Q. Please specify if ITEM 0019 Installation requires just to put each machine into the position inside the gym and power it up to show that is functional (not broken), or to power it up + demonstrate that each feature of each machine is fully functional? And, in addition, is it necessary that the vendor instruct a designated person how to operate each type of machine?
It is important to know this in order to estimate how long the Installation process is going to take and to quote it fairly.
A. In response to the vendors query ITEM 0019 INSTALATION.MWR will need the vendor to do the following as far as installation of the requested equipment. Place equipment in the MWR facility with MWR assistance and direction as needed. Power up and run through all functions to ensure serviceability of all equipment. Demonstrate all features relevant to the proper operation of said equipment to designated MWR personnel. Instructions to our designated MWR personnel as to proper operation and relevant special functions of equipment.