This is an Industry Day presentation for two Army Reserve Center repair projects in New Cumberland, PA and Newtown Square, PA, to be held on March 4, 2025. The projects will be issued as Design-Build contracts under total small business set-asides using a two-phase best value trade-off source selection process.

The New Cumberland project (W912QR25NEWCUMBERLAND) involves repairing a 28,989 SF facility built in 1992, while the Newtown Square project (W912QR25RA019) involves repairing a 38,987 SF facility built in 1976. Both projects have an estimated 1,100-day construction duration with planned advertisement in March/April 2025, Phase I proposals due April/May 2025, Phase II proposals due August 2025, and contract award in September 2025. The work includes mechanical, electrical, plumbing repairs, life safety upgrades, and facility modernization. The U.S. Army Corps of Engineers Louisville District is managing the projects in partnership with the 99th Readiness Division. Interested contractors must register in SAM.gov and submit proposals through the PIEE Solicitation Module. The presentation includes floor plans, site layouts, and detailed evaluation criteria for both Phase I (past performance, technical approach) and Phase II (design narrative, management plan, schedule).

View the file

Other files

File Type Posted
Industry Day Attendee List.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INDUSTRY DAY FORUM

New Cumberland and Newtown square ARC Presenters:

Jonathan Cowen – Project Manager Felix Carrion-Viera – Project Engineer Eliot Lincoln – Project Engineer Ryan King – Contract Specialist Crystal Harbin – Deputy for Small Business

Date: 04 March 2025

Training Center Two, Newtown Square Army Reserve Center (ARC) ”The views, opinions and findings contained in this report are those of the author(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”

ADMINISTRATIVE ANNOUNCEMENTS

Please ensure that you have signed in (Send in chat for remote participants) Company Name, POC Name, Email, Phone Are you interested in being the Prime or Subcontractor If you’re interested in being a subcontractor, state the type of work you are interested (Electrical, Mechanical, Roofing, etc.)

Please turn off all mobile devices No recording This briefing and the attendee roster will be posted to SAM Please be advised that none of the information discussed today is contractually-binding

Introduction of Team Members

Army Reserve Overview

USACE Procurement Process Overview

Overview of the New Cumberland ARC Project

Overview of the Newtown Square ARC Project

Q&A Session

AGENDA

US Army Reserve OVERVIEW

Jonathan A. Cowen Program Manager U.S. Army Corps of Engineers Louisville District

Army reserve program 88th Readiness Division Ft McCoy, WI

California Nevada Arizona New Mexico Texas Oklahoma Arkansas Kansas Nebraska Iowa Missouri Minnesota Ohio Illinois Utah Colorado South Dakota North Dakota Montana Wyoming Idaho Oregon Mississippi Alabama Georgia

MD

DC

Maine

VT

NH

RI

DE

81st Readiness Division Ft Jackson, SC

63rd Readiness Division Mountain View, CA

99th Readiness Division Ft Dix, NJ OCAR - Fort Belvoir, VA USARC - Fort Bragg, NC

OCAR – Fort Belvoir, VA

USARC –

Fort Liberty, NC Puerto Rico

Fort Hunter Liggett – CA -Parks Reserve Forces Training Area – CA

JBMDL

Fort Buchanan, PR

The AR MILCON program has been centrally managed by the Louisville District since 1995

AR MILCON Opportunities thru LRL

Military Construction Army Reserve (MCAR)

Unspecified Minor Military Construction (UMMCR)

Maintenance & Repair, Army Reserve (MRAR)

LRL partners with Geographic Districts for construction oversight and local expertise

Louisville District (LRL) + Roadrunner Resident Office (CESPL)

Daniel Netherton, Administrative Contracting Officer (ACO)

Stephanie Kenett, Contracting Officer’s Representative (COR)

Local District Construction Management Team (TBD) Administrative Contracting Officer (ACO) – Jeff Owens

Contracting Officer’s Representative (COR) – Elvis Garay

Army reserve MILCON program management

Army reserves milcon communication plan

USACE PROCUREMENT PROCESS OVERVIEW

Newtown Square Project

Ryan King Contract Specialist U.S. Army Corps of Engineers Louisville District

Jesse Scharlow Contracting Officer

New Cumberland Project

Adam Brooks Contract Specialist U.S. Army Corps of Engineers Louisville District

Adam Wantland Contracting Officer

System for Award Management (SAM) – www.SAM.gov

New Cumberland Solicitation will beW912QR25NEWCUMBERLAND Newtown Square Solicitation will be W912QR-25-R-A019 Search by keyword (Select “Any Words” or “All Words”): “Newtown, New Cumberland”

View Interested Vendors List and register as an Interested Vendor.

Register to receive notifications and updates / amendments.

RFP Technical Information (i.e., Plans and Specs) will be available for download from www.SAM.gov

HOW TO OBTAIN THE SOLICITATION

A list of general contractors bidding the project is not maintained. The Government does not know who is bidding the project until a proposal is received. SAM.gov does contain an Interested Vendors List to which you may add your firm’s name.

Pre-Solicitation Notice – will be posted on www.sam.gov at least 15 days prior to the initial issuance of the Solicitation package.

Advertisement – Minimum 30 days to prepare proposals for Each Phase.

Amendments issued to the RFP will also be posted on www.sam.gov

OBTAINING THE ISSUE DOCUMENTS

Requirements to download Technical Data Package:

Locate and access the Solicitation notice in the SAM database.

- Go to the “Attachments/Links” section to download the solicitation and all technical documents.

Sign-Up and Sign-In to your SAM account to:

- “Follow” to receive email notifications (i.e., amendments)

- View Interested Vendors List

- Sign up as an Interested Vendor

Requirements to Submit Proposals:

Register your business entity (you as an individual or your organization) to be able to propose on contracts as the Prime.

All proposals will be submitted through the PIEE Solicitation Module on time. Therefore, offerors must register in advance for a user ID and Password to access this system.

The projects will be Design-Build (D-B) Request for Proposals (RFP).

The solicitations are Total Small Business Set-Aside procurements

Project award will be made via a Two-Phase “Best Value Trade-off” basis as described in the evaluation criteria.

Proposals must be submitted on time.

The Louisville District is located within the Eastern time zone.

The Source Selection Evaluation Board (SSEB) will evaluate offerors’ proposals based on specific factors which are defined in the RFP Package.

THE PROCUREMENT PROCESS

New Cumberland Solicitation will be W912QR25NEWCUMBERLAND Newtown Square Solicitation will be W912QR25RA019

Source Selection Evaluation Criteria for the “Best Value Trade-Off” consists of the following elements for Phase I:

1) Volume I – Factor I: Past Performance Evaluation Project(s) submitted for both Prime Contractor and A/E Designer of Record (maximum 3 each) Relevancy - Recent projects, similar in size, scope, magnitude of effort & complexities Quality of performance on submitted projects Other sources of relevant past performance information (i.e., CPARS, FAPIIS, eSRS)

Volume I – Factor II: Technical Approach for Design-Build (i.e., Collaboration, Organization, Quality Control)

PROPOSAL REQUIREMENTS

Technical Evaluation Factors

Source Selection Evaluation Criteria for a “Best Value Trade-Off” consists of the following elements Phase I:

3) Volume II – Pro Forma & Price Information Tab A: Standard Form 1442 (Price is not included in Phase I) Tab B: Joint Venture Agreements (if applicable) Tab C: Evidence of Ability to Obtain Bonding & Proof of Financial Ability Tab D: Pre-Award Information (i.e., Reps & Certs, offeror information, etc.)

Offerors selected as among the most highly qualified will be invited to participate in Phase II.

Phase II will be issued as an Amendment.

Submission Requirements and Source Selection Evaluation Criteria will be issued as a DRAFT during Phase I, subject to change w/the Phase II Amendment.

Information for an Optional Site Visit provided.

Source Selection Evaluation Criteria for the “Best Value Trade-Off” consists of the following elements for Phase II (subject to change):

1) Volume I – Factor I: Design Narrative

Volume I – Factor II: Management Plan

Volume I – Factor III: Schedule Narrative

Technical Evaluation Factors

Source Selection Evaluation Criteria for a “Best Value Trade-Off” consists of the following element(s) for Phase II:

4) Volume II – Pro Forma & Price Information Tab A: Standard Form 1442 & Price

Technical Factors listed in relative order of importance for Phase I:

Volume I – Factor I: Past Performance1st
Prime ContractorEqual to A/E (DOR)
A/E Designer of Record (DOR)Equal to Prime

Volume I – Factor II: Technical Approach for D/B 2nd

The ratings from Phase I will not be considered in Phase II for the final selection.

Technical Factors listed in relative order of importance for Phase II:

Volume I – Factor I: Design NarrativeEqual to Factors II & III
Volume I – Factor II: Management PlanEqual to Factors I & III
Volume I – Factor III: Schedule NarrativeEqual to Factors I & II

All Technical Evaluation Factors, other than Price, when combined are considered approximately equal to Price.

Submit your best proposal the 1st time. If we receive an initial proposal that is awardable, discussions may not be opened.

Instructions for submitting a Request for Information (RFI) will be included in the Solicitation.

RFIs for these projects will be received and answered through the ProjNet system: www.ProjNet.org

Any RFIs submitted/emailed directly to the Project Team will NOT receive a response, and offerors will be directed to the ProjNet system.

A ProjNet Bidder’s Key included in the solicitation’s Project Instructions section of the RFP, which is used to post your RFIs/questions.

RFIs and their responses will be available for public review through ProjNet.

Optional Site Visit held to familiarize Offerors with the jobsite and conditions, not for the purposes of answering questions.

We will utilize the Electronic Receipt of Proposal process – Instructions will be in Section 00 21 00 of the solicitation package

Proposals are uploaded to and submitted through PIEE Solicitation Module Recommend performing a test run well in advance

Don’t wait until the last minute to upload your proposal. Late is Late! No exceptions!

Proposal submission

PROCUREMENT SCHEDULE

Dates are approximate AND SUBJECT TO CHANGE ISSUE SOLICIATION (PHASE I) March/April 2025

PHASE I – SOLICITATION CLOSES April/May 2025

PHASE I – EVALUATION BOARD May 2025

PHASE II – AMENDMENT ISSUED JULY 2025

PHASE II – SOLICITATION CLOSES AUGUST 2025

PHASE II – EVALUATION BOARD SEPTEMBER 2025

AWARD SEPTEMBER 2025

Crystal Harbin Deputy for Small Business

SBO-LRL@usace.army.mil

Courtney Luckett Small Business Professional

Small Business Participation plan & Subcontracting PLAN The Small Business Participation Plan is a rated evaluation factor in all unrestricted procurements Both large and small business offerors must submit a participation plan.

The participation plan is based on total contract value.

The Small Business Participation Plan must meet the minimum Total Small Business Participation goal. The percentage will be included the solicitation.

Small Business prime self-performance counts as Small Business Participation.

Large Business offerors must submit a Small Business Subcontracting Plan Mandated by FAR 19.702 This is not a rated element as a part of the Source Selection process but the offeror shall submit an acceptable plan prior to award The subcontracting plan is based on total subcontracted dollars Failure to comply in good faith is in material breach of the contract

Obtain information Attend Site Visits, Pre-Proposal Conferences, & Industry Days Obtain copies of attendee roster for subcontracting opportunities

Register as an Interested Vendor on SAM

Attend Workshops and Conferences

Louisville District Networking: Tentatively 29 July 2025

Construction & IDIQ Forecast is maintained on the Business with Us page of the Great Lakes and Ohio River Division website, https://www.lrd.usace.army.mil/Opportunity-Forecast/ opportunities We anticipate executing approximately $1.3B in FY25 through both small and large businesses.

Contracting opportunities are posted in the System for Award Management (SAM) website at www.sam.gov. Use “W912QR” to search for Louisville District projects.

Actively Respond to Sources Sought Notices (Market Surveys) posted to SAM

Actively Respond to Competitive Requirements posted to SAM

New Cumberland Arc Overview

Jonathan Cowen Project Manager

Felix Carrion-Viera Project Engineer U.S. Army Corps of Engineers - Louisville District

Project Information:

Description-This project will repair an existing 28,989 square feet Army Reserve Center, Training Building 315, that is in a failed or failing condition. Constructed in July 1992, building 315 provides mission essential functional areas in support of USAR units. The repairs will provide the necessary operational building functional areas for the training and mission support of these commands. The mechanical, plumbing and electrical systems are beyond serviceable life. A technical review will be conducted, work classification verified, and other facility alternatives were visited but the most expedient and best option was to repair the listed facility. This project is required right now, because the present condition of the facility has extensive Life Safety issues and inadequate power and cooling which has a negative impact on the operations mission and the health of Soldiers.

Project Delivery Method - Design/Bid/Build Procurement Method- Best Value Trade Off SSEB Estimated Construction Duration - 1100 days Stakeholder- 99th Readiness Division and ARIMD Scheduled Milestones (estimates for planning):

Advertise Period – JUN-JUL 2025 Source Selection Evaluation Board – JUL 2025 Discussions (if needed) – AUG 2025 Contract Award – AUG 2025 Admin NTP – SEP 2025 Construction NTP – OCT 2025 Construction Completion – APR 2028

New Cumberland ARC

New Cumberland arc DLA Distribution Center Susquehanna, PA 40.21182364094431, -76.83435547365774

New Cumberland site plan

New Cumberland Army reserve Center

New Cumberland main floor

New Cumberland lower floor

Project Information:

Description- This project will repair the failing 38,987 square feet Edgemont Army Reserve Center (ARC) Building 92001 located on approximately 45 acres in Newtown Square, PA. This facility was constructed in 1976 to provide mission essential training and operational capabilities supporting USAR units. This project is required now due to the present conditions of the facility which include extensive life safety issues and inadequate power and cooling which has a negative impact on the health and mission of assigned personnel. Much of the infrastructure is over 46 years old and requires replacement to ensure continuous mission operation. If not corrected in this project, temporary repairs will continue to be costly and conditions in the facility will continue to degrade.

Project Delivery Method - Design/Bid/Build Procurement Method- Best Value Trade Off SSEB Estimated Construction Duration - 1100 days Stakeholder- 99th Readiness Division and ARIMD Scheduled Milestones (estimates for planning):

Advertise Period – JUN-JUL 2025 Source Selection Evaluation Board – JUL 2025 Discussions (if needed) – AUG 2025 Contract Award – AUG 2025 Admin NTP – SEP 2025 Construction NTP – OCT 2025 Construction Completion – APR 2028

Newtown square ARC

Newtown square arc 2101 Delchester Rd. Newtown Square PA 19073

Newtown square site plan

Newtown square Army reserve Center

Newtown square 1st floor

Newtown square 2nd floor

Register SAM.gov to obtain and respond to solicitations

Source Selection Evaluation Criteria are basis for selection by source evaluation boards

Unrestricted solicitations require small business participation plan

New Cumberland project is scheduled for bids due in:

November 2024 via Solicitation W912QR-24-R-0077

Newtown Square project is scheduled for bids due in:

November 2024 via Solicitation W912QR-24-R-0077

SUMMARY

What Questions do you have for us?

This power point presentation will be posted to FBO and will be linked to the industry day announcement. It will be available for download for 15 days.

image3.png image4.png image11.png image12.png image13.png image14.png image15.png image16.png image17.png image18.png image19.jpg image20.emf oleObject1.bin image21.emf image22.png image23.png image24.emf image25.png image26.png image27.png image28.png image29.emf image30.png image31.png image1.png image8.png image9.png image2.png image5.png image6.png

File details come from the government source that posted it. Updated .