICE LINE CONDUIT SIZE, TYPE, & COLOR MIN. BEND RADIUS

TYPICAL RESIDENTIAL ≤185' 2" (MINIMUM) SCHEDULE 40 YELLOW OR WHITE PVC 36"

TYPICAL RESIDENTIAL SERVICES >185' AND ≤ 1000' 3" (MINIMUM) SCHEDULE 40 YELLOW OR WHITE PVC 48"

TYPICAL RESIDENTIAL > 1000' 4" (MINIMUM) SCHEDULE 40 YELLOW OR WHITE PVC 60"

TYPICAL LARGE MULTI-FAMILY & COMMERCIAL SERVICES 4" (MINIMUM) SCHEDULE 40 YELLOW OR WHITE PVC 60"

Meter and service connections work pit

Conduit requirements for gas service

Preferred trench location when the trench must pass near trees

1/2 YARD BEDDING AND SHADING SAND

SAND SHALL BE PROVIDED ON-SITE BY THE CUSTOMER AND PLACED WITHIN

HAND-SHOVELING DISTANCE TO THE WORK PIT FOR BEDDING AND SHADING OF

DIRECT-BURIED FACILITIES. A LARGER WORK PIT MAY REQUIRE MORE SAND (SEE

BACKFILL REQUIREMENTS IN THIS HANDOUT). SAND SHALL BE WASHED, CLEAN,

AND FREE OF DEBRIS OR ROCKS LARGER THAN 1/4 INCH.

24"

TYPICAL

12"

12"

GAS SERVICE LINE

CONDUIT

DRIPLINEROOT ZONE

48" TO 60"

(APPROX)

FUEL LINE STUB

36"

TYP (APPROX)

GA

S

GA

S

M

ET

ER

FI

N

IS

HE

D

W

AL

L

TV

T

EL

PO

W

ER

WORK PIT DIMENSIONSFUEL LINE STUB TYPICALLY PROTRUDES 4" TO 5”

CUSTOMER PROVIDED

GAS METER

UTILITY PROVIDED

SERVICE RISER

3/8" PULL ROPE

IF CONDUIT IS OVER 100'

SHUTOFF VALVE

WORK PIT 48" TO 60"

FROM FUEL LINE STUB

GAS SERVICE LINE CONDUIT

CUSTOMER PROVIDES AND PLUGS CONDUIT END

DRAINAGE PIPE

6" MINIMUM CLEARANCE

SHOULD BE MAINTAINED FROM

GAS SERVICE LINE

FINISH GRADE SHALL BE CLEARLY

MARKED AT FUEL LINE STUBOUT

4" TO 5"

• PSE recommends the use of conduit for all gas service installations.

• Conduit installation requirements

» Gas conduit runs over 100 feet long must have a 3/8-inch minimum diameter pull rope installed.

» Conduit bends shall be one long radius, single-piece sweeps (see table below).

» Fittings and elbows shall not be used because the joints prohibit service insertion.

» The sum total of the degrees of bends in the conduit run cannot exceed 180° .

» Conduit shall not cross in the trench.

» Yellow or white Schedule 40 PVC conduit used for gas service lines shall not be marked “water,” or any other utility.

MINIMUM

CONDUIT

BEND RADIUS

The preferred position for customer-provided trenching is as far as possible outside of the dripline of trees. If this is not possible, contact PSE’s Customer Construction Services at 1-888-321-7779 for trench location and depth requirements

20" TO 24" DEEP

Canceling: 03/01/16

CLEARANCE ZONE FROM WINDOWS, BUILDING VENTS, AND FIREPLACE CLEANOUTS

WINDOW

OPENING

ATTIC VENT

OPENING

CRAWL SPACE OR GARAGE

VENT OPENING

SOFFIT VENT

OPENING

3' 3'

3'3'

1'

Regulator relief vent clearances from building features

CLEARANCE ZONE FROM DOORS AND GARAGE DOORSCLEARANCE ZONE FROM ELECTRICAL COMPONENTS

POWER DISCONNECT

WALL SWITCH ELECTRIC OUTLET

3' 3' 3'

3'

1'

3'

3'

3'

10' 10'

10'10'

3'

3'

3'

3'3'

GARAGE DOORS

BATHROOM FAN VENTS FIREPLACE CLEANOUT

OPENING

DRYER

INTAKE/EXHAUST

FIREPLACE AIR

INTAKE/EXHAUST

FURNACE AIR

INTAKE/EXHAUST

MECHANICAL AIR

INTAKE OPENING

WINDOW-MOUNTED

AIR CONDITIONER

WALL-MOUNTED

AIR CONDITIONER

WINDOW/

WALL-MOUNTED FAN

DOORS

MECHANICAL AIR INTAKE FEATURES

AT CLEARANCE DISTANCE A (10 FEET)

APPLIANCE INTAKE AND EXHAUST FEATURES

AT CLEARANCE DISTANCE B (3 FEET)

CLEARANCE ZONES FROM WALL-MOUNTED FANS AND AIR CONDITIONERS, AND APPLIANCE VENTS AND INTAKES

CLEARANCE ZONE

CLEARANCE ZONECLEARANCE ZONE

CLEARANCE ZONE

B

A

Canceling: 03/01/16

Gas meter clearances from building features

Gas meter clearances under porches, decks, and balconies

GROUND LEVEL

CLEARANCE ZONE

PREFERRED CLEARANCE ZONE

CLEARANCE ZONE FROM OVERHEAD- OR UNDERGROUND-FED

PSE ELECTRIC METERS

PREFERRED CLEARANCE ZONE FROM WATER SPIGOTS,

AND FROM COMMUNICATIONS AND CABLE BOXES

CLEARANCES FROM PADMOUNTED AIR CONDITIONERS,

HEAT PUMPS, GENERATORS OR TRANSFORMERS CLEARANCE ZONE FROM INCINERATORS OR OPEN FLAME DEVICES

WATER SPIGOT COMMUNICATIONS BOX

MINIMUM CLEARANCE

FROM GRADE BELOW

METER TO DECK BOTTOM

MINIMUM CLEARANCE

FROM GRADE BELOW

METER TO DECK BOTTOM

GENERATOR OR

TRANSFORMER

OPEN FLAME OR

PERMANENT BBQ

INCINERATORAIR CONDITIONER OR

HEAT PUMP

GROUND LEVEL

GROUNDING ROD

ROOFLINE

NOTE: CLEARLY MARK

BURIED GROUND ROD

NOTE: A CLEARANCE

OF 36" IS REQUIRED

IN FRONT OF THE

ELECTRIC METER FACE

3'

3' 3' 3'

3'

3'

3'

3'

1'18"

2'

2'

3'

6'

3' 3'

6'

CLEARANCE ZONE UNDER BALCONIES (NO STAIRS TO GROUND LEVEL)

CLEARANCE ZONE UNDER DECKS AND PORCHES

(METER MUST NOT BE LOCATED UNDER STAIRS OR ANYWHERE

BETWEEN DOORS AND STAIRS)

CLEARANCE ZONE CLEARANCE ZONE

© 2017 Puget Sound Energy | 3885 03/17

Effective: 03/01/17 Canceling: 03/01/16

Guard post installation (PSE’s responsibility)

• To protect meter set assembly from vehicle damage, PSE will install guard posts when required.

• To avoid the need for PSE to install guard posts, choose a meter location that is away from driveways or other areas where vehicles travel.

• Guard post requirements are based on the following factors:

» Existing barriers (curbs, guard rails, steep increases in grade, ditches, rockeries, trees, shrubs, chimneys, recessed walls, etc.), which will provide adequate protection;

» Proximity of the facility to the edge of the travel lanes;

» The expected speeds in the travel lanes;

» The width of the travel lane;

» The volume of vehicle traffic;

» Existing nearby building damage or other indicators of vehicle damage that may have already occurred; and, » The type of customer (i.e., single-family residential versus commercial/industrial or multifamily).

• In cases where a meter set assembly will be installed behind a curb, observe the following:

» If the curb will be a rolled curb, and if there is less than 10 feet of space between the curb and the meter, guard posts will be installed; and, » If the curb will have a vertical face, and if there will be less than 5-1/2 feet between the curb and the meter, guard posts will be installed.

• Guard posts will be painted “caution” yellow, especially those located in commercial or industrial locations, street rights-of-way, and alleyways.

1. Guard posts shall be made from steel pipe, 6 feet long, filled with wet concrete and domed on top.

2. In this installation, the guard post can be solid concrete 9 inches in diameter.

3. At least 24 inches of the guard post shall be embedded in the base, with at least 42 inches of the post above final grade.

4. In this installation, at least 26 inches of the guard post shall be embedded in the base, with at least

42 inches of the post above final grade.

5. Additional guard posts are required if the centerline spacing between guard posts exceeds 36 inches.

The additional guard posts are typically evenly spaced between the outer two posts.

2-1/2" DIA STEEL PIPES

FILLED WITH CONCRETE

POSSIBLE DIRECTION OF

VEHICULAR TRAVEL

POSSIBLE DIRECTION OF

VEHICULAR TRAVEL

POSSIBLE DIRECTION OF

VEHICULAR TRAVEL

POSSIBLE DIRECTION

OF VEHICULAR TRAVEL

POSSIBLE DIRECTION OF

VEHICULAR TRAVEL

EDGE OF MSA

UNDERGROUND

CONCRETE BASE

42"

MIN

ABOVE

GRADE

30" 24"

EDGE OF MSA

EDGE OF MSA

BU

IL

DI

N

G W

AL

L

GAS METER

ASSEMBLY

8"

8"

8"

DO NOT INSTALL

CENTERLINE OF GUARD

POSTS IN SHADED AREA

TYPICAL SINGLE-FAMILY GUARD POST INSTALLATION

SINGLE-FAMILY RESIDENCE COMMERCIAL/INDUSTRIAL OR MULTI-FAMILY LEGAL SPEED LIMIT GREATER THAN 35 MPH

Guard Post 1 2-1/2" Dia. 4" Dia. 6" Dia.2

Concrete Base 3 8" Dia. x 30" High 15" Dia. x 30" High 30" Dia. x 42" High4

Minimum Clearance between Meter Set Assembly & Guard Post 5 8" 12" 12"

TOP VIEW EXAMPLE OF GUARD POST LOCATIONS

THAT PROVIDE PROTECTION FROM ALL POSSIBLE

DIRECTIONS OF VEHICULAR TRAVEL

DRIVEWAY OR PARKING

AREA

Atch-4 PSE Gas Service Installation Reqmnts - Mar2017
PSE Gas Meter Clearance Reqmnts - Mar2017