This justification and approval document supports a sole source procurement for fire monitoring system equipment and software from Monaco Enterprises Incorporated for a Child Development Center construction project at Scott Air Force Base, Illinois. The solicitation was issued by the Department of the Army Corps of Engineers Engineering District Louisville as solicitation number W912QR23R0028. The justification cites that MEI is the only manufacturer that can ensure compatibility with the base-wide fire monitoring system currently in use, for which the government has an existing maintenance contract. Market research found no other equipment that would integrate seamlessly. Notice of intent to sole source was posted on SAM.gov on March 16, 2023 with no other sources expressing interest. The contracting officer determines the anticipated cost from MEI to be fair and reasonable based on the project estimate and recommends proceeding with the sole source award for prompt service delivery.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
LRL-FY23-38
c) Impact: Failure to establish adequate compatibility will result in delayed emergency response times. We utilize a base-wide maintenance contract to maintain these systems and installing a new system would require additional training and the establishment of another service contract at a significant cost to the government.
d) Alternatives: None viable to achieve a fully functioning system for the reasons noted above in paragraph 5. b) and c).
6. Efforts to Obtain Competition: Technical capabilities of various manufacturers were reviewed for compatibility to the current system. None of the various manufacturers’ equipment would ensure a seamless compatibility with the existing system which currently utilizes Monaco Enterprises Incorporated (MEI) fire monitoring system equipment/software exclusively.
A Notice of Intent to Sole Source was posted on the SAM.gov website on 16 March 2023. To date, no other sources have written to express interest.
7. Actions to Increase Competition: Apart from the complete replacement of the current system in its entirety, competition will be limited. This is a finite requirement with no future needs, and therefore there are no actions to increase future competition.
8. Market Research: A technical review and evaluation was conducted of the system requirements for the Child Development Center project. As discussed above, in paragraph 6 above, only Monaco Enterprises Incorporated (MEI) fire monitoring system equipment/software will ensure seamless compatibility with the existing system.
Interested Sources: A Notice of Intent to Sole Source was posted on the SAM.gov website on 16 March 2023. To date, no other sources have written to express interest.
9. Other Factors: None
10. Technical Certification: I certify that the supporting data under my cognizance, which are included in the Justification and Approval, are accurate and complete to the best of my knowledge and belief.
DATE ____________
Project Engineer
LRL-FY23-38
11. Requirements Certification: I certify that the supporting data under my cognizance, which are included in the Justification and Approval, are accurate and complete to the best of my knowledge and belief.
DATE ____________
Project Manager
12. Legal Review and Concurrence: I hereby determine that the information herein is legally sufficient, and I concur with the sole source procurement.
DATE _____________
Office of Counsel
13. Contracting Officer Certification & Fair and Reasonable Cost Determination: I certify that this justification is accurate and complete to the best of my knowledge and belief.
I hereby determine that an anticipated cost for Monaco Enterprises Incorporated (MEI) fire monitoring system in the firm fixed price construction contract for the Child Development Center at Scott Air Force Base, Illinois will be fair and reasonable based upon the estimate outlined in paragraph 3. At time of evaluating proposal price, the overall proposed price will be evaluated for fair and reasonableness. I recommend this approach to the prompt attainment of services for the upcoming construction.
DATE _____________