W912QR24R0021_CF_Specs_Vol2-0002.pdf

PDF 17 MB Posted

Attached to
Design-Build Maintenance and Repair Army Reserves (MRAR) Fort Snelling B505
Solicitation number
W912QR24R0021
Issued by

About this file

This document appears to be Volume 2 of the Contract Specifications for Solicitation W912QR24R0021, which is a design-build solicitation for maintenance and repair of Army Reserve facilities at Fort Snelling, MN.

The key details are: Solicitation W912QR24R0021 is for the "Design-Build Maintenance and Repair Army Reserves (MRAR) Fort Snelling B505" project, issued by the Department of the Army Corps of Engineers, Engineering District Louisville. The solicitation is seeking proposals for the design and construction of maintenance and repair work on Army Reserve facilities at Fort Snelling. The contract type is not specified. No set-aside or pricing terms are provided. The document appears to be technical specifications for the required construction and repair work, but does not contain information on submission requirements, award dates, or other solicitation details.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation For Maintenance/Renovation Army Reserves (MRAR) Building 505, Fort Snelling, Minneapolis, MN

P2: 510375 Design-Build

Specifications Vol. 2 of 3

18 March 2024

W912QR24R0021

Phase 1

17 June 2024

W912QR24R0021-0002

Certified Final

ARIMS: 200A Disposition: Maintain for 15yrs after construction.

W912QR24R0021_CF_Specs_Vol2-0002

P2# 510375 - Repair Bldg. 505, USAR Center Ft Snelling, Minneapolis, MN

February 2020 version Table of Contents ToC - 1 of 3

CERTIFIED FINAL DESIGN SUBMITTAL

DESIGN/BUILD RFP FOR

Repair Bldg. 505, USAR Center

Fort Snelling, Minneapolis, MN

Table of Contents

SPECIFICATION VOLUME 1 of 3

Division 00 – Procurement and Contracting Requirements

00 10 00 Solicitation – [Offer and Award DF 1442], Price Breakout Schedule 00 21 00 Instructions 00 22 00 Supplementary Instructions

0011x Procedures for Submittal and Evaluation of Offers for Phase One

0011x Procedures for Submittal and Evaluation of Offers for Phase Two

0045 00 Representations and Certifications 00 70 00 Conditions of the Contract 00 73 00 Supplementary Conditions 00 80 00.00 06 Special Provisions Construction Project Signage Submittal Register

Division 01 – General Requirements Specifications

01 02 00.00 48 Statement of Work Table of Contents Part 1 Design Objectives, Functional and Area Requirements Part 2 Design Criteria and Coordination with Local Authorities Part 3 Site Civil Design Part 4 Site Electrical Design Part 5 Landscape Architecture Design Part 6 Architectural and Interior Design Part 7 Structural Design Part 8 Thermal Design Part 9 Plumbing Design Part 10 Electrical Design Part 11 HVAC Design Part 12 Energy Conservation and Sustainable Design Part 13 Fire Protection Design

Part 14 Commissioning and Building Envelope Sealing Performance Requirements

Part 15 Telecommunications Design

February 2020 version Table of Contents ToC - 2 of 3

CERTIFIED FINAL DESIGN SUBMITTAL

Attachment A Preliminary Subsurface Characterization Report Attachment B1 Fire Flow Data (Sloan Boulevard) Attachment B2 Fire Flow Data (Minnehaha Ave) Attachment C Site Photographs

Attachment D Room-by-Room Supplemental Requirements

Attachment E Airport Layout Plan

Attachment F1 Alta Survey Drawings 2005

Attachment F2 City of Minneapolis Utility Maps 2004

Attachment G Existing Building 505 Drawings

Attachment H 2020 Roof As-Built Drawings and Specifications

SPECIFICATION VOLUME 2 of 3

01 02 00.00 48 Attachments to the Statement of Work (continued)

Attachment I Review of Building Enclosure Fort Snelling Building

Attachment J Existing Building 506 Floor Plans

Attachment K1 Hazardous Building Materials and Radon Survey Report

Attachment K2 Asbestos and Lead Paint Inspection Summary

Attachment K3 Additional Radon Test Results Room113B

Attachment L 88th Readiness Division Interior Signage

Attachment M Federal Aviation Administration (FAA) 7460 Report

Attachment N Arms Vault Weapons Rack List (Redacted)

Attachment O UFGS Specification Section 02 41 00 ‘Demolition and

Deconstruction’ (to be edited by the DOR)

February 2020 version Table of Contents ToC - 3 of 3

CERTIFIED FINAL DESIGN SUBMITTAL

Attachment P UFGS Specification Section 02 82 00 ‘Asbestos

Remediation’ (to be edited by the DOR)

Attachment Q UFGS Specification Section 02 83 13.00 06 ‘Lead in

Attachment R UFGS Specification Section 09 67 23.13 ‘Standard Resinous

Flooring’

Attachment S Army Reserve Enterprise Building Control System (EBCS) Design Guide (October 2021)

Attachment T Existing Building 505-506 Connector Link Floor Plans

01 03 00.00 48 Design Submission Requirements After Award 01 04 00.00 48 The Design/Build Process 01 32 01.00 06 Project Schedule 01 33 00 Submittal Procedures 01 33 29.00 06 Sustainability Reporting

Attachment A - LEED Credit Guidance 01 35 26.00 06 Government Safety Requirements

01 42 00 Sources for Reference Publications 01 45 00.15 10 Resident Management System Contractor Mode (RMS CM) 01 45 04.10 06 Contractor Quality Control 01 45 35 Special Inspections 01 46 00.00 06 Total Building Commissioning (Contractor CxA) 01 50 00 Temporary Construction Facilities and Controls 01 57 19.00 Temporary Environmental Controls

01 74 19 Construction Waste Management and Disposal 01 78 23 Operation and Maintenance Data

SPECIFICATION VOLUME 3 of 3

Divisions 03-41 D/B RFP Outline Technical Specifications

See separate Table of Contents with Outline Technical Specifications.

P2 #510375 – Repair Bldg. 505, USAR Center Fort Snelling, Minneapolis, MN

Attachment ‘I’ 01 02 00.00 48

Section 01 02 00.00 48

ATTACHMENT I

REVIEW OF BUILDING ENCLOSURE – FT SNELLING, BUILDING 505

FEBRUARY 6TH, 2024

REVIEW OF BUILDING ENCLOSURE

FORT SNELLING, BUILDING 505

88 DIVISION ROAD, MINNEAPOLIS, MN 55111

23-13945-07

Prepared For:

Tim Grundtner

RSP Architects

1220 Marshall St NE

Minneapolis, MN 55413 tim.grundtner@rsparch.com

St. Paul, Minnesota

• BUILDING ENVELOPE CONSULTING • SPECIFICATIONS • DESIGN • QUALITY ASSURANCE OBSERVATION • TESTING •

Prepared By:

Mary Owen

Project Designer

RSI Building Envelope

2400 Prior Avenue North

St. Paul, MN 55113

Phone: 651-639-0644 www.rsi-be.com http://www.rsi-be.com/

Client: Tim Grundtner Project: Fort Snelling, Building 505

RSP Architects 88 Division Road, Minneapolis, MN 55111

Date: February 6th, 2024 RSI Project #: 23-13945-07 Page 2

All information is submitted as the confidential property of our clients. Any copies or extractions are reserved pending our written approval.

I. INTRODUCTION:

On November 30th, 2023, we were present at the above referenced facility to perform a review of the existing building enclosure:

In general, our scope of work was as follows:

A. Perform a visual review of the in-place exterior wall assembly;

B. Obtain photographs to substantiate our findings;

C. Based on the information obtained, develop a report as to the condition of the exterior wall assembly with conclusions and recommendations for repair and/or replacement.

Our work was requested and authorized by Tim Grundtner of RSP Architects, and authorized on site by Dan Nickols of Fort Snelling’s Facility Operations.

II. BACKGROUND INFORMATION:

Building 505 was constructed in 1977 (with as-built drawings dated 1983) at the North-East corner of the Minneapolis-St. Paul International Airport on what is now part of the Minneapolis-

St. Paul Joint Air Reserve Station of Fort Snelling. A small entry addition was added (date unknown) to the building after the initial construction. An enclosed connecting walkway was added at the time of construction for the adjacent building (506) for secure access between the two buildings.

The existing exterior wall assembly consists of exterior brick veneer, 1.5” expanded polystyrene insulation, and a CMU backup wall. There is flashing material present at the head and sill of each window (assumption based on test openings at 2 window conditions), but the wall assembly does not include a vapor barrier or coating of any kind.

Photograph A: Destructive test opening at sill condition at first floor window.

Photograph B: Destructive test opening at head condition at first floor window.

Date: February 6th, 2024 RSI Project #: 23-13945-07 Page 3

All information is submitted as the confidential property of our clients. Any copies or extractions are reserved pending our written approval.

III. FIELD OBSERVATIONS:

The following is a photographic summary of our field observations documenting the defects observed.

Specific defect locations are indicated on the attached elevations.

Bricks cracked and broken off at South-East building corner, possibly due to lawn maintenance equipment running into the building corner.

(Refer to Photograph #1)

Photograph #1

Evidence that a sign of some kind was previously hung at this location. Metal anchors were left in the mortar joint, which are rusting and causing discoloration of the brick.

(Refer to Photograph #2)

Photograph #2

Date: February 6th, 2024 RSI Project #: 23-13945-07 Page 4

All information is submitted as the confidential property of our clients. Any copies or extractions are reserved pending our written approval.

Efflorescence was found at most sill conditions throughout the building.

(Refer to Photographs #3 & #4)

Deformation of the steel lintel at window head conditions were common throughout the building.

(Refer to Photograph #3)

Photograph #3

Deterioration of the brick sill at the edges of the bricks and at mortar joints.

(Refer to Photograph #4)

Photograph #4

All vertical control joints throughout the building are cracking, delaminating, or have voids in the sealant.

(Refer to Photograph #5)

Photograph #5

Date: February 6th, 2024 RSI Project #: 23-13945-07 Page 5

All information is submitted as the confidential property of our clients. Any copies or extractions are reserved pending our written approval.

Voids were identified in the mortar joints at many sill locations.

(Refer to Photograph #6)

Photograph #6

Mortar joint is delaminating at head condition.

(Refer to Photograph #7)

Photograph #7

Steel lintels are rusting and deflecting at most window head locations.

(Refer to Photograph #8)

Photograph #8

Date: February 6th, 2024 RSI Project #: 23-13945-07 Page 6

All information is submitted as the confidential property of our clients. Any copies or extractions are reserved pending our written approval.

Evidence that a sign of some kind was previously hung at this location. Metal anchors were left in the mortar joint, which are rusting and causing discoloration of the brick.

(Refer to Photograph #9)

Photograph #9

Discoloration was seen in the mortar joints at and under many sill locations throughout the building.

(Refer to Photographs #10 & #11)

Photograph #10

Efflorescence was found at most sill conditions throughout the building. The new window sealant joint has begun to delaminate from the older brick sealant joint at the corner of the sill.

(Refer to Photograph #11)

Photograph #11

Date: February 6th, 2024 RSI Project #: 23-13945-07 Page 7

All information is submitted as the confidential property of our clients. Any copies or extractions are reserved pending our written approval.

Evidence of a masonry anchor of some kind was found under the coping cap at the entry addition, which damaged the brick either during its removal, addition, or created a hole for moisture infiltration and caused the area to spall.

(Refer to Photograph #12)

Photograph #12

Significant deflection of the brick sill was found at this particular West-facing upper floor window, deflecting both up towards the window assembly, and out proud of the exterior by approximately an inch. Sill bricks have cracked horizontally, and there is extensive deterioration of the mortar joints under the sill.

(Refer to Photograph #13)

Photograph #13

Interior photograph of the deflected sill seen above, showing cracking and delamination of the mortar joints at the sill. (Same window condition as shown in Photograph #13)

(Refer to Photograph #14)

Photograph #14

Date: February 6th, 2024 RSI Project #: 23-13945-07 Page 8

All information is submitted as the confidential property of our clients. Any copies or extractions are reserved pending our written approval.

Bricks cracked and broken off at building corner of the entry addition, possibly due to lawn maintenance equipment or plows running into the building corner.

(Refer to Photograph #15)

Photograph #15

The sheet metal coping cap from the roof assembly has detached from its keeper strip.

(Refer to Photograph #16)

Photograph #16

Discoloration of the brick and mortar was found under most spigot housings throughout the building.

Discoloration of the brick was found behind most splash blocks around the building.

(Refer to Photograph #17)

Photograph #17

Date: February 6th, 2024 RSI Project #: 23-13945-07 Page 9

All information is submitted as the confidential property of our clients. Any copies or extractions are reserved pending our written approval.

Interior photograph of water damage at the painted

CMU. Paint bubbling and water infiltration at the window opening stopped after window replacement work was completed.

(Refer to Photograph #18)

Photograph #18

Destructive test opening at head condition at first floor window location. Rust was found on the steel plate lintel under the flashing, showing signs that water has been getting under the flashing and causing damage to the steel lintel.

(Refer to Photograph #19)

Photograph #19

Destructive test opening at head condition at first floor window location. Turned hollow core brick has been lodged into the CMU backup wall with excessive amounts of mortar. This appears to have been the solution for continuation of the back up wall next to the wide flange steel structural lintel in lieu of cutting a CMU block in half or using a half block.

(Refer to Photograph #20)

Photograph #20

Date: February 6th, 2024 RSI Project #: 23-13945-07 Page 10

All information is submitted as the confidential property of our clients. Any copies or extractions are reserved pending our written approval.

IV. CONCLUSIONS & RECOMMENDATIONS:

HEAD CONDITIONS:

Significant damage was found on and around the steel lintels at all window locations throughout the building. After a series of test openings, it was determined that the window heads are not properly flashed to accommodate the moisture infiltrating the wall assembly. Though no water appears to be entering the building any more after replacing the window assemblies throughout the building (verified by water testing done on 12/07/23), water is still entering the wall assembly.

Because the steel lintel bottom plate is exposed and ends flush with the brick, water is able to either get back into the wall assembly under the head flashing, or it is lead to the underside of the steel lintel bottom plate through capillary action. Under the head condition in the window opening, without direct sunlight, the assembly isn’t able to dry properly and the water sits for long periods of time on the steel lintel plate. During freeze/thaw cycles, water expands within the assembly and causes the steel lintel plate to deflect away from the brick, delaminating it from the mortar joint. This would also cause small cracks to form in the exterior coating, allowing the moisture to penetrate directly to the steel, causing the steel to rust over time. We recommend removing and replacing a minimum of 4 courses of brick above each head, repairing and applying a corrosion resistant coating to the steel lintel bottom plates as necessary, and installing through-wall flashing (with termination bar, stainless steel drip edge, end dams of 2” minimum, weep vents, and a thermal break) at the head of every exterior wall opening.

SILL CONDITIONS:

Deterioration and evidence of water infiltration is found at every window sill location with varying severity. The sills consist of horizontal bricks with mortar joints, and have sealant joints at either side of the window opening that are failing, delaminating and cracking. After a series of test openings, it was determined that the window sills are not properly flashed to accommodate the moisture infiltrating the wall assembly. Though no water appears to be entering the building any more after replacing the window assemblies throughout the building (verified by water testing done on 12/07/23) and replacement of the roof in 2021, water is still entering the wall assembly.

Water enters the system through the mortar joints in the sill, and either sits on top of the brick directly under them, or makes its way backwards into the cavity wall assembly. Because of the small overhang of the sill, the mortar joint directly beneath it doesn’t get direct sunlight and doesn’t dry properly. Efflorescence in the masonry is an indication of this; it is a buildup of salts from water infiltration and gradual evaporation. We recommend removing the brick-and-mortar sill, installing through-wall flashing (with termination bar, stainless steel drip edge, end dams of

2” minimum, and a thermal break) at the sill, and replacing with a cast-stone sill (with a sloped top and a drip edge) at every window and louver location throughout the entire building. We also recommend cleaning the efflorescence and discoloration off of the brick, and repointing all discolored or deteriorated mortar throughout the entire building.

JAMB CONDITIONS:

The brick return at the jambs causes a thermal bridge in the wall assembly and can lead to excess moisture in the wall system in the form of condensation. We recommend removing the brick at each jamb, adding a thermal break between the brick veneer and the CMU back-up wall, installing a flashing membrane at the jamb, and reinstalling the face brick as necessary at all jamb locations throughout the entire building.

Date: February 6th, 2024 RSI Project #: 23-13945-07 Page 11

All information is submitted as the confidential property of our clients. Any copies or extractions are reserved pending our written approval.

EXISTING WALL ANCHORS:

At the locations where metal anchors are rusting and causing discoloration of the brick, we recommend removing the masonry anchors, cleaning the brick, and repointing the mortar joints as necessary. Where anchors appear to have damaged the brick, we recommend replacing bricks and repointing impacted mortar joints as necessary.

EXISTING MASONRY JOINTS:

All masonry sealant joints throughout the entire building are failing. This includes expansion joints, control joints, and joints around the existing brick sills (excluding the black sealant around the new window assemblies). We recommend replacing all sealant joints throughout the entire building.

EXISTING ROOF CAP:

At the location where the coping cap has detached from its keeper strip, we recommend reattachment as soon as possible to prevent water infiltration into the roof and wall assemblies.

WATER TESTING:

The water test (referenced above) consisted of a series of 3 two-hour tests conducted at a window opening. The interior wall is tested with a pin-point moisture meter to determine a baseline moisture level for the wall (average measurement of 6.6 baseline). Water is then directed at the exterior wall by an apparatus that simulates wind driven rain. After 2 hours, the interior wall is visually inspected for signs of water infiltration and tested again with the pin-point moisture meter to determine if the moisture level of the wall has increased from the baseline measurement.

This test was performed 3 times; below the window sill, on and around the window opening, and above the window head; each location was tested for 2 hours, for a total of 6 hours of water testing. No substantial increase of moisture or water infiltration was found on the interior wall

(average measurement of 7.7 after water testing).

The existing interior face of the CMU back-up wall shows signs of past water infiltration

(bubbling paint). Since the wall doesn’t have a high moisture level, we believe the paint bubbling was caused by past water intrusion via the original windows (recently replaced) and/or the old parapet cap condition (recently replaced). The recommended repairs should reduce the risk of further moisture issues in the CMU back-up wall.

Redacted

Date: February 6th, 2024 RSI Project #: 23-13945-07 Page 12

All information is submitted as the confidential property of our clients. Any copies or extractions are reserved pending our written approval.

Respectfully, RSI BUILDING ENVELOPE

Mary Owen

Project Designer

Redacted

Attachment ‘J’

ATTACHMENT J

EXISTING BUILDING 506 FLOOR PLANS

C

LA

S S R

O O

M

T .A . S

TO

R

A G E

C

LA

S S R

O O

M

C O

R R

ID

O R

LIB

R

A R

Y /C

LA

S S R

O O

M

C

LA

S S R

O O

M

C

LA

S S R

O O

M

1104A

V E S T

JA

N

M E N S

W O

M E N S

R O

O M

M E C

H A N

IC

A L

205TH ADVISOR

TECH

56TH

BN TECH

206TH

BN TECH

205TH

CDR

205TH

XO

205TH

S-3, 4

205TH

COMMONS

56TH MGT CH

CO CDR

56TH

CORRIDOR

CHIEF

56TH

CHIEF

56TH

REPRO

SIDPSE

882ND

205TH S-1

205TH RR

DRAFTING

CO CDR

13TH

13TH CDR

COMMONS

13TH S-1, 3, 4

XO/CSM

13TH

S-2

13TH

TECH

13TH

TECH

19TH

CDR

19TH

XO

19TH

MMC TANKS

56TH PETRO

19TH TM

CORRIDOR

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

F T

C F T

C F T

C F T

C F T

CFT

CFT

CFT

T

C

CFT

CFT

CFT

CFT

CFT

2-1-22

VAV

2-1-21

VAV

2-1-20

VAV

2-1-23

VAV

2-1-24

VAV

2-1-25

VAV

2-1-26

VAV

2-1-27

VAV

2-1-16

VAV

2-1-19

VAV

2-1-18

VAV

2-1-17

VAV

2-1-15

VAV

2-1-14

VAV

2-1-8

VAV

2-1-13

VAV

2-1-12

VAV

2-1-11

VAV

2-1-10

VAV

2-1-9

VAV

2-1-7

VAV

2-1-6

VAV

2-1-3

VAV

2-1-4

VAV

2-1-5

VAV

TYP OF (4)

C U

H5

TYP OF (2)

TYP OF (4)

TYP OF (8)

0 8' 32'16'

NORTH

PLAN

88TH ADVISOR

88TH IO

88TH ADVISOR

ADVISOR

88TH

LOBBY

385TH ADVISOR

RETENTION

VEST

CORRIDOR

PHOTO LAB

CHIEFS

205TH

88TH ADVISOR

56TH MMC

WOMENS

MENS

CORRIDOR

88TH ADVISOR

CE

385TH

TECH

385TH

882 CDR

PERS TECH

882ND

TECH

BD

205TH

TECH

205TH

TC SUP

205TH

BSO

205TH

TECH

205TH

TM

19TH

COMMONS

CDR38

5T

H

TE

CH38

5T H

CE36

7T

H

TE

CH36

7T H

XO38

5T

H

S-

5T H

CSM38

5T

H

PERS88

2N

D

83ENG

S-

7T

H

S-

7T H

85COMMONS

89ROOM

DRAFT

IN

G

TM13

TH

ENG33

6 11

PERS88

2N

D

94AC

COM

5T H

95CO

CDR

5T H

96RR/

EEO

5T H

CHAP38

5T

H

TE

CH38

5T

H 11

99CO

CDR

7T H

S-

7T H

CSM36

7T

H 12

CDR36

7T

H 12

XO36

7T

H

04CHAP36

7T

H 12

TE

CH36

7T H

TE

CH36

7T H

06ENGR41

6T H

07SURG36

7T H

93COMMONS

C O

R R

ID

O R

S T O

R A

G E

T E L E

C O

M

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T T T T T T

TT

T

T

T

T T

T T

T T

T

T

T

T

T

T

T

CFT CFT

CFT CFT CFT CFT CFT CFT CFT CFT CFT

CFT

CFT

CFT

CFT

CFT

CFT

CFT

CFT

CFT

CFT

CFT

CFT

CFT

CFT

CFT

1-1-23

VAV

1-1-22

VAV

1-1-24

VAV

1-1-25

VAV

1-1-26

VAV

1-1-27

VAV

1-1-28

VAV

1-1-29

VAV

1-1-31

VAV

1-1-30

VAV

1-1-21

VAV

1- 1-

VAV

1- 1-

VAV

1- 1-

VAV

1- 1-

VAV

1- 1-

VAV

1- 1-

VAV

1- 1-

VAV

1- 1-

VAV

1- 1-

VAV

1- 1-

VAV

1- 1-

VAV

1- 1-

VAV

1- 1-

VAV

1- 1-

VAV

1- 1-

VAV

1- 1-

VAV

1- 1-

VAV

1- 1-

VAV

1- 1-

VAV

1- 1-

VAV

1- 1-

VAV

1- 1-

VAV

1- 1-

VAV

1-1-16

VAV

1-1-15

VAV

1-1-17

VAV

1-1-18

VAV

1-1-19

VAV 1-1-20

VAV

1-1-14

VAV

1-1-12

VAV

1-1-10

VAV

1-1-13

VAV

1-1-11

VAV

1-1-9

VAV

TYP OF (9)

5 3 5

6 6

TYP OF (2)

CFT

CFT

6 3

TYP OF (11)

TYP OF (5)

SURG36

7T

H

V E S T

O F F

IC

E

O F F

IC

E

L O

B B

Y

W O

M E

N S

M E

N S

C O

R R

ID

O R

S T O

R A

G E

T E L E

C O

M

A R

C H

IV

E R

O O

M

O F F

IC

E

C O

N F E

R E

N C

E

O F F

IC

E

O F F

IC

E

O P E

N O

F F

IC

E

O F F

IC

E

V E S T

S T A

IR

O F F

IC

E

O F F

IC

E

O F F

IC

E

O F F

IC

E

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

-1 -1

V A V

-1 -1

V A V

-1 -1

V A V

-1 -1

V A V

-1 -1

V A V

-1 -1

V A V

-1 -1

V A V

-1 -1

V A V

-1 -1

V A V

-1 -1

V A V

-1 -9V A V

-1 -8V A V

-1 -7V A V

-1 -6V A V

-1 -4V A V

-1 -3V A V

-1 -2V A V

-1 -1

V A V

-1 -5V A V

C F T

C F T

C F T

C F T

C F T

C F T

C F T

C F T

C F T

C F T

C F T

C F T

C F T

C F T

CFT

CFT

CFT

CFT

CFT

CFT

CFT

TYP OF (4)

TYP OF (4)

TYP OF (2)

TYP OF (3)

C U

H

B124

ROOM

ELEC

B130

UNIT STORAGE

B129

CORRIDOR

B128

ARMS VAULT

B131

CORRIDOR

B127

& COMM

205TH RADIO

B132

REPRO ROOM

B133

672ND ADMIN

B134

MAT LAB

B

C O

R R

ID

O R

B1

36ROOM

MECHANI

CAL

B1

37COMM

SEC

B

C O

R R

ID

O R

B1

39STORAGE

B1

40STORAGE

UNI

T

B1

41CORRI

DOR

B1

UNI

T

STORAGE

B1

43ROOM

MECHANI

CAL

T E L E

C O

N

T T T

T

T

T

T

T

T

T

T

T

T

T

T

T

CFT CFT CFT CFT CFT

1-0-3

VAV

1-0-4

VAV 1-0-7

VAV

2 2 2 2 2

1 1

UH

UH

SMAC

UH

SMAC

1- 0-

8VAV

1- 0-

7VAV

VAV

VAV

ACCU-

R A

D

3 3

5 5

VAV

M-401

A1

B

B O

IL

E R

B

E L E

C T R

IC

A L

B

W O

M E

N

B

M E

N

B

T E L E

C O

N

B

M E

C H

A N

IC

A L

B

C O

N F E

R E

N C

E

B

S T O

R A

G E

B

F

IN

IS

H E

D S

P A

C E

B

U N F

IN

IS

H E

D S

P A

C E

S

T

S

T

S

T

T

T

T

S

T

T

T

T

T

T

T

T

T

SEMENT HVAC PLAN NEW WORK - C

C F T

C F T

C F T

C F T

C F T

CFT

CFT

CFT

CUH

CUH

C U

H

V A V -0 -7

V A V -0 -4

V A V -0 -2

V A V -0 -5

V A V -0 -3

V A V -0 -6

V A V -0 -1

V A V -0 -9

V A V -0 -1

2V A V -0 -1

V A V -0 -8

V A V -0 -1

TYP OF (5)

ACCU-

M-401

A9

B

C H

A

IR

S

TO

R

A G E

B

B A N

D S

TO

R

A G E

B

A S S E

M B

LY

H

A

LL

B

451S

T LIB

B

451S T C

D R

B

M E N S

TO

ILE

T

B

JA

N

ITO

R

B

TO

ILE

T

W O

M E N

SB

LO

B B Y

B

S

TO

R A G E

K

IT

C H E N

B

K

IT

C H E N

B

S C

U

LLE

R Y

B

C O

R R

ID

O R

B114

BAND STORAGE

B115

UNIT STORAGE

B116

CORRIDOR

B117

UNIT STORAGE

B118

ROOM

MECH

B119

SCIF

B120

CORRIDOR

B

C O

R R

ID

O R

B123

SEC

COMM

ROOM

ELEC

B125

ACCT

205TH PROP

B126

& COMM

205TH RADIO

T

T

T

T

T

T

T

T

T

T T

T

T

T

T

T

A C C

U -2

A C C

U -3

2-0-1

VAV

C F

TVAV

2-0-2 C F T

CUH

CUH

ACCU(S)

CFT

1-0-2

VAV

CFT

AHU

AHU

CFT1

JACE

E F

E F

CUH

C F T

C F T

CFT

1-0-1

VAV

C F T

C F T

0 8' 32'16'

NORTH

PLAN

BASEMENT FLOOR PLAN

FIRST FLOOR PLAN

SCALE: 3/32" = 1'-0"

SCALE: 3/32" = 1'-0"

MAIN SERVER ROOM B140-A

ROUTE COPPER AND FIBER TO THIS

SPACE FROM BUILDING 505 TR.

HEAD END

EQUIPMENT FOR

ACCESS CONTROL IN

ROOM 1148

Bldg. 506 Floor Plans

0 8' 32'16'

NORTH

PLAN

PM

205TH

S-1

205TH

RR/EEO

205TH

TECH

306TH

TECH

DCRM

88TH

STAFF

DCSPA

88TH

DCSPA

88TH

CDR

306TH

S-2

360TH

CO CDR

360TH

DCSPA

88TH

DCSPA

88TH

RR/EEO

88TH

COMMONS

COMMONS

SEC

MED

OFC

XO/CSM

360TH

DCSRM

88TH

DCSRM CH

88TH

MMC

56TH

ROOM

DRAFT

ROOM

REPRO

SURG

88TH

WOMENS

MENS

ADVISOR

205TH

MMC

56TH

JAG

117TH

S-2, 4

302ND

S-1

302ND

TECH

302ND

XO/CSM

302ND

CDR

302ND

SJA

88TH

ADVISOR

88TH

COMMONS

IG

88TH

CHAP

88TH

81DCSP

A88

TH

82DCSOI88

TH 21

83DCSOI88

TH

TE

CH88

TH 21

85HQ

CO88

TH

ACHI

EF

S

DCSOI88

TH

80TM

CHI

EF

S

0T H

88COMMONS

87ADVI

SOR

TH

B

DCSOI

C

HI

EF

S

TH

89CENTE

RMSG

90DSLOG88

TH

MMC56

TH

CONFE

RENCE

07COMMON

97DSLOG88

TH

98DSLOG88

TH

ATE

CHDSLOG88

TH

TE

CHDSLOG88

TH 22

RA36

4T

H 22

SEC88

TH 22

TE

CH88

TH

CS88

TH 22

CSM88

TH

CDR88

TH

06DEP

C

DR

TH

C O

R R

ID

O R

C O

R R

ID

O R

O F F

IC

E

O F F

IC

E

S T O

R A

G E

T E L

W C

P R

IV

A T E

T T T T T T T T T

T T

T T T T

T

T

T

T T T T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

B

T

S

S

S

S

T T

T

T

T T

T

T

T

S

S T

T

T

T

T

T

S T

1-2-56

VAV

1-2-57

VAV

1-2-58

VAV

1-2-60

VAV

1-2-61

VAV

1-2-59

VAV

1-2-62

VAV

1-2-55

VAV

1-2-64

VAV

1-2-63

VAV

1-2-67

VAV

1-2-68

VAV

1-2-65

VAV

1-2-66

VAV

1-2-70

VAV

1-2-69

VAV

1-2-72

VAV

1-2-73

VAV

1-2-74

VAV

1-2-75

VAV

1-2-76

VAV

1-2-77

VAV

1-2-78

VAV

1-2-79

VAV

1-2-80

VAV

1-2-71

VAV

1-2-81

VAV

1-2-82

VAV

1- 2-

VAV

1- 2-

VAV

1- 2-

VAV

1- 2-

VAV

1- 2-

VAV

1- 2-

VAV

1- 2-

VAV

1- 2-

VAV

1- 2-

VAV

1- 2-

VAV

1- 2-

VAV

1- 2-

VAV

1- 2-

VAV

1- 2-

VAV

1- 2-

6VAV

1- 2-

VAV

1- 2-

VAV 1-

2-

0VAV

1- 2-

1VAV

1- 2-

2VAV

1- 2-

3VAV

1- 2-

4VAV

1- 2-

5VAV

CFT CFT CFT CFT CFT CFT CFT CFT CFT

CFT CFT CFT CFT

CFT

CFT

CFT

CFT

CFT

CFT

CFT

CFT

CFT

CFT

CFT

CFT

TYP OF (4)

TYP OF (9)

TYP OF (6)

TYP OF (8)

3 3

UH

3 3 3 3

3 3

UH

2 3

33333333

6 6

5 5

5 5 5

5 5

6 6

5 5 5

UH

UH

UH

5 5

C F T

C F T

C F T

C F T

C F T

1- 2-

VAV

CHI

EF

S

DCSOI88

TH

O F F

IC

E

O F F

IC

E

O F F

IC

E

O F F

IC

E

O F F

IC

E

C O

R R

ID

O R

W O

M E

N S

M E

N S

S T O

R A

G E

3T E L

C L A S S

R O

O M

C R T O

P E

N O

F F

IC

E

5W C

P R

IV

A T E

O F F

IC

E

O P E

N O

F F

IC

E

O F F

IC

E

O F F

IC

E

O F F

IC

E

S T O

R A

G E

O F F

IC

E2

S T A

IR

S

O F F

IC

E

O F F

IC

E

O F F

IC

E

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

-2 -1

V A V

-2 -1

V A V

-2 -1

V A V

-2 -1

V A V

-2 -1

V A V

-2 -1

V A V

-2 -1

V

-2 -1

V A V

-2 -3V A V

-2 -4V A V

-2 -5V A V

-2 -2V A V

-2 -1

V A V

-2 -6V A V

-2 -8V A V

-2 -7V A V

-2 -9V A V

-2 -1

V A V

-2 -1

V

T

C F T

C F T

C F T

C F T

C F T

C F T

C F T

C F T

C F T

C F T

C F T

C F T

C F T

C F T

CFT

CFT

CFT

CFT

CFT

CFT

CFT

S M

A C

A C

C U

S M

A C

TYP OF (2)

TYP OF (2)

TYP OF (3)

TYP OF (4)

TYP OF (4)

5 5

C

LA

S S R

O O

M

C

LA

S S R

O O

M

C E N T E R

LE

A R

N

IN

G

C O

R R

ID

O R

C

LA

S S R

O O

M

TA

S

TO

R

A G E

M E N S

W O

M E N S

S

TO

R A G E

BD TECH

205TH

CHAP

205TH

ARM

302ND

TECH

302ND

TECH

205TH

CO CDR

205TH

MP

205TH

PM

205TH

S-1

205TH

RR/EEO

205TH

TEL ROOM

MMC

56TH

CHIEFS

302ND

COMMONS

DP CDR

205TH

CSM

205TH

TECH

205TH

C O

R R

ID

O R

C O

R R

ID

O R

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

T

SECOND FLOOR HVAC PLAN NEW WORK - A

2-2-36

VAV

2-2-35

VAV

2-2-34

VAV

2-2-33

VAV

2-2-32

VAV

2-2-38

VAV

2-2-37

VAV

2-2-41

VAV

2-2-40

VAV

2-2-42

VAV

2-2-39

VAV

2-2-53

VAV

2-2-45

VAV

2-2-43

VAV

2-2-44

VAV

2-2-46

VAV

2-2-47

VAV

2-2-48

VAV

2-2-49

VAV

2-2-50

VAV

2-2-51

VAV

2-2-52

VAV

2-2-29

VAV

2-2-28

VAV

2-2-30

VAV

2-2-31

VAV

C F T

C F T

C F

TC

F T

CFT

CFT

CFT

CFT

CFT

CFT

CFT

CFT

CFT

CFT

CFT

CFT

TYP OF (2)

TYP OF (2)

TYP OF (5)

TYP OF (7)

6 6

C F T

CFT

SECOND FLOOR PLAN

SCALE: 3/32" = 1'-0"

1TYP OF (2)

Attachment ‘K1’

ATTACHMENT K1

HAZARDOUS BUILDING MATERIALS AND RADON SURVEYS REPORT

March 6, 2024

Final Hazardous Building Materials and Radon Surveys Report

Fort Snelling Army Reserve Center, Building 505

506 Roeder Circle

Fort Snelling, Minnesota

FACID/Site Code: MN036

Prepared for:

RSP Architects 1220 Marshall Street NE and:

US Army Reserve

88th Readiness Division

506 Roeder Circle

Fort Snelling, MN 55111

Pinyon Project No.:

121143001.002

March 6, 2024

Fort Snelling Army Reserve Center, Building 505

506 Roeder Circle

Fort Snelling, Minnesota

FACID/Site Code: MN036

Prepared for:

RSP Architects

1220 Marshall Street NE and

US Army Reserve

88th Readiness Division

506 Roeder Circle

Fort Snelling, MN 55111

Pinyon Project No.:

121143001.002

Prepared by:

Darin Worden, Senior Hydrologist

Reviewed by:

Russ Cirillo, PE, Federal Market Manager

Final Hazardous Building Materials and Radon Survey Report

Fort Snelling Building 505 Renovation, US Army Reserve Center 506 Roeder Circle, Ft. Snelling, Minnesota 55111 Page i

Table of Contents

Executive Summary

1. Radon Survey

1.1 Testing Procedures

1.2 Testing Results

1.3 Conclusions

2. Hazardous Building Materials Survey

Tables

Table 1-1 Radon Sample Test Results

Table 2-1 Summary of Potential Hazardous Building Materials/Components

Figures

Figure 1 Site Location Map Figure 2 Radon Sample Locations 1st Floor

Figure 3 Radon Sample Locations 2nd Floor

Appendices

Appendix A. Radon Sample Laboratory Report

Fort Snelling Building 505 Reovation, US Army Reserve Center 505 Roeder Circle, Fort Snelling, Minnesota 55111 Page 1

Executive Summary

Pinyon Environmental, Inc., (Pinyon) presents the following report detailing the Hazardous Building

Material (HBM) and Radon Surveys conducted as part of the planning and design for the update/renovation of Building 505, US Army Reserve Center, located at 506 Roeder Circle, Fort Snelling, Minnesota 55111

(Figure 1, the Site). The mechanical room in Building 509 was also included in the HBM survey as this is the location where utility connections will be made for a new wash rack that is also part of the Building

505 renovation project.

The HBM and radon surveys were conducted the week of October 30, 2023. The HBM survey was conducted by Ms. Rachel Hernandez of Pinyon and Mr. Brett Brumbaugh of Castle Hill Associates on

October 30 and 31, 2023; and the radon survey was conducted by Mr. Brad Nyberg, Great River Radon

(GRR), under Minnesota License #MN00054 on October 30 through November 2, 2023. Castle Hill

Associates (asbestos and LBP) and GRR (radon) were subcontracted by Pinyon due to the specialized certification and licensing requirements for the surveys.

The two surveys indicated:

• Radon. Forty-six (46) radon samples were collected throughout Building 505 (Figures 2 and 3).

Analytical results indicated that one sample, collected from Room 113C (Figure 2), contained radon activity levels in excess of the Environmental Protection Agency (EPA) screening level of 4.0 picocuries per liter (pCi/L). The measured radon level in Room 113C was measured at 4.3 pCi/L. The radon survey is further detailed below in Section 1. Due to the Room 113C test results, Mr. Nyberg recommends re-testing Room 113C and all adjacent rooms that share a wall. The re-testing would be performed using Continuous Radon Monitors (CRM) to establish the most appropriate path forward to protect occupants. The 4 rooms that are recommended for re-testing using CRMs are 113C, 113, 113B, and 111 (Figure 2).

• Hazardous Building Materials (HBMs). Several building components associated with future construction or demolition were identified that have the potential to meet the definition of “hazardous waste” or regulated waste material if removed. This includes fluorescent bulbs, light ballasts, mercury switches, exit signs, emergency lights, smoke detectors, and fire extinguishers. A detailed list of the potential HBMs identified in Building 505 and the mechanical room of Building 509 is presented in

Section 2.

505 Roeder Circle, Fort Snelling, Minnesota 55111 Page 2

1. Radon Survey

Great River Radon (GRR) completed the Building 505 radon survey by collecting 46 samples at the locations identified on Figures 2 (1st Floor) and Figure 3 (2nd Floor). The purpose of the sampling was to evaluate indoor air radon levels of frequently occupied rooms, which include, but are not limited to, offices, work rooms, and common rooms. The building has two floors with no accessible areas below ground level. The sampling was conducted by GRR’s Minnesota licensed radon measurement and mitigation professional, Mr. Brad Nyberg (#MN00054).

1.1 Testing Procedures

The radon testing was initiated on October 30, 2023, by placing radon test kits (activated charcoal) at select locations throughout the building. The test kits were retrieved on November 2, 2023. The sampling was performed in accordance with the American National Standards Institute (ANSI) and American

Association of Radon Scientists and Technologists (AARST) procedures for radon testing. The sample locations were selected because facility personnel are likely to be present in these areas. The approved test kits were produced by Air Chek, Inc. of Mills River, North Carolina, and are approved by AARST.

The tests were conducted under ANSI/AARST protocol which requires:

• A test length of at least 48 hours.

• Tests to be located in breathing zones (between 20 inches and 96 inches from the floor).

• Ingress and egress activities be minimized.

• Indoor air temperatures above 65°F before and during sampling.

An overview of the radon sampling at the Property includes:

• On October 30, 2023, GRR placed 46 test kits throughout the building. The test kits were placed near the entrances in rooms identified on Figure 2 (1st floor) and Figure 3 (2nd floor). The sampling included 4 duplicate samples, and 5 blank samples and 37 primary samples.

• The test kits were left in place for over 48 hours, with retrieval of the kits on November 2, 2023.

• The HVAC system was operational when the test kits were placed, and when the test kits were retrieved.

• Upon collection of each sample, the test kits were sealed, and the date/time was documented. After the test kits were collected, sealed, and labeled, they were shipped to Air Chek, Inc. for analysis.

• The test kits were analyzed by Air Chek using a scintillation detector to count the gamma decay absorbed by the charcoal. The radon concentration for each sample was calculated using instrument calibration information.

505 Roeder Circle, Fort Snelling, Minnesota 55111 Page 3

• No test kits appeared to have been tampered with or moved in the time-period between deployment and retrieval.

Sample blanks were stored with the other testing devices. Upon deployment, the blanks were opened and then sealed immediately. The blanks were placed in Rooms 101, 116, 115, 127, and 209 (Figure 2 and

Figure 3). The blank sample cartridges were retrieved at the same time as all other testing devices and followed the same shipping to the laboratory. All blank sample results are expected to be under 0.3 picocuries per liter pCi/L.

1.2 Testing Results

The indoor radon sample laboratory report is presented in Appendix A. Radon levels in the samples collected at the Property ranged from <0.3 picocuries per liter (pCi/L) to 4.3 pCi/L. Blank sample results were less than 0.3 pCi/L. An overall summary of sample results is presented below in Table 1-1.

1.3 Conclusions

Based on laboratory analysis results of collected radon samples, one sample (Room 113C) exceeded EPA’s action level of 4.0 pCi/L (Figure 2).

To further evaluate this exceedance, it is recommended that Room 113C be retested and that all adjacent offices that share a wall also be tested. The recommended testing would use Continuous Radon Monitors

(CRM) to further evaluate risks and understand the extent of the potential impact. The four rooms recommended for CRM testing include 113C, 113, 113B, and 111.

505 Roeder Circle, Fort Snelling, Minnesota 55111 Page 4

Table 1-1

Radon Sample Test Results

Ft. Snelling Building 505

Notes:

pCi/L – picocuries per liter

< - less than

Bold – Concentration exceeds EPA screening level of 4.0 pCi/L

Test Kit

Number

Deployment

Date

Retrieval

Date Building

Building

Floor

Building

Room

Radon Result pCi/L Comment

7401437 10/30/2023 11/2/2023 505 2 201 <0.3

7401438 10/30/2023 11/2/2023 505 2 304 <0.3 Blank Sample/Room 101

7401439 10/30/2023 11/2/2023 505 2 201 0.8 Duplicate Sample

7401440 10/30/2023 11/2/2023 505 1 122 3.0

7401441 10/30/2023 11/2/2023 505 1 125-126 0.8

7401442 10/30/2023 11/2/2023 505 1 128A 1.1

7401443 10/30/2023 11/2/2023 505 1 124 0.6

7401444 10/30/2023 11/2/2023 505 1 123 1.5

7401445 10/30/2023 11/2/2023 505 2 209 1.2

7401446 10/30/2023 11/2/2023 505 2 222 0.6

7401447 10/30/2023 11/2/2023 505 1 127 1.0

7401448 10/30/2023 11/2/2023 505 1 128 <0.3

7401449 10/30/2023 11/2/2023 505 1 303 <0.3 Blank Sample/Room 116

7401450 10/30/2023 11/2/2023 505 2 202 1.2

7401451 10/30/2023 11/2/2023 505 2 305 <0.3 Blank Sample/Room 115

7401452 10/30/2023 11/2/2023 505 1 121 2.1

7401453 10/30/2023 11/2/2023 505 2 222 0.6 Duplicate Sample

7401454 10/30/2023 11/2/2023 505 2 206 1.0 Listed as room 26 on lab report

7401455 10/30/2023 11/2/2023 505 2 211 1.4

11693749 10/30/2023 11/2/2023 505 1 119 1.4

11693755 10/30/2023 11/2/2023 505 1 111A 1.5

11693771 10/30/2023 11/2/2023 505 1 113C 4.3

11693773 10/30/2023 11/2/2023 505 1 102 2.0

11693774 10/30/2023 11/2/2023 505 1 114 <0.3

11693775 10/30/2023 11/2/2023 505 1 111 1.0

11693779 10/30/2023 11/2/2023 505 1 113D 2.7

11693780 10/30/2023 11/2/2023 505 1 116 1.3

11693781 10/30/2023 11/2/2023 505 1 110-2 1.2

11693782 10/30/2023 11/2/2023 505 1 112 0.7

11693821 10/30/2023 11/2/2023 505 1 113B 0.9

11693823 10/30/2023 11/2/2023 505 1 110 1.1

11693824 10/30/2023 11/2/2023 505 1 108A <0.3

11693836 10/30/2023 11/2/2023 505 1 113 0.8

11693837 10/30/2023 11/2/2023 505 1 108 1.5

11693838 10/30/2023 11/2/2023 505 1 109 1.8

11693839 10/30/2023 11/2/2023 505 1 113 1.7 Duplicate Sample

11693840 10/30/2023 11/2/2023 505 1 117 1.7

11693892 10/30/2023 11/2/2023 505 1 113E 1.2

11693893 10/30/2023 11/2/2023 505 1 113A 0.9

11693894 10/30/2023 11/2/2023 505 1 301 <0.3 Blank Sample/Room 127

11693895 10/30/2023 11/2/2023 505 1 103 0.5

11693896 10/30/2023 11/2/2023 505 1 103A 1.0

11693897 10/30/2023 11/2/2023 505 1 102 1.6 Duplicate Sample

11693898 10/30/2023 11/2/2023 505 1 101 1.2

11693899 10/30/2023 11/2/2023 505 1 302 <0.3 Blank Sample/Room 209

11693900 10/30/2023 11/2/2023 505 1 115 1.2

505 Roeder Circle, Fort Snelling, Minnesota 55111 Page 5

2. Hazardous Building Materials Survey

Hazardous building materials include but are not limited to: asbestos (caulking, weather stripping, masonry joints); LBP; polychlorinated biphenyls (PCBs) in fluorescent light ballasts or electrical transformers;

mercury-containing fluorescent lamps, thermostats, and switches; and smoke detectors. The asbestos and

LBP survey for the Property is covered under a separate, stand-alone document prepared by Castle Hill

Associates (CHA). CHA is a subcontractor licensed and certified to conduct asbestos and LBP sampling in Minnesota. Pinyon and CHA together surveyed Building 505 and the mechanical room in Building 509, for mercury-containing devices, PCBs, and other potentially regulated equipment and/or building materials.

The non asbestos and LBP potentially hazardous building materials are covered below.

Pinyon and CHA surveyed Building 505 for PCB, mercury-containing equipment, and other potentially hazardous building materials on October 30 and November 1, 2023. The survey was conducted by experienced inspectors walking through the facility and documenting possible PCB-containing equipment, mercury-containing devices, and other potentially hazardous equipment and/or materials. No laboratory samples were collected. Two pad-mounted electrical transformers were noted outside of Building 505.

One transformer was observed northwest, and the 2nd west of Building 505. No leaks or stains were noted in the vicinity of either transformer.

Component removal or disassembly for internal inspection was not performed, except for HVAC system thermostats. The cover of approximately 10 HVAC system thermostats were removed and none contained mercury switches. Therefore, it was assumed that the Building 505 thermostats do not contain mercury.

Based solely on visual observation and prior experience, building components were identified and may require removal during construction or demolition and have the potential to meet the definition of

“hazardous waste” or other classification as a regulated waste material. Table 2-1 below provides a building component list and estimated quantities that were observed in Building 505 and the mechanical room of

Building 509.

No green markings were observed on fluorescent bulbs. Green markings suggest the bulbs may contain a small amount of mercury.

The use of PCBs was banned in 1978. Building 505 was constructed in 1979. Fluorescent light ballasts and other equipment, manufactured after 1978 likely do not contain PCBs. No markings were observed on the ballasts that would indicate the presence or non-presence of PCBs. Because of the construction date, it is possible that the building’s fluorescent lighting ballasts do not contain PCBs, but due to the lack of external markings, the actual content cannot be determined without laboratory analysis.

The building components referenced in Table 2-1 may require special handling if removal is performed.

Additional characterization may be required by receiving disposal facilities. The inspection was performed in a manner consistent with the level of care and expertise exercised by members of the hazardous building materials inspection and assessment profession. Those entities and persons involved with the inspection and generation of this report do not imply or guarantee that all potential materials on or in the structure have been identified. The inspection was intended to identify those accessible materials that were

505 Roeder Circle, Fort Snelling, Minnesota 55111 Page 6 reasonably suspect and were most likely to contain PCBs, mercury, or other potentially regulated equipment and/or materials.

Table 2-1. Summary of Potential Hazardous Building Materials/Components

Regulated Building

Material Location(s)

Estimated

Total Building

1,412 505

3 509

582 505

1 509

Compact fluorescent lighting Entryways 10 505

18 505

1 509

Emergency lights Walls 20 505

7 505

1 509

26 505

1 509

Electrical Transformers Exterior, northwest and west of Building 505 2 505

Fire extinguishers Walls

Smoke Detectors Ceilings

Fluorescent bulbs Ceilings

Ballasts for fluorescent lighting Ceilings

Exit signs Exit Sign

505 Roeder Circle, Fort Snelling, Minnesota 55111

Figures

Fort Snelling Army Reserve Center Building 505 Building 509

Figure 1 – Site Location Map Fort Snelling, Building 505 506 Roeder Circle, Fort Snelling, MN 55111

Test Location exceeded screening level Legend

Test Location less than screening level

Duplicate Test Location

128A

Cross hatch is remnant from previous map use.

It does not represent any condition for radon sampling.

Figure 2 Radon Sampling Locations

Building 505 1st Floor Ft. Snelling, MN November 2023

Map Source: Pansch, Martin R CTR USARMY 88 RD (USA) <martin.r.pansch.ctr@army.mil>

Test Location exceeded screening level Legend

Test Location less than screening level

Duplicate Test Location

Cross hatch is remnant from Previous map use. It does not represent any condition for radon sampling.

Figure 3 Radon Sampling Locations

Building 505 2nd Floor Ft. Snelling, MN November 2023

Map Source: Pansch, Martin R CTR USARMY 88 RD (USA) <martin.r.pansch.ctr@army.mil>

Appendices

Appendix A. Radon Survey Subcontractor Report

23-A1104

Fort Snelling Building 505

11/9/2023 c/o Darin Worden Pinyon Environmental Fort Snelling g

Building 505 Dear Mr. Worden, T s re

Radon Measurement Results

SSeeee llaabb rreeppoorrttss

23-A1104

#$%��&'()*��%+*%�,+%)��%+*%��$')��-.�,+%)��-.��$')��)'/0�1+2$3$%4� �&$3.$-5��66'��*67)2%��,�1366*��)8&3%�

9:��:

9� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ���� �� I��J

9:��:

K� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H�

�:� �� I��J

9:��:

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ���� �� �JK�

9:��::�� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ���� ��

J��

9:��::�� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ��H;��L� �� �JK�

9:��::�� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ��KM� �� �J��

9:��::

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ��:� �� �JL�

9:��:::� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ��

� �� �JH�

9:��::H� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� �� � �� �J��

9:��::L� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ���� �� �JL�

9:��::9� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ��9� �� �J��

9:��::K� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ��K� �� I��J

9:��:: � ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H�

� �� I��J

9:��:H�� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ���� �� �J��

9:��:H�� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H�

�H� �� I��J

9:��:H�� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ���� �� �J��

9:��:H

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ���� �� �JL�

9:��:H:� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� �L� �� �J��

9:��:HH� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ���� �� �J:�

��L 9: � ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� �� � �� �J:�

��L

9HH� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ���M� �� �JH�

��L 99�� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ��

N� �� :J

��L

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ���� �� �J��

��L 99:� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ��:� �� I��J

��L 99H� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ���� �� �J��

��L 99 � ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ��

O� �� �J9�

��L 9K�� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ��L� �� �J

��L 9K�� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ���;�� �� �J��

��L 9K�� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ���� �� �J9�

��L K��� ���

;��;���<���>��� 9�� ?@AB�C�DEEF�G�H�H� ��
P� �� �J�

��L K�

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ���� �� �J��

��L K�:� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ��KM� �� I��J

��L K L� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ��

� �� �JK�

��L K 9� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� ��K� �� �JH�

��L K K� ���

;��;��� <���>��� 9�� ?@AB�C�DEEF�G�H�H� �� � �� �JK�

MQ��NR�S���

L�PTUV���P�QW���AW

���XQVVY�AQ���

����N��K9H;
K�����R�Z�<�[K�K\�LK:;�K
�?>]<�[K�K\�LK:;K:K

"#$��%&'()��$*)$�+*$(��$*)$��#&(��,-�+*$(��,-��#&(��(&./�0*1#2#$3� �%#2-#,4��55&��)56(1$��+�0255)��(7%2$�

;8�;

;88;��� <���>��� ?�� @ABC�D�EFFG�H�I�I� 88

� 8� 8J?�

:K�� ��� ;8�;

;88;��� <���>��� ?�� @ABC�D�EFFG�H�I�I� 88?� 8� 8J?�

;8�;

;88;��� <���>��� ?�� @ABC�D�EFFG�H�I�I� 88

E� 8� 8J��

;8�;

;88;���<���>��� ?�� @ABC�D�EFFG�H�I�I� 88
L� 8� �J�

: K� ��� ;8�;

;88;��� <���>��� ?�� @ABC�D�EFFG�H�I�I�

�8� 8� M��J

: I� ��� ;8�;

;88;��� <���>��� ?�� @ABC�D�EFFG�H�I�I� 8�

� 8� �JI�

: 9� ��� ;8�;

;88;��� <���>��� ?�� @ABC�D�EFFG�H�I�I� 8�

L� 8� 8J��

;8�;

;88;��� <���>��� ?�� @ABC�D�EFFG�H�I�I� 8��� 8� 8J9�

;8�;

;88;��� <���>��� ?�� @ABC�D�EFFG�H�I�I� 8�8� 8� 8J��

;8�;

;88;��� <���>��� ?�� @ABC�D�EFFG�H�I�I�

��� 8� M��J

;8�;

;88;��� <���>��� ?�� @ABC�D�EFFG�H�I�I� 88I� 8� 8J��

LN��OP�Q��8

9�RSTU���R�NV���BV

���WNUUX�BN���

����O��:?I;
:�����P�Y�<�Z:�:[�9:K;�:
�@>\<�Z:�:[�9:K;:K:

Attachment ‘K2’

ATTACHMENT K2

ASBESTOS AND LEAD PAINT INSPECTION SUMMARY

Items: Summary Results of Asbestos & Lead-Based Paint, Site Visit, Visual Inspection, Lab Results

Site Visit: October 30, 2023

Inspector: Brett Brumbaugh - Castle Hill Associates

Findings: Asbestos containing materials are present in Building 505 Lead-based paint is present in Building 505

Note: There were no asbestos containing materials or lead-based paint identified in B509 where the renovations will be conducted for the utility tie-ins.

Asbestos Containing Materials Summary – Building 505

Asbestos Containing Material Locations Quantity

Black mastic on concrete floors under non-asbestos floor tile, yellow mastic, and carpeting

First Floor: Hallways, entries, stairwells, and Rooms 101, 102, 103, 103A, 104, 108, 108A, 109, 110, 111, 111A, 112, 112A, 113, 114, 115, 116, 117, 118, 119, 120, 121, 122, 124, 125, 126, 127, 129 Second Floor: Hallways, stairwells, and Rooms 201, 202, 202A, 206, 206A, 206B, 207, 208, 208A, 208B, 209, 209A, 209B 210, 211, 211A, 212, 213, 213A, 213B, 215.

36,740 sf

Exterior brown window frame caulking

All exterior window frames on 1st and 2nd floors windows

3 Boiler door and burner gaskets 3 boilers in boiler room 6 gaskets

(30 lf)

Lead Painted Materials – Building 505

Lead Painted or Lead Building Materials Locations

1 Metal lockers (interior orange paint and exterior gray paint)

1st and 2nd floor hallways

Asbestos Containing Materials (ACM) Summary – Building 509

Asbestos Containing Material Locations Quantity

1 None N/A N/A

Lead Painted Materials – Building 509

Lead Painted or Lead Building Materials Locations

1 None N/A

35% SCHEMATIC DESIGN SUBMISSION

ASBESTOS & LEAD PAINT INSPECTION SUMMARY

FORT SNELLING USARC – FT. SNELLING, MN

BUILDINGS 505 & 509 – RENOVATION PROJECT 35% SCHEMATIC DESIGN SUBMISSION

Date: November 12, 2023

35% SCHEMATIC DESIGN SUBMISSION

ASBESTOS & LEAD PAINT INSPECTION SUMMAR

FORT SNELLING USARC – FT. SNELLING, MN

BUILDINGS 505 & 509 – RENOVATION PROJECT

INSPECTION DATE:

OCTOBER 30, 2023

ENVIRONMENTAL CONSULTANT:

CASTLE HILL ASSOCIATES, LLC

1197 FARNSWORTH RD., UNIT E

WATERVILLE, OH 43566

567-952-0212

WWW.CASTLEHILLASSOCIATES.COM

ASBESTOS & LEAD PAINT SURVEY

FORT SNELLING USARC – FT. SNELLING, MN

BUILDINGS 505 & 509 – RENOVATION PROJECT

ASBESTOS & LEAD PAINT SAMPLING REPORT

for

BUILDINGS 505 & 509

FORT SNELLING USARC/AMSA #22

(MN036/27865)

506 ROEDER CIRCLE

FT. SNELLING, MN 55111

PREPARED FOR:

U.S. ARMY CORPS OF ENGINEERS

LOUISVILLE DISTRICT

600 MARTIN LUTHER KING JR PLACE

LOUISVILLE, KY 40202

ASBESTOS & LEAD PAINT SURVEY

FORT SNELLING USARC – FT. SNELLING, MN

BUILDINGS 505 & 509 – RENOVATION PROJECT

TABLE OF CONTENTS

ASBESTOS & LEAD-BASED PAINT INSPECTION SUMMARY ……………………………

APPENDIX A:

ASBESTOS BULK SAMPLING DESCRIPTIONS AND LAB RESULTS (TABLE 5) .….….

APPENDIX B:

ASBESTOS CONTAINING MATERIAL PHOTOS (TABLE 6) …………………………….…

APPENDIX C:

ASBESTOS HOMOGENEOUS SAMPLING AREAS (HSA) LIST (TABLE 7) …….….…...

APPENDIX D:

ASBESTOS HOMOGENEOUS SAMPLING AREAS (HSA) PHOTOS (TABLE 8) ……

APPENDIX E:

LEAD-BASED PAINT SAMPLING RESULTS (TABLE 9) ………………………………….…

APPENDIX F:

LEAD-BASED PAINT COMPONENT PHOTOS (TABLE 10) .………………………….…...

APPENDIX G:

LEAD-BASED PAINT TESTED MATERIAL PHOTOS (TABLE 11) …………………….….

APPENDIX H:

ASBESTOS LABORATORY REPORT …………………………………………………….….

APPENDIX I:

ASBESTOS LABORATORY CERTIFICATIONS ……………………………………………...

APPENDIX J:

INSPECTOR CERTIFICATIONS ……………………………………………………………….

APPENDIX K:

ASBESTOS SAMPLE AND MATERIAL LOCATION DRAWINGS ……………………….…

APPENDIX L:

LEAD-BASED PAINT XRF SAMPLE AND MATERIAL LOCATION DRAWINGS ………

APPENDIX M:

US ARMY ASBESTOS CONTAINING MATERIAL CHECKLISTS ……………………….….

APPENDIX N:

2004 ASBESTOS SURVEY – FLOOR PLANS AND LAB REPORT …………………….…..

APPENDIX O:

2013 ECP – LEAD DUST CLEANUP DOCUMENTATION FOR FORMER GUN RANGE …

FORT SNELLING USARC – FT. SNELLING, MN

BUILDINGS 505 & 509 – RENOVATION PROJECT

PROJECT SUMMARY

On October 30, 2023, Brett Brumbaugh of Castle Hill Associates performed an asbestos survey and lead (Pb) paint testing utilizing a Viken Detection Pb200i direct read X-Ray Fluorescence (XRF) analyzer prior to the planned interior renovations planned in Buildings 505 & 509 at the Ft.

Snelling USARC (United States Army Reserve Center) in Minneapolis, MN.

Building 505 was constructed in 1979 and is approximately 63,000 square feet (sf) in size. The building is on a concrete slab with no basement and has a flat roof rubber roof. The roof was recently replaced with an EDPM rubber roof and therefore not sampled due to warranty issues and conditions. Bulk samples were collected from suspect asbestos containing materials (ACM) that had not been sampled during previous asbestos surveys in the building. Thirty-eight (38) bulk samples were collected during the survey; this report summarizes the collection and laboratory analysis of the samples.

Building 509, which is a small metal maintenance shed, was tested because there is a water…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .