W912QR24R0022_Specs-0001.pdf
PDF 918 KB Posted
- Solicitation number
- W912QR24R0022
About this file
This document is an amendment to Solicitation W912QR24R0022 for the Design-Bid-Build construction of a Military Equipment Parking (MEP) area located in Cedar Rapids, IA. The solicitation is for a Firm-Fixed-Price contract with an anticipated construction value between $5,000,000 and $10,000,000. The scope includes land clearing, paving, fencing, general site improvements, and utility connections to convert an undeveloped site into approximately 9,200 square yards of fenced and lighted military vehicle parking. This is an unrestricted full and open procurement with a single-phase source selection process evaluating past performance, technical factors, and price. The solicitation amendment extends the proposal due date from April 8, 2024 to April 15, 2024 and provides updates to certain specification sections and drawings. All other terms and conditions remain unchanged.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912QR24R0022_Plans-0001.pdf | ||
| W912QR24R0022_Specs-0000.pdf | ||
| W912QR24R0022_Plans-0000.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Solicitation W912QR24R0022 for the Construction of a Military Equipment Parking (MEP) Lot at Cedar Rapids, IA is hereby amended as follows:
Please see attached Summary of Changes AMDT 0001.
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912QR24R0022
X 9B. DATED (SEE ITEM 11)
06-Mar-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
04 Apr-2024
CODE
U. S. ARMY ENGINEER DISTRICT, LOUISVILLE
600 DR. MARTIN LUTHER KING, JR. PLACE
ROOM 821
LOUISVILLE KY 40202-2239
W912QR 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912QR24R0022_Specs-0001
W912QR24R0022
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
The following have been added by full text:
SUMMARY OF CHANGES AMDT 0001
1. The following SPECIFICATION SECTIONS have been replaced in their entirety:
01 35 26.00 06 GOVERNMENT SAFETY REQUIREMENTS
32 01 19.61
32 11 20
SEALING OF JOINTS IN RIGID PAVEMENT
BASE COURSE FOR RIGID
32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND
SITE FACILITIES
2. The following PLAN SHEETS have been replaced in their entirety:
C-501
C-505
CIVIL DETAILS
CIVIL DETAILS
3. The proposal due date is hereby extended from 08 April 2024 at 12:00 PM ET to 15 April 2024 at 12:00
PM ET.
4. All other terms and conditions remain unchanged.
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 08-Apr-2024 12:00 PM to 15-Apr-2024 12:00 PM.
(End of Summary of Changes)
P2 503171 MEP Expansion Cedar Rapids AFRC, IA
SECTION 01 35 26.00 06
GOVERNMENT SAFETY REQUIREMENTS
05/19
Amendment 0001
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)
ASSP A10.32 (2012) Fall Protection
ASSP A10.34 (2001; R 2012) Protection of the Public on or Adjacent to Construction Sites
ASSP Z359.1 (2016) The Fall Protection Code
ASME INTERNATIONAL (ASME)
ASME B30.22 (2016) Articulating Boom Cranes
ASME B30.3 (2016) Tower Cranes
ASME B30.5 (2018) Mobile and Locomotive Cranes
ASME B30.8 (2015) Floating Cranes and Floating Derricks
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 10 (2018; TIA 18-1) Standard for Portable Fire Extinguishers
NFPA 241 (2019) Standard for Safeguarding Construction, Alteration, and Demolition Operations
NFPA 51B (2019) Standard for Fire Prevention During Welding, Cutting, and Other Hot Work
NFPA 70 (2017; ERTA 1-2 2017; TIA 17-1; TIA 17-2;
TIA 17-3; TIA 17-4; TIA 17-5; TIA 17-6;
TIA 17-7; TIA 17-8; TIA 17-9; TIA 17-10;
TIA 17-11; TIA 17-12; TIA 17-13; TIA
17-14; TIA 17-15; TIA 17-16; TIA 17-17 )
National Electrical Code
NFPA 70E (2018; TIA 18-1; TIA 81-2) Standard for Electrical Safety in the Workplace
SECTION 01 35 26.00 06 Page 1 Certified Final Design Submittal
AMENDMENT 0001
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910 Occupational Safety and Health Standards
29 CFR 1915 Confined and Enclosed Spaces and Other Dangerous Atmospheres in Shipyard Employment
29 CFR 1926 Safety and Health Regulations for Construction
29 CFR 1926.500 Fall Protection
1.2 SUBMITTALS
Government approval/acceptance is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with LRL Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Accident Prevention Plan (APP) Fatigue Management Plan Bloodborne Pathogen Plan Exposure Control Plan Automatic External Defibrillator (AED) Program Site Layout Plan
Access/Haul Road Plan Hearing Conservation Program Respiratory Protection Plan Health Hazard Control Program Hazard Communication Program
Process Safety Management Plan Lead Compliance Plan & Specifications Asbestos Abatement Plan & Specifications Radiation Safety Program Abrasive Blasting Plan
Heat Stress Monitoring Plan Cold Stress Monitoring Plan Indoor Air Quality Management Plan Mold Remediation Plan Chromium (VI) Exposure Evaluation
Crystalline Silica Assessment Lighting Plan for Night Operations Traffic Control Plan Fire Prevention Plan Wild Land Fire Management Plan
SECTION 01 35 26.00 06 Page 2 Certified Final Design Submittal
Arc Flash Hazard Analysis Assured Equipment Grounding Control Program (AEGCP) Hazardous Energy Control Plan Standard Pre-Lift Plan (LHE) Critical Lift Plan - LHE
Naval Architectural Analysis-LHE (Floating) Floating Plant Inspection and Certification Severe Weather Plan for Marine Activities Emergency Plan for Marine Activities Man Overboard/Abandon Ship Procedures
Float Plan for Launches, Motorboats, Skiffs Fall Protection and Prevention Plan Demolition/Renovation Plan (to include engineering survey) Rope Access Work Plan Excavation/Trenching Plan
Compressed Air Plan for Underground Construction Erection and Removal Plan for Formwork and Shoring PreCast Concrete Plan Lift-Slab Plans
Masonry Bracing Plan Steel Erection Plan Explosives Safety Site Plan (ESSP) Blasting Plan Dive Operations Plan
Safe Practices Manual for Diving Activities Emergency Management Plan for Diving Tree Felling/Maintenance Program Aircraft/Airfield Construction Safety & Phasing Plan (CSPP) Aircraft/Airfield Safety Plan Compliance Document (SPCD)
Site Safety and Health Plan (HTRW) Confined Space Entry Procedures Confined Space Program
Activity Hazard Analysis (AHA); G, RO
Site Safety and Health Officer Qualifications(SSHO); G, RO
Proof of qualification for Crane Operators; G, RO
Critical Lift Plan; G, RO
SD-06 Test Reports
Reports
Submit reports as their incidence occurs, in accordance with the requirements of the paragraph entitled, "Reports."
Accident Reports
Monthly Exposure Reports
SECTION 01 35 26.00 06 Page 3 Certified Final Design Submittal
Crane Reports
Regulatory Citations and Violations
SD-07 Certificates
Confined Space Entry Permit
Hot work permit
Crane Certificate of Compliance
Submit one copy of each permit/certificate attached to each daily Quality Control Report.
1.3 DEFINITIONS
a. Site Safety and Health Officer (SSHO). The qualified or competent person who is responsible for the on-site safety and health management required for the contract project work.
b. Competent Person, Fall Protection: A person designated in writing by the employer to be responsible for immediate supervising, implementing and monitoring of the fall protection program, who through training, knowledge and experience in fall protection and rescue systems and equipment, is capable of identifying, evaluating and addressing existing and potential fall hazards and, who has the authority to take prompt corrective measures with regard to such hazards.
c. High Visibility Accident. Any mishap which may generate publicity and/or high visibility.
d. Medical Treatment. Treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even through provided by a physician or registered personnel.
e. Qualified Person, Fall Protection: A person with a recognized degree or professional certificate and with extensive knowledge, training and experience in the fall protection and rescue field who is capable of designing, analyzing, evaluating and specifying fall protection and rescue systems; shall have an advanced understanding of the regulatory requirements, physical sciences and engineering principles that affect equipment and systems for FP and rescue; be able to calculate forces generated by an arrested fall, the total loading and the deflection of the fall arrest anchorage, the impact on the structural members to which the fall arrest system is attached and shall be able to determine safe locations of anchorages; shall supervise the design, selection, installation and inspection of certified anchorages and horizontal lifelines.
f. Recordable Injuries or Illnesses. Any work-related injury or illness that results in:
(1) Death, regardless of the time between the injury and death, or the length of the illness;
(2) Days away from work (any time lost after day of
SECTION 01 35 26.00 06 Page 4 Certified Final Design Submittal injury/illness onset);
(3) Fatal injury / illness;
(4) Permanent totally disabling injury/illness;
(5) Permanent partial disabling injury/illness;
(6) One(1) or more persons hospitalized as inpatients as a result of a single occurrence
(7) $500,000 or greater accidental property damage
(8) Three(3) or more individuals become ill or have a medical condition which is suspected to be related to a site condition, or a hazardous or toxic agent on the site.
(9) Restricted work;
(10) Transfer to another job;
(11) Medical treatment beyond first aid;
(12) Loss of consciousness; or
(13) A significant injury or illness diagnosed by a physician or other licensed health care professional, even if it did not result in (1) through (13) above.
g. "USACE" property and equipment specified in USACE EM 385-1-1 should be interpreted as Government property and equipment.
h. Weight Handling Equipment (WHE) Accident. A WHE accident occurs when any one or more of the six elements in the operating envelope fails to perform correctly during operation, including operation during maintenance or testing resulting in personnel injury or death;
material or equipment damage; dropped load; derailment; two-blocking;
overload; and/or collision, including unplanned contact between the load, crane, and/or other objects. A dropped load, derailment, two-blocking, overload and collision are considered accidents even though no material damage or injury occurs. A component failure (e.g., motor burnout, gear tooth failure, bearing failure) is not considered an accident solely due to material or equipment damage unless the component failure results in damage to other components (e.g., dropped boom, dropped load, roll over, etc.).
i. Low-slope roof. A roof having a slope less than or equal to 4 in 12 (vertical to horizontal).
j. Steep roof. A roof having a slope greater than 4 in 12 (vertical to horizontal).
k. Certified Safety Professional/Certified Industrial Hygienist Qualifications
(1) Certified Construction Health & Safety Technician (CHST). An individual who is currently certified by the Board of Certified Safety Professionals.
SECTION 01 35 26.00 06 Page 5 Certified Final Design Submittal
(2) Certified Industrial Hygienist (CIH). An individual who is currently certified by the American Board of Industrial Hygiene.
(3) Certified Safety Professional (CSP). An individual who is currently certified by the Board of Certified Safety Professionals.
(4) Certified Safety Trained Supervisor (STS). An individual who is currently certified by the Board of Certified Safety Professionals.
(5) Associate Safety Professional (ASP). An individual who is currently certified by the Board of Certified Safety Professionals.
1.4 REGULATORY REQUIREMENTS
In addition to the detailed requirements included in the provisions of this contract, work performed shall comply with USACE EM 385-1-1 , federal, state, local, host nation laws, ordinances, criteria, rules and regulations. Submit matters of interpretation of standards to the appropriate administrative agency for resolution before starting work.
Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements shall apply.
1.5 SITE QUALIFICATIONS, DUTIES AND MEETINGS
1.5.1 Personnel Qualifications
Amendment 0001***************************************************************
1.5.1.1 Site Safety and Health Officer Qualifications(SSHO)
a.) A Site Safety and Health Officer (SSHO)and alternate(s) shall be provided at the work site at all times and shall be a member of the onsite work organization and be responsible for overall management of the safety and occupational health program. The SSHO shall have the authority to act in all safety matters for the Contractor at all times to perform safety and occupational health management, surveillance, inspections, and safety enforcement for the Contractor. The SSHO and alternate(s) shall be employed by the Prime Contractor and shall report to a corporate safety official or other corporate official not engaged in quality control or supervision.
The SSHO shall be:
assigned as the SSHO, but shall not be the Superintendent .
b.) The SSHO and alternate(s)shall have an experience Level as follows and the Contractor must show evidence that the SSHO and alternate(s) have met these requirements. When an alternate is required for the project, the alternate shall have the same experience level and other qualifications as the SSHO. In addition, the SSHO and alternate(s) are also required to have:
(1) Completed, as a minimum, the 30-Hour OSHA Construction Industry safety class with current First Aid and CPR Training / AED.
(2) Either a person with 10 years of demonstratable SSHO experience on similar projects or a College graduate with Five (5) years of Construction
SECTION 01 35 26.00 06 Page 6 Certified Final Design Submittal
Industry safety experience on similar projects in supervising or managing general or industry construction (managing safety programs or processes or conducting hazard analyses and developing controls).
(3) Maintained experience through having taken 24 hours of documented formal or on-line safety and health related coursework in the past three years. The training must be applicable to the work being performed on the contract. Teaching is not considered the equivalent of attending training.
(4) SSHO shall be able to demonstrate training in the following areas:
personal protective equipment and clothing to include selection, use and maintenance; hazard communication; excavation; scaffolding; fall protection;
health hazard recognition, evaluation and control of chemical, physical and biological agents.
c.) To insure that safety and health conditions are maintained/enforced at all times, and a SSHO is present at all times, the Contractor shall designate one or more alternates to perform the safety and health requirements stated herein to cover any period when the SSHO cannot be present, such as during absences for vacations/extended sickness, or when there are multiple shifts that requires additional coverage. The alternate(s) shall have the same qualifications/training/ education requirements as the SSHO.
d.) The Contractor shall identify the SSHO and alternate(s)for this project and shall submit qualifications to the Government in resume form for acceptance. A copy of the letter to the SSHO and alternate(s) signed by an authorized official of the firm describing responsibilities and delegating authority to stop work when safety or occupational health of workers is compromised must be provided to the Government.
e.) Acceptance of the Contractor's SSHO and alternate(s) is required prior to the start of construction. Acceptance is conditional and will be predicated on satisfactory performance during construction. The Government reserves the right to require the Contractor to make changes to operations including removal of personnel, as necessary, to obtain a safe work site. At no time will the job be permitted to operate without a SSHO on duty at the work site.
f.) Duties of the SSHO shall include, as a minimum, the following in addition to the duties now listed per other paragraphs of this Section:
(1) Prepare the Contractor's Safety Plan, and Activity Hazard Analysis for each definable feature of work;
(2) Provide safety indoctrination to all construction site visitors;
(3) Ensure the Contractor's accepted Accident Prevention Plan is carried out;
(4) Ensure that all Contractor/subcontractor employees have all HTRW, asbestos, and lead paint training, and their personnel protection equipment meets applicable OSHA/EPA and EM 385-1-1 requirements;
(5) Conducts daily walk through of the site ensuring work is being accomplished safely and occupational health is not compromised;
(6) Attend and participate in all preparatory and initial quality control phase meetings;
SECTION 01 35 26.00 06 Page 7 Certified Final Design Submittal
(7) Conduct weekly safety meetings for all workers;
(8) Conduct monthly supervisory safety meetings;
(9) Provide accident reports;
(10)Produce a Daily Safety Report of activities performed and attach this report to the Contractor's Quality Control Report.
(11)Provide minutes for weekly and monthly safety meetings, minutes to be attached with the Daily Safety Report.
***************************************************************Amendment 0001
1.5.2 Personnel Duties
1.5.2.1 Site Safety and Health Officer (SSHO)
a. Conduct daily safety and health inspections and maintain a written log which includes area/operation inspected, date of inspection, identified hazards, recommended corrective actions, estimated and actual dates of corrections. Safety inspection logs shall be attached to the Contractors' daily quality control report.
b. Conduct mishap investigations and complete required reports.
Maintain the OSHA Form 300 for prime contractor.
c. Maintain applicable safety reference material on the job site.
d. Attend the pre-construction conference, pre-work safety conference, pre-work meetings including preparatory inspection meeting, and periodic in-progress meetings.
e. Implement and enforce accepted APPS and AHAs.
f. Maintain a safety and health deficiency tracking system that monitors outstanding deficiencies until resolution. A list of unresolved safety and health deficiencies shall be posted on the safety bulletin board.
g. Ensure sub-contractor compliance with safety and health requirements.
h. Other duties as identified per LRL Section 01 45 04.10 06 Contractor Quality Control. Failure to perform the above duties shall result in dismissal of the SSHO, and/or CQC System Manager, and/or superintendent and a project work stoppage. The project work stoppage will remain in effect pending approval of a suitable replacement.
1.5.3 Meetings
1.5.3.1 Prework Safety Conference
a. Contractor representatives who have a responsibility or significant role in accident prevention on the project shall attend the prework safety conference. The purpose of the prework safety conference is for the Contractor and the Contracting Officer's representatives to become acquainted and explain the functions and operating procedures of their
SECTION 01 35 26.00 06 Page 8 Certified Final Design Submittal respective organizations and to reach mutual understanding relative to the administration of the overall project's APP before the initiation of work.
This includes the project superintendent, Site Safety and Health Officer, Quality Control System Manager, or any other assigned safety and health professionals who participated in the development of the APP (including the Activity Hazard Analyses (AHAs) and special plans, program and procedures associated with it).
b. The Contractor shall discuss the details of the submitted APP to include incorporated plans, programs, procedures and a listing of anticipated AHAs that will be developed and implemented during the performance of the contract. This list of proposed AHAs will be reviewed at the conference and an agreement will be reached between the Contractor and the Contracting Officer's representative as to which phases will require an analysis. In addition, a schedule for the preparation, submittal, review, and acceptance of AHAs shall be established to preclude project delays.
c. Deficiencies in the submitted APP will be brought to the attention of the Contractor at the prework safety conference, and the Contractor shall revise the plan to correct deficiencies and re-submit it for acceptance.
Work shall not begin until there is an accepted APP.
d. The functions of a prework safety conference, may take place at the Post-Award Kickoff meeting for Design Build Contracts.
1.5.3.2 Weekly Safety Meetings
Shall be conducted and documented as required by EM 385-1-1 . Minutes showing contract title, signatures of attendees and a list of topics discussed shall be attached to the Contractors' daily quality control report.
1.5.3.3 Work Phase Meetings
The appropriate AHA shall be reviewed and attendance documented by the Contractor at the preparatory, initial, and follow-up control phases of quality control inspection in accordance with LRL Section 01 45 04.10 06 CONTRACTOR QUALITY CONTROL. The analysis should be used during daily inspections to ensure the implementation and effectiveness of safety and health controls; and the results reported on the daily QC Report.
1.6 TRAINING
1.6.1 New Employee Indoctrination
New employees (prime and sub-contractor) will be informed of specific site hazards before they begin work. Documentation of this orientation shall be kept on file at the project site.
1.6.2 Periodic Training
Provide Safety and Health Training in accordance with USACE EM 385-1-1 and the accepted APP. Ensure all required training has been accomplished for all onsite employees.
1.6.3 Training on Activity Hazard Analysis (AHA)
Prior to beginning a new control phase, training will be provided to all
SECTION 01 35 26.00 06 Page 9 Certified Final Design Submittal affected employees to include a review of the AHA to be implemented.
1.7 ACCIDENT PREVENTION PLAN (APP)
a. The Contractor shall use a qualified person to prepare the written site-specific APP. Prepare the APP in accordance with the format and requirements of USACE EM 385-1-1 and as supplemented herein. Cover all paragraph and subparagraph elements in USACE EM 385-1-1 , Appendix A, "Minimum Basic Outline for Accident Prevention Plan". Specific requirements for some of the APP elements are described below. The APP shall be job-specific and shall address any unusual or unique aspects of the project or activity for which it is written. The APP shall interface with the Contractor's overall safety and health program. Any portions of the Contractor's overall safety and health program referenced in the APP shall be included in the applicable APP element and made site-specific.
The Government considers the Prime Contractor to be the "controlling authority" for all work site safety and health of the subcontractors.
Contractors are responsible for informing their subcontractors of the safety provisions under the terms of the contract and the penalties for noncompliance, coordinating the work to prevent one craft from interfering with or creating hazardous working conditions for other crafts, and inspecting subcontractor operations to ensure that accident prevention responsibilities are being carried out. The APP shall be signed per requirements of EM 385-1-1 , Appendix A-1, Paragraph 3, Signature Sheet.
Fatigue Management Plan Bloodborne Pathogen Plan Exposure Control Plan Automatic External Defibrillator (AED) Program Site Layout Plan
Access/Haul Road Plan Hearing Conservation Program Respiratory Protection Plan Health Hazard Control Program Hazard Communication Program
Process Safety Management Plan Lead Compliance Plan & Specifications Asbestos Abatement Plan & Specifications Radiation Safety Program Abrasive Blasting Plan
Heat Stress Monitoring Plan Cold Stress Monitoring Plan Indoor Air Quality Management Plan Mold Remediation Plan Chromium (VI) Exposure Evaluation
Crystalline Silica Assessment Lighting Plan for Night Operations Traffic Control Plan Fire Prevention Plan Wild Land Fire Management Plan
Arc Flash Hazard Analysis Assured Equipment Grounding Control Program (AEGCP) Hazardous Energy Control Plan Standard Pre-Lift Plan (LHE)
SECTION 01 35 26.00 06 Page 10 Certified Final Design Submittal
Critical Lift Plan - LHE
Naval Architectural Analysis-LHE (Floating) Floating Plant Inspection and Certification Severe Weather Plan for Marine Activities Emergency Plan for Marine Activities Man Overboard/Abandon Ship Procedures
Float Plan for Launches, Motorboats, Skiffs Fall Protection and Prevention Plan Demolition/Renovation Plan (to include engineering survey) Rope Access Work Plan Excavation/Trenching Plan
Compressed Air Plan for Underground Construction Erection and Removal Plan for Formwork and Shoring PreCast Concrete Plan Lift-Slab Plans
Masonry Bracing Plan Steel Erection Plan Explosives Safety Site Plan (ESSP) Blasting Plan Dive Operations Plan
Safe Practices Manual for Diving Activities Emergency Management Plan for Diving Tree Felling/Maintenance Program Aircraft/Airfield Construction Safety & Phasing Plan (CSPP) Aircraft/Airfield Safety Plan Compliance Document (SPCD)
Site Safety and Health Plan (HTRW) Confined Space Entry Procedures Confined Space Program
b. Submit the APP to the Contracting Officer 15 calendar days prior to the date of the prework safety conference for acceptance. Work cannot proceed without an accepted APP. The Contracting Officer reviews and comments on the Contractor's submitted APP and accepts it when it meets the requirements of the contract provisions.
c. Acceptance is conditional and will be predicated on satisfactory performance during the construction. Once accepted by the Contracting Officer, the APP and attachments will be enforced as part of the contract.
Disregarding the provisions of this contract or the accepted APP will be cause for stopping of work, at the discretion of the Contracting Officer, until the matter has been rectified. Work cannot proceed without an accepted APP.
d. Once work begins, changes to the accepted APP shall be made with the knowledge and concurrence of the Contracting Officer, project superintendent, SSHO and Construction Quality Control System Manager.
Should any hazard become evident, stop work in the area, and secure the area. The project superintendent shall inform/notify the Contracting Officer within 12 hours of discovery, both verbally and in writing, and develop a plan for resolution as soon as possible to eliminate/ remove the hazard. In the interim, all necessary action shall be taken to restore and maintain safe working conditions in order to safeguard onsite personnel, visitors, the public (as defined by ASSP A10.34 ,) and the
SECTION 01 35 26.00 06 Page 11 Certified Final Design Submittal environment.
e. Copies of the accepted plan will be maintained at the Resident Engineer's office and at the contractor's job site office.
f. The APP shall be continuously reviewed and amended, as necessary, throughout the life of the contract. Unusual or high-hazard activities not identified in the original APP shall be incorporated in the plan as they are discovered.
1.8 ACTIVITY HAZARD ANALYSIS (AHA)
a) The Activity Hazard Analysis (AHA) format shall be in accordance with USACE EM 385-1-1 as modified by the Louisville District, using CELRL Form 1259, current edition. Submit the AHA for review at least 15 calendar days prior to the start of each phase. Format subsequent AHAs as amendments to the APP.
b)An AHA will be developed by the Contractor for every operation involving a type of work presenting hazards not experienced in previous project operations or where a new work crew or subcontractor is to perform work.
In addition, AHA's are needed using the project schedule as the basis for the activities performed. Any activities listed on the project schedule will require an AHA. The AHA's will either be developed by the contractor, supplier or subcontractor and provided to the prime contractor for submittal to the Contracting Officer. The analysis must identify and evaluate hazards and outline the proposed methods and techniques for the safe completion of each phase of work. At a minimum, define activity being performed, sequence of work, specific safety and health hazards anticipated, control measures (to include personal protective equipment) to eliminate or reduce each hazard to acceptable levels, equipment to be used, inspection requirements, training requirements for all involved, and the competent person in charge of that phase of work. The analysis should be used during daily inspections to ensure the implementation and effectiveness of the activity's safety and health controls. For work with fall hazards, including fall hazards associated with scaffold erection and removal, identify the appropriate fall arrest systems. For work with materials handling equipment, address safeguarding measures related to materials handling equipment. For work requiring excavations, include requirements for safeguarding excavations.
c. The analysis should be used during daily inspections to ensure the implementation and effectiveness of the activity's safety and health controls.
d. The AHA list will be reviewed periodically (at least monthly) at the Contractor supervisory safety meeting and updated as necessary when procedures, scheduling, or hazards change.
e. Activity hazard analyses shall be updated as necessary to provide an effective response to changing work conditions and activities. The on-site superintendent, site safety and health officer and competent persons used to develop the AHAs, including updates, shall sign and date the AHAs before they are implemented.
f. The activity hazard analyses shall be developed using the project schedule as the basis for the activities performed. Any activities listed on the project schedule will require an AHA. The AHAs will be developed by the contractor, supplier or subcontractor and provided to the prime
SECTION 01 35 26.00 06 Page 12 Certified Final Design Submittal contractor for submittal to the Contracting Officer.
1.9 DISPLAY OF SAFETY INFORMATION
Within 1 calendar day after commencement of work, erect a safety bulletin board at the job site. The safety bulletin board shall include information and be maintained as required by EM 385-1-1 , Section 01.A.07.
1.10 SITE SAFETY REFERENCE MATERIALS
Maintain safety-related references applicable to the project, including those listed in the article "References." Maintain applicable equipment manufacturer's manuals.
1.11 EMERGENCY MEDICAL TREATMENT
Contractors will arrange for their own emergency medical treatment.
Government has no responsibility to provide emergency medical treatment.
1.12 REPORTS
1.12.1 Accident Reports
a. For recordable injuries and illnesses, and property damage accidents resulting in at least $5,000 in damages, the Prime Contractor shall conduct an accident investigation to establish the root cause(s) of the accident, complete the USACE Accident Report Form 3394 and provide the report to the Contracting Officer within 5 calendar day(s) of the accident. The Contracting Officer will provide copies of any required or special forms.
1.12.2 Accident Notification
Notify the Contracting Officer as soon as practical, but not later than four hours, after any accident meeting the definition of Recordable Injuries or Illnesses or High Visibility Accidents, property damage equal to or greater than $5,000, or any weight handling equipment accident.
Information shall include contractor name; contract title; type of contract; name of activity, installation or location where accident occurred; date and time of accident; names of personnel injured; extent of property damage, if any; extent of injury, if known, and brief description of accident (to include type of construction equipment used, PPE used, etc.). Preserve the conditions and evidence on the accident site until the Government investigation team arrives on-site and Government investigation is conducted.
1.12.3 Monthly Exposure Reports
Monthly exposure reporting to the Contracting Officer is required to be attached to the monthly billing request. This report is a compilation of employee-hours worked each month for all site workers, both prime and subcontractor. The Contracting Officer will provide copies of any special forms.
1.12.4 Regulatory Citations and Violations
Contact the Contracting Officer immediately of any OSHA or other regulatory agency inspection or visit, and provide the Contracting Officer with a copy of each citation, report, and contractor response. Correct
SECTION 01 35 26.00 06 Page 13 Certified Final Design Submittal violations and citations promptly and provide written corrective actions to the Contracting Officer.
1.12.5 Crane Reports
Submit crane inspection reports required in accordance with USACE EM 385-1-1 and as specified herein with Daily Reports of Inspections.
1.12.6 Crane Certificate of Compliance
The Contractor shall provide a Certificate of Compliance for each crane entering an activity under this contract (see Contracting Officer for a blank certificate). Certificate shall state that the crane and rigging gear meet applicable OSHA regulations (with the Contractor citing which OSHA regulations are applicable, e.g., cranes used in construction, demolition, or maintenance shall comply with 29 CFR 1926 and USACE EM 385-1-1 Section 16. Certify on the Certificate of Compliance that the crane operator(s) is qualified and trained in the operation of the crane to be used. The Contractor shall also certify that all of its crane operators working on the DOD activity have been trained in the proper use of all safety devices (e.g., anti-two block devices). These certifications shall be posted on the crane.
1.12.7 Critical Lift Plan
Prior to performing Load Handling Equipment Critical Lifts, as identified in EM 385-1-1, a detailed Critical Lift Plan shall be developed and written by a competent person complying with all USACE requirements in EM 385-1-1. As part of the Critical Lift Plan, Proof of qualification for Crane Operators, lift supervisors and the rigger shall be submitted to the
GDA.
1.12.8 Confined Space Entry Permit
In accordance with 29 CFR 1910 , 29 CFR 1915 and EM 385-1-1, prior to entering a permit required confined space, a confined space entry permit shall be completed, reviewed, processed, signed and maintained. The entry supervisor or manager shall be required to sign all permits daily before entry.
1.13 HOT WORK PERMIT
Prior to performing "Hot Work" (welding, cutting, etc.) or operating other flame-producing/spark producing devices, a written Hot Work Permit shall be requested from the area, base, post or local fire district.
CONTRACTORS ARE REQUIRED TO MEET ALL CRITERIA BEFORE A PERMIT IS ISSUED.
The Contractor will provide at least two (2) twenty (20) pound 4A:20 BC rated extinguishers for normal "Hot Work". All extinguishers shall be current inspection tagged, approved safety pin and tamper resistant seal.
It is also mandatory to have a designated FIRE WATCH for any "Hot Work" done at this activity. The Fire Watch shall be trained in accordance with NFPA 51B and remain on-site for a minimum of 30 minutes after completion of the task or as specified on the hot work permit.
When starting work in the facility, Contractors shall require their personnel to familiarize themselves with the location of the nearest fire alarm boxes and place in memory the emergency Fire Division phone number.
ANY FIRE, NO MATTER HOW SMALL, SHALL BE REPORTED TO THE RESPONSIBLE FIRE
DIVISION IMMEDIATELY.
SECTION 01 35 26.00 06 Page 14 Certified Final Design Submittal
PART 2 PRODUCTS NOT USED
PART 3 EXECUTION
3.1 CONSTRUCTION AND/OR OTHER WORK
The Contractor shall comply with USACE EM 385-1-1 , NFPA 241 , the APP, the AHA, Federal and/or State OSHA regulations, and other related submittals and installation/activity fire and safety regulations. The most stringent standard shall prevail.
3.1.1 Hazardous Material Use
Each hazardous material must receive approval prior to being brought onto the job site or prior to any other use in connection with this contract.
Allow a minimum of 10 working days for processing of the request for use of a hazardous material.
3.1.2 Hazardous Material Exclusions
Notwithstanding any other hazardous material used in this contract, radioactive materials or instruments capable of producing ionizing/non-ionizing radiation (with the exception of radioactive material and devices used in accordance with USACE EM 385-1-1 such as nuclear density meters for compaction testing and laboratory equipment with radioactive sources) as well as materials which contain asbestos, mercury or polychlorinated biphenyls, di-isocynates, lead-based paint are prohibited. The Contracting Officer, upon written request by the Contractor, may consider exceptions to the use of any of the above excluded materials.
3.1.3 Unforeseen Hazardous Material
The design should have identified materials such as PCB, lead paint, and friable and non-friable asbestos. If material, not indicated, that may be hazardous to human health upon disturbance during construction operations is encountered, stop that portion of work and notify the Contracting Officer immediately. Within 14 calendar days the Government will determine if the material is hazardous. If material is not hazardous or poses no danger, the Government will direct the Contractor to proceed without change. If material is hazardous and handling of the material is necessary to accomplish the work, the Government will issue a modification pursuant to FAR 52.243-4 - Changes and FAR 52.236-2 - Differing Site Conditions.
3.2 PRE-OUTAGE COORDINATION MEETING
Contractors are required to apply for utility outages at least 15 days in advance. As a minimum, the request should include the location of the outage, utilities being affected, duration of outage and any necessary sketches. Special requirements for electrical outage requests are contained elsewhere in this specification section. Once approved, and prior to beginning work on the utility system requiring shut down, the Contractor shall attend a pre-outage coordination meeting with the Contracting Officer and the Installation representative to review the scope of work and the lock-out/tag-out procedures for worker protection.
No work will be performed on energized electrical circuits unless proof is provided that no other means exist.
SECTION 01 35 26.00 06 Page 15 Certified Final Design Submittal
3.3 FALL HAZARD PROTECTION AND PREVENTION PROGRAM
The Contractor shall establish a fall protection and prevention program, for the protection of all employees exposed to fall hazards. The program shall include company policy, identify responsibilities, education and training requirements, fall hazard identification, prevention and control measures, inspection, storage, care and maintenance of fall protection equipment and rescue and evacuation procedures.
3.3.1 Training
The Contractor shall institute a fall protection training program. As part of the Fall Hazard Protection and Prevention Program, the Contractor shall provide training for each employee who might be exposed to fall hazards. A competent person for fall protection shall provide the training. Training requirements shall be in accordance with USACE EM 385-1-1 , Section 21.C.
3.3.2 Fall Protection Equipment and Systems
The Contractor shall enforce use of the fall protection equipment and systems designated for each specific work activity in the Fall Protection and Prevention Plan and/or AHA at all times when an employee is exposed to a fall hazard or on a surface 6 feet or more above lower levels. Fall protection systems such as guardrails/toeboards, personnel fall arrest system, safety nets, etc., are required when working within 6 feet of any leading edge and employees shall be protected from fall hazards as specified in EM 385-1-1, Section 21. In addition to the required fall protection systems, safety skiff, personal floatation devices, life rings etc., are required when working above or next to water in accordance with USACE EM 385-1-1, Section 21. Personal fall arrest systems are required when working from an articulating or extendible boom, swing stages, or suspended platform. In addition, personal fall arrest systems are required when operating other equipment such as scissor lifts if the work platform is capable of being positioned outside the wheelbase. The need for tying-off in such equipment is to prevent ejection of the employee from the equipment during raising, lowering, or travel. Fall protection must comply with 29 CFR 1926.500 , Subpart M, USACE EM 385-1-1 and
ASSP A10.32 .
3.3.2.1 Personal Fall Arrest Equipment
Personal fall arrest equipment, systems, subsystems, and components shall meet ASSP Z359.1 . Only a full-body harness with a shock-absorbing lanyard or self-retracting lanyard is an acceptable personal fall arrest body support device. Body belts may only be used as a positioning device system (for uses such as steel reinforcing assembly and in addition to an approved fall arrest system). Harnesses shall have a fall arrest attachment affixed to the body support (usually a Dorsal D-ring) and specifically designated for attachment to the rest of the system. Only locking snap hooks and carabiners shall be used. Webbing, straps, and ropes shall be made of synthetic fiber. The maximum free fall distance when using fall arrest equipment shall not exceed (6 feet). The total fall distance and any swinging of the worker (pendulum-like motion) that can occur during a fall shall always be taken into consideration when attaching a person to a fall arrest system.
SECTION 01 35 26.00 06 Page 16 Certified Final Design Submittal
3.3.3 Fall Protection for Roofing Work
Fall protection controls shall be implemented based on the type of roof being constructed and work being performed. The roof area to be accessed shall be evaluated for its structural integrity including weight-bearing capabilities for the projected loading.
a. Low Sloped Roofs:
(1) For work within (6 feet) of an edge, on low-slope roofs, personnel shall be protected from falling by use of personal fall arrest systems, guardrails, or safety nets.
(2) For work greater than (6 feet) from an edge, warning lines shall be erected and installed in accordance with 29 CFR 1926.500 and USACE
EM 385-1-1 .
b. Steep-Sloped Roofs: Work on steep-sloped roofs requires a personal fall arrest system, guardrails with toe-boards, or safety nets. This requirement also includes residential or housing type construction.
3.3.4 Existing Anchorage
Existing anchorages, to be used for attachment of personal fall arrest equipment, shall be certified (or re-certified) by a qualified person for fall protection in accordance with ASSP Z359.1 . Exiting horizontal lifeline anchorages shall be certified (or re-certified) by a registered professional engineer with experience in designing horizontal lifeline systems.
3.3.5 Horizontal Lifelines
Horizontal lifelines shall be designed, installed, certified and used under the supervision of a qualified person for fall protection as part of a complete fall arrest system which maintains a safety factor of 2 (
29 CFR 1926.500 ).
3.3.6 Guardrails and Safety Nets
Guardrails and safety nets shall be designed, installed and used in accordance with EM 385-1-1 and 29 CFR 1926 Subpart M.
3.3.7 Rescue and Evacuation Procedures
When personal fall arrest systems are used, the contractor must ensure that the mishap victim can self-rescue or can be rescued promptly should a fall occur. A Rescue and Evacuation Plan shall be prepared by the contractor and include a detailed discussion of the following: methods of rescue; methods of self-rescue; equipment used; training requirement;
specialized training for the rescuers; procedures for requesting rescue and medical assistance; and transportation routes to a medical facility.
The Rescue and Evacuation Plan shall be included in the Activity Hazard Analysis (AHA) for the phase of work, in the Fall Protection and Prevention (FP&P) Plan and the Accident Prevention Plan (APP).
3.4 SCAFFOLDING
Employees shall be provided with a safe means of access to the work area on the scaffold. Climbing of any scaffold braces or supports not
SECTION 01 35 26.00 06 Page 17 Certified Final Design Submittal specifically designed for access is prohibited. Access to scaffold platforms greater than 6 (six) feet in height shall be accessed by use of a scaffold stair system. Vertical ladders commonly provided by scaffold system/tower manufacturers shall not be used for accessing scaffold platforms greater than 6 (six) feet in height. The use of an adequate gate is required. Contractor shall ensure that employees are qualified to perform scaffold erection and dismantling. Do not use scaffold without the capability of supporting at least four times the maximum intended load or without appropriate fall protection as delineated in the accepted fall protection and prevention plan. Stationary scaffolds must be attached to structural building components to safeguard against tipping forward or backward. Special care shall be given to ensure scaffold systems are not overloaded. Side brackets, used to extend scaffold platforms on self-supported scaffold systems for the storage of material is prohibited. The first tie-in shall be at the height equal to 4 times the width of the smallest dimension of the scaffold base. Work platforms shall be placed on mud sills. Scaffold or work platform erectors shall have fall protection during the erection and dismantling of scaffolding or work platforms that are more than 6 (six) feet. Delineate fall protection requirements when working above 6 (six) feet or above dangerous operations in the Fall Protection and Prevention (FP&P) Plan and Activity Hazard Analysis (AHA) for the phase of work.
3.4.1 Stilts
The use of stilts in conjunction with scaffolds is prohibited. Stilts shall not be used for gaining additional height for construction, renovation, repair or maintenance work; see EM 385-1-1 for types of scaffolds where this requirement applies.
3.5 EQUIPMENT
3.5.1 Material Handling Equipment
a. Material handling equipment such as forklifts shall not be modified with work platform attachments for supporting employees unless specifically delineated in the manufacturer's printed operating instructions.
b. The use of hooks on equipment for lifting of material must be in accordance with manufacturer's printed instructions.
c. Operators of forklifts or power industrial trucks shall be licensed in accordance with OSHA and EM 385-1-1.
3.6 Weight Handling Equipment
a. Cranes and derricks shall be equipped as specified in EM 385-1-1 , Section 16.
b. The Contractor shall notify the Contracting Officer 15 days in advance of any cranes entering the activity so that necessary quality assurance spot checks can be coordinated. Contractor's operator shall remain with the crane during the spot check.
c. The Contractor shall comply with the crane manufacturer's specifications and limitations for erection and operation of cranes and hoists used in support of the work. Erection shall be performed under the supervision of a designated person (as defined in ASME B30.5 ). All
SECTION 01 35 26.00 06 Page 18 Certified Final Design Submittal testing shall be performed in accordance with the manufacturer's recommended procedures.
d. The Contractor shall comply with ASME B30.5 for mobile and locomotive cranes, ASME B30.22 for articulating boom cranes, ASME B30.3 for construction tower cranes, and ASME B30.8 for floating cranes and floating derricks.
e. Under no circumstance shall a Contractor make a lift at or above 85% of the cranes rated capacity in any configuration.
f. When operating in the vicinity of…
This is the start of the file's text. The full file is on GovTribe.